Trans Mountain pipeline

Last updated

Trans Mountain Pipeline (TMPL)
TransMountainPipeline.svg
Trans Mountain pipeline route from Edmonton to Burnaby
Location
CountryCanada
Province Alberta and British Columbia
From Edmonton, Alberta
To Burnaby, British Columbia
General information
TypeMultiple product pipelines: crude oil, refined petroleum products such as jet fuel, gasoline, diesel [1]
StatusOperational – twinning completed May 1, 2024
OwnerTrans Mountain Corporation (TMC) (Canada Development Investment Corporation)
Commissioned1951
Technical information
Length1,150 km (710 mi)
Diameter610 mm (24 in)

The Trans Mountain Pipeline System, or simply the Trans Mountain Pipeline (TMPL), is a multiple product pipeline system that carries crude and refined products from Edmonton, Alberta, to the coast of British Columbia, Canada. [1] [2]

Contents

The corporation was created in 1951, construction began in 1952, and operations commenced in 1953. It is the only pipeline to run between these two areas.

The construction of a second pipeline between Hinton, Alberta, and Hargreaves, British Columbia, running adjacent to the existing line, was completed in 2008. [3]

In 2013, a project to twin the existing Trans Mountain pipelinethe Trans Mountain Expansion Projectwas proposed to the Canadian National Energy Board. [4] The project was 98% complete, as of 23 January 2024, [5] and began operations on 1 May 2024. [6] The expansion, which runs roughly parallel to the existing pipeline, increased capacity from 300,000 to 890,000 barrels per day (48,000–141,000 m3/d), at a cost of C$34 billion. [7]

The Trans Mountain Expansion Project was controversial due to its potential environmental impact. It faced legal challenges, as well as challenges from environmentalists and First Nations groups on the grounds of inadequate consultation of the pipeline route passing through unceded indigenous land. A Supreme Court decision on July 2, 2020, that rejected the appeals made by First Nations and environmental groups, "[brought] an end to the years-long legal challenge". [8]

On August 31, 2018, the Government of Canada purchased the pipeline for $4.7 billion [9] from Kinder Morgan through the creation of the Trans Mountain Corporation (TMC), in order to "keep the project alive". [10] TMC is a Crown corporation, a subsidiary of the Canada Development Investment Corporation (CDEV). [11] Until the purchase by CDEV, the Trans Mountain Pipeline was owned by the Houston, Texas–based pipeline operator's Canadian division.

History

In February 1947, large oil deposits were discovered near Leduc, Alberta. The idea for a pipeline from Alberta to British Columbia quickly emerged, driven by the growing demand for oil both in Asia and on the west coast of Canada and the United States. One element seen as a benefit to the project were defence implications, with availability of oil infrastructure being beneficial to both the Canadian and US militaries. [12]

On March 21, 1951, the Trans Mountain Pipeline Company Trans Mountain was created when the Canadian Parliament granted the company a charter under a special act of Parliament. [13] The proposal for the pipeline was immediately submitted to the Board of Transport Commissioners and was approved. Construction began in February 1952 and the final section was welded in place near Aldergrove, British Columbia, on October 17, 1952. [13]

According to a 2019 JWN Energy seriesInside Canada's Pipeline Industryby former editor of Oilweek, Gordon Jaremko, both the Board approval and the construction of the 1,150-kilometre (710 mi) pipeline were sped up as concerns about the Korean War mounted. The governments considered the TMPL to be a strategic way of reducing reliance on oil tankers, made vulnerable under threats of potential attack on the west coast of North America. [14]

Canadian Bechtel Ltd. was responsible for engineering, design, and construction of the project. Ownership of the company was split between Canadian Bechtel Ltd. and Standard Oil.[ clarification needed ]

In August 1953, crude oil from Edmonton, Alberta, began flowing to refineries in the Vancouver area and the northwestern U.S. through TMPL. [14]

The total cost of TMPL was $93 million, according to then Premier of British Columbia W. A. C. Bennett at the opening ceremony. [15] [16]

Prior to 1983, the only product TMPL carried was crude oil to supply refineries in the Vancouver area and to the state of Washington. [1]

Shift from single to multiple products pipelines

In 1983, Trans Mountain began experiments to shift from single- to multiple-product pipelines to increase efficiency and to become more competitive. [1] By 1985, TMPL regularly carried refined-products 820 kilometres (510 mi) from Edmonton to Kamloops, British Columbia. This had extended to Vancouver by 1993. [1]

A 1993 report said that the TMPL was the "only major system in the world" at that time, transporting both crude oil and refined petroleum products" in a single pipeline. [17] [1]

By 1998, TMPL made regular shipments to Vancouver of refined petroleum products "including jet fuel, gasoline (unleaded and premium unleaded), diesel (regular sulfur, low sulfur, and low temperature), methyl tertiary butyl ether (MTBE), and crude-oil (light sweet, light sour, and heavy)". [1]

In 2004, Kinder Morgan began the process to add a second pipeline, running parallel to the first, for the portion running between Hinton, Alberta, and Hargreaves, British Columbia. This required two more pumping stations – the Wolf Pump Station, near Niton Junction, Alberta, and the Chappel Pump Station, near Pyramid Creek Falls Provincial Park, British Columbia. This increased capacity by 40,000 barrels per day (6,400 m3/d), (from 260,000 to 300,000 barrels per day (41,000 to 48,000 m3/d)). [3]

TMPL and oil refineries

Shell, Petro-Canada and Imperial closed refineries in British Columbia in the 1990s and expanded their refineries in the Edmonton area following the TMPL construction. [18] TMPL had the capacity to carry refined products, as well as crude oil via the batch system. [18] According to a 2016 Oil Sands Magazine article, this resulted in the conversion of existing refineries along the TMPL route into storage and distribution facilities and terminals. [18] In 1983, Kamloops' Royalite Refinery, was shut down. [18] In 1993, two refineries were closedShell's in North Burnaby a large Vancouver neighbourhoodand Petro-Canada's in Port Coquitlam 27 km (17 mi) east of Vancouverwere closed. [18] In 1995, Imperial Oil closed their refinery in Port Moody a city that is part of the Metro Vancouver Regional District. [18] After TMX opened in 2024, oil refineries complained about poor oil quality. [19]

Spill history

As of 2017, TMPL had reported approximately 84 spills to Canada's National Energy Board since 1961. [20] [21] Although a majority occurred at contained zones such as pumping stations, and a majority were below the mandatory reporting threshold of 1.5 cubic metres, there were some significant spill events.

In Abbotsford in 2005, a ruptured pipeline dumped 210 m3 (1,300 bbl) of crude oil. The company attributed the accident to activity on a neighbouring property. [22] In 2007, in Burnaby, a contractor working on a sewage project for the City of Burnaby ruptured a pipeline, causing spillage of 224–234 m3 (1,410–1,470 bbl) of crude oil. Some of it flowed into Burrard Inlet via the Burnaby storm sewer system. Most of it was recovered. Eleven houses were sprayed with oil, and about 225–250 residents were evacuated or left voluntarily. Cleanup took more than a year. [23] [24] [25] [26] In 2009, in Burnaby 305 m3 (1,920 bbl) of crude oil were released from a tank at the Trans Mountain Burnaby Terminal. Most of it flowed into a containment area. [27] In Sumas in 2012 90 m3 (570 bbl) of light crude oil leaked from a Sumas Mountain holding tank. All of it flowed into a containment area. [28] In 2020, in Sumas, 190.0 m3 (1,195 bbl) of light crude leaked from small pipe connected to mainline. Trans Mountain reported on June 14 that the spill was contained on the property and that groundwater was monitored for contamination. [29]

Trans Mountain Expansion Project

On June 18, 2013, Kinder Morgan filed an application with the National Energy Board pursuant to Part III of the National Energy Board Act [4] to build a second pipeline under the Trans Mountain Pipeline Expansion Project. [30] The second pipeline was to run roughly parallel to the existing pipeline, between Edmonton and Burnaby (east of Vancouver) and to be used to transport diluted bitumen, also known as dilbit. The additional pipeline requires 12 new pumping stations. The proposed expansion, with 980 kilometres (610 mi) of pipe, would increase the system's capacity from 300,000 to 890,000 barrels per day (48,000 to 141,000 m3/d). In 2013, the cost of completing the connection between Strathcona County, Alberta, and Burnaby, British Columbia was estimated at $6.8 billion. [31]

Trans Mountain Pipeline, in green, with other Canadian Energy Regulator managed pipelines. Petroleum Infrastructure Alberta CER.svg
Trans Mountain Pipeline, in green, with other Canadian Energy Regulator managed pipelines.

Kinder Morgan had the support at that time of several large petroleum industry customers for this expansion (BP Canada Energy Trading Co., Canadian Natural Resources, Canadian Oil Sands Ltd., Cenovus Energy Inc., Devon Canada Corp., Husky Energy Marketing Inc., Imperial Oil Ltd., Nexen Marketing Inc., Statoil Canada Ltd., Suncor Energy Marketing Inc., Suncor Energy Products Partnership, Tesoro Refining & Marketing Co, and Total E&P Canada Ltd). [32]

In 2016, the B.C. government said it did not support Trans Mountain, partly because Kinder Morgan had not provided enough information about its proposed spill prevention and spill clean-up program. [33] On November 29, 2016, the federal cabinet approved the expansion project, announcing that the approval was "subject to 157 binding conditions that will address potential Indigenous, socio-economic and environmental impacts, including project engineering, safety and emergency preparedness." [34]

On January 11, 2017, B.C. Premier Christy Clark announced British Columbia's support for the expansion of the Trans Mountain pipeline, saying the project met her government's five conditions for approval and included a revenue-sharing agreement worth up to $1 billion. [35]

In 2018, the federal government created a Crown corporation, the Trans Mountain Corporation (TMC), when it bought the pipeline from the Houston-based Kinder Morgan for C$4.5 billion. [10] [36] The purchase had been announced by the federal government in May 2018. At that time, the government said it would seek outside investors to complete the expansion. These investors would also be indemnified for any delays induced by provincial or municipal governments.

In 2020, three insurance companies that had previously supported the project withdrew their support, including Zurich Insurance Group, the leading insurer. The company that is advancing the project said that it still had enough insurance coverage. [37]

By February 2020, the assessment for the completion of the project was estimated at $12.6 billion, an increase of the previous estimate of $7.4 billion. [36] The cost increase was the result of rising costs of "labour, steel, and land". [38]

In a September 2020 interview with the Canadian Press, TMC's CEO Ian Anderson said that the expansion was on schedule despite the $5.2-billion increase in its cost. [39] Anderson cited other challenges to construction including the COVID-19 pandemic, the slump in the demand for fuel, which contributes to the slump in the price of oil, [40] and the protests by opponents to the expansion. [39]

By February 2022, TMC said that costs had increased by 70%, from $12.6 billion to $21.4 billion. [10] Faced with the federal government's costly COVID-19 response, Finance Minister Chrystia Freeland, said this new funding for the pipeline was not part of the federal government's commitment. [10] The status of the company changed to a non-agent Crown corporation on April 29, 2022, which meant that it was able to access financing from third-party lenders. [41] In March 2023, it was announced that the cost has again increased to $30.9 billion. [42]

As of April 2022, construction had reached the half-way mark. [43] The company said in their November 2022 third-quarter report that expansion would be mechanically complete by the third quarter of 2023 and the commercial service would be operational in the fourth quarter of 2023. [44] [41]

According to a January 2023 statement from the company, more than 700 kilometres (430 mi) of pipe was already in place representing 75% of the entire project. [41]

On January 3, 2024, Trans Mountain Corp said in a 33-page filing that it planned to begin line fill in March or May, depending on the diameter of pipe to be used and assuming no new problems. [45] The line fill represents the final step before the pipeline goes into service. [45] According to the filing, the pipeline can enter service within one month of mechanical completion preceding line fill. [45]

On May 1, 2024, the long-delayed Trans Mountain pipeline expansion officially begun operations after 12 years and C$34 billion in costs. The project nearly tripled Canada's oil export capacity to 890,000 barrels per day, enabling better access to global markets and boosting crude prices. [6]

Debate

The expansion project faced criticism, particularly from environmentalists and First Nations groups. To reach the terminus, tankers have to pass through a very narrow channel of shallow water from the open sea, still putting leaks at risk due to vehicle crashes. [46] Environmentalists expressed concern about the heightened risk of an oil spill in the Burrard Inlet resulting from the expansion, which entailed the obstruction of 30% of the inlet and a seven-fold increase in tanker traffic, according to Stand.earth, formerly ForestEthics. [47]

Those who supported the expansion said that it would create jobs and that it had a lower risk of spilling oil than transporting oil by rail, which pipeline proponents said would otherwise have to be used. [48]

A 2014 study by Simon Fraser University claimed that Kinder Morgan overestimated the economic benefits of the pipeline expansion. [49] From 2008 through 2018, Western Canadian Select (WCS), Canada's benchmark for heavy crude oil sold at an average discount of US$17 against the benchmark for light oil, West Texas Intermediate (WTI). This widened to a record US$50 in the fall of 2018 with the price of WCS hitting a record low of less than US$14 a barrel. [50] [51]

Despite federal government approval, seven Federal Court challenges were filed by the municipalities of Vancouver and Burnaby, and the Tsleil-Waututh, Squamish, Kwantlen, and Coldwater First Nations. [52] In November 2017, Minister of Natural Resources Jim Carr stated that the federal government had sent a letter in support of a dispute resolution process to the National Energy Board to expedite any future disputes over provincial or municipal permits impeding the expansion. BC Environmental Minister George Heyman accused the federal government of interfering with an independent review of the project, arguing that "it's both a highly unusual and a highly troubling intrusion on a province's right to enforce its own permits, its own regulations and the interests of its own citizens". [53] [54]

On January 30, 2018, the B.C. government proposed a restriction on increases to the amount of diluted bitumen that could be imported into the province from Alberta, until the completion of studies on whether potential spillage could be mitigated. The province also announced an intent to consult with local communities and First Nations among others. Alberta premier Rachel Notley criticized the proposal as being a stalling tactic on Trans Mountain expansion, explaining that "the B.C. government has every right to consult on whatever it pleases with its citizens. It does not have the right to rewrite our constitution and assume powers for itself that it does not have." On February 6, 2018, Notley ordered the Alberta Gaming and Liquor Commission to cease future imports of British Columbia wine as a retaliatory sanction over these moves. [55] [56] The wine sanctions were lifted on February 22, 2018. [57]

On April 8, 2018, Kinder Morgan suspended "non-essential" activities relating to the pipeline, as the company did not want to "put [its] shareholders at risk on the remaining project spend". The company stated that it would attempt to reach agreements on a funding plan with stakeholders by May 31. [58] On April 16, the Alberta government introduced the Preserving Canada's Economic Prosperity Act, which would give the Minister of Energy power to regulate the export of crude oil, natural gas, or refined fuel from Alberta. The act could be used to effectively ban the export of Alberta gas to British Columbia. As such, B.C. Attorney General David Eby threatened to sue Alberta over the act, as he considered it unconstitutional, and stated that it could have a further impact on gasoline prices in the province. [59] [60] [61]

On May 29, 2018, the federal government announced its intent to acquire the Trans Mountain Pipeline from Kinder Morgan for $4.5 billion. The government did not intend to remain the permanent owner of the pipeline, as it planned to seek outside investors to finance the twinning project. The government could not find a buyer before the consummation of the purchase, and it carried out the purchase via a crown corporation, and operated it in the meantime. [62] [63]

Critics[ who? ] of the expansion argued[ where? ] that the purchase was a taxpayer-funded bailout of the project. B.C. Premier John Horgan stated that the sale would not affect the provincial government's ongoing efforts to block the pipeline expansion, stating that "rather than go to the court to determine jurisdictions, they're making financial decisions that affect taxpayers and they'll have to be accountable for that". Stewart Phillip, president of the Union of British Columbia Indian Chiefs, stated that the union was "absolutely shocked and appalled that Canada is willingly investing taxpayers' money in such a highly controversial fossil fuel expansion project". [64]

On August 30, 2018, Kinder Morgan Canada's shareholders voted to approve the sale of the pipeline to the federal government. [65] However, the same day, the Federal Court of Appeal overturned the government's approval of the expansion project, citing that it did not sufficiently fulfill its constitutional duties to consult local First Nations groups, [66] [67] and because it lacked an environmental assessment of increased tanker traffic on orcas in the Salish Sea [68] off the BC coast. [69] On August 31, Trudeau said the federal government remained committed to the pipeline expansion project in spite of this setback. [70] [71] In response to the approval being overturned, Premier Rachel Notley announced that Alberta would pull out of the national carbon price and called for an appeal to the Supreme Court of the Federal Court's August 30 decision. [71]

Protests

The expansion project faced opposition from civic governments, First Nations, environmentally concerned citizens, and others. In September 2012, Tsleil-Waututh leaders had hoped to shut down the project altogether. [72]

In November 2014, opponents of the pipeline expansion camped in Burnaby Mountain Park to block pipeline construction crews, and over 100 were arrested. [39] Members of the Squamish and Tsleil-Waututh First Nations in British Columbia paddled canoes on Burrard Inlet, in North Vancouver, to Kinder Morgan's Burnaby Terminal for a ceremony to protest the expansion of the Trans Mountain pipeline. [72] In a 2020 Global News interview, with the pipeline expansion work underway again, Grand Chief Stewart Phillip, president of the Union of BC Indian Chiefs, said that he expected that there would be more "Burnaby Mountain-style" protests. [39]

Protests took place in Vancouver to stop work on the pipeline on September 19, 2017.

A protester at a rally in 2017 Protester holding sign stating No Pipeline, No Consent, during a Kinder Morgan Pipeline Rally on September 9th, 2017 in Vancouver, Canada.jpg
A protester at a rally in 2017
Burnaby Mayor Derek Corrigan addresses a protest in 2014 STOP KINDER MORGAN Burnaby Mayor.jpg
Burnaby Mayor Derek Corrigan addresses a protest in 2014

Burnaby Mayor Derek Corrigan addressed the crowd at a Stop Kinder Morgan protest rally in Burnaby Mountain Park. By 2018, rallies opposing the projects had been organized across Canada. Organizations including LeadNow and the Dogwood Initiative also opposed the project and organized protests. [73] [74]

The RCMP contained the protests on Burnaby Mountain.

In July 2018 activists blocked an oil tanker from the Ironworkers' Memorial Bridge in Vancouver. [75]

In September 2021 a treetop camp in the Brunette River Conservation Area was dismantled by RCMP following a court injunction. The protest camp had been occupied by protesters since December 2020, and a leader of the protest claimed further actions would be planned. [76]

Secwépemc opposition

According to Aboriginal Peoples Television Network, since 2013 Secwépemc community members, primarily women, have been defending their traditional land (known as Secwepemcul’ecw) against the proposed expansion of the pipeline, asserting that the expansion was approved without sufficient consultation. The expansion would cross 518 km of Secwépemc territory. The land defenders (as they call themselves; some media refers to them as protesters and activists) are concerned about the damage to the land and water the pipeline passes through, in particular the disruption of salmon populations, violation of the Declaration on the Rights of Indigenous Peoples, and violation of traditional Secwépemc law, founded by the Okanagan Shuswap Confederacy. Their claim is that the First Nation band governments only have jurisdiction through Canadian law on their reserves, whereas traditional Secwépemc leadership retains sovereignty over Secwepemcul’ecw. [77]

Since July 2018, a Secwépemc protest camp has been occupied just outside of Blue River, British Columbia, where there are plans to drill under the river. [78] That camp, established by a group known as the Tiny House Warriors, is near a planned work camp. [79] The establishment of the camp led Kúkpi7 (Chief) Rosanne Casimir of Tk’emlúps te Secwépemc First Nation (TteS), along with Chief Shelly Loring of Simpcw First Nation to issue a joint statement asking the Tiny House Warriors to stand down, claiming it was the Warriors violating Secwépemc law. [80]

In early September 2020, protester Loralie Dick chained herself to the TMX worksite in Kamloops before being arrested by the RCMP for violating a B.C. Supreme Court injunction from 2018 that barred land defenders from blocking work. [78] [80]

In early October 2020, a protest camp was set up along the Thompson River, along the proposed route of the expansion. One of the residents of the Thompson River camp was Secwépemc matriarch Miranda Dick, who told reporters there were an average of 20 people at the camp as of October 5th. At the time it was set up, Kúkpi7 Casimir said she had no issue with the protest camp, so long as health and safety guidelines were followed. [81] On October 9, in response to TMX workers being seen surveying in preparation to drill under the river, the camp was moved directly in the way of the expansion. On October 10, the Secwépemc delivered a cease and desist notice to TMX for the second time. [82] On October 11 it was moved again due to a chemical leak in the river. By October 15, the RCMP had begun arresting people connected to the camp, including Hereditary Chief Segwses, Loralie Dick, April Thomas, Billie Pierre and Romilly Cavanaugh. [78] In February 2020, Segwses and his daughter gave themselves up for arrest for participating in the 2020 Canadian pipeline and railway protests, in order to prevent the RCMP from snuffing a sacred fire as well as to prevent the escalation of a confrontation. [82]

On October 17, 2020, Dick cut her hair in ceremony before the gates of the expansion project. Soon after the ceremony, she and four other women were arrested by RCMP officers. [77] In a statement released the following day, TteS Kúkpi7 Rosanne Casimir thanked the RCMP for maintaining peace and order and stated that she and the elected council did not endorse the protesters. TteS is one of several First Nations bands that have signed agreements with Trans Mountain. Casimir's statement asserted that the council "[had] not sold or ceded or given anything away" but that "[they had] upheld [their] jurisdictional rights." [83]

Phase III consultations

In response to the Federal Court's overturning the federal authorization of Trans Mountain, the Canadian government "reinitiated Phase III consultations" with Natural Resources Canada as lead and Justice Frank Iacobucci appointed by the government to oversee consultations. An NEB panel heard three weeks of Indigenous traditional testimony with 117 Indigenous groups impacted by the pipeline, beginning on November 19, [68] with sessions in Calgary, Victoria and Nanaimo. [84]

The Trudeau government restricted the Phase III hearings in terms of time and scope. [68] The government gave the NEB a "tight timeline" with a final report due on February 22, 2019. [68] The hearings were also restricted by the NEB panel to investigate "new information" as it related to the impact of increased oil tanker traffic to and from the Westridge Marine Terminal in Burrard Inlet, Burnaby, to Canada's 12-nautical-mile territorial waters. The environmental concern in this area included the Salish Sea's southern resident killer whales' (SRKW) prime Chinook salmon feeding ground. By November 2018, there were only 74 SRKW left. [68] Noise and pollution from marine vessels along with the diminishing stocks of salmon  their prime source of food  contributed to the whales' declining numbers. [68]

Hearings in the form of pipeline roundtable meetings with Trans Mountain representative and indigenous groups took place in Calgary in November, and in Kamloops and Nanaimo in December, with the summary expected in January. [69] [84]

Government of Canada 2019 approval of TMX

On June 18, 2019, the federal government through the Governor in Council confirmed the approval of federally-owned TMX project. The twinned pipeline will have the capacity to carry almost 1 million barrels per day (160,000 m3/d) from Alberta to the coast of British Columbia. [85] The National Energy Board, Prime Minister Justin Trudeau and his cabinet agreed that the TMX was in the "national interest" as it would add "tens of billions of dollars" to government revenue as well as sustaining thousands of jobs. [85] Both the NEB and the federal government acknowledged that there was a possibility that TMX could "damage the environment and marine life", but the benefits outweighed the risks. [85]

Trudeau said that the revenue from TMC, which was estimated at $500 million annually just in federal corporate taxes, would be invested in "unspecified clean energy projects". [85] [4] [86]

In their letter sent to both Trans Mountain and the lawyers representing the Tsleil-Waututh First Nation, the NEB wrote that within the context of "substantial" and "significant" interest and participation on the part of Indigenous peoples and the general public, including the August 30, 2018, decision in Tsleil-Waututh Nation v. Canada, [87] the NEB's regulatory oversight processes for the next phases of the Trans Mountain Expansion Project "lifecycle", which include "detailed route approvals", such as potential "routing and non-routing", would include a public comment period. [87]

SCC 2020 decisions dismissing appeals challenging TMX

By December 2019, the legal basis of the expansion was challenged in Canada's Federal Court of Appeal as politicians, environmentalists and some Indigenous groups returned to the courts and pressed the issue of Aboriginal title. [88] Some Indigenous groups, such as the Kehewin Cree Nation, T'Sou-ke Nation, Frog Lake First Nation, Scia'new First Nation, Simpcw First Nation, Pellt'iq't First Nation and Squiala First Nation formed the Western Indigenous Pipeline Group (WIPG) and have sanctioned the project for ownership stakes. Others, like the Coldwater Indian Band, have unsettled issues. These issues include disputes over the compensation from the institution of the first pipeline right-of-way in the 1950s, as well as future water supply risks that they would assume.

In February 2020, a Federal Court of Appeal denied the request by environment and Indigenous groups to "consider whether there had been sufficient consultation". [8]

On March 5, 2020, the Supreme Court of Canada "declined to hear" a set of five legal challenges to the project's approval. These originated from First Nations groups, environmental organization, and teenage activists. [89]

On July 2, 2020, the Supreme Court rejected appeals by the Squamish Nation, Tsleil-Waututh Nation, and Coldwater Indian Band and others challenging federal approval of the Trans Mountain pipeline expansion project, "bringing an end to the years-long legal challenge". [8]

See also

Notes

    Related Research Articles

    Enbridge Inc. is a multinational pipeline and energy company headquartered in Calgary, Alberta, Canada. Enbridge owns and operates pipelines throughout Canada and the United States, transporting crude oil, natural gas, and natural gas liquids, and also generates renewable energy. Enbridge's pipeline system is the longest in North America and the largest oil export pipeline network in the world. Its crude oil system consists of 28,661 kilometres of pipelines. Its 38,300 kilometre natural gas pipeline system connects multiple Canadian provinces, several US states, and the Gulf of Mexico. The company was formed by Imperial Oil in 1949 as the Interprovincial Pipe Line Company Limited to transport Alberta oil to refineries. Over time, it has grown through acquisition of other existing pipeline companies and the expansion of their projects.

    Kinder Morgan Energy Partners LP (NYSE: KMI) (KMEP) is a subsidiary of Kinder Morgan, Inc. The company, which is classified as an oil and gas master limited partnership (MLP), owns or operates petroleum product, natural gas, and carbon dioxide pipelines, related storage facilities, terminals, power plants and retail natural gas in the United States and Canada.

    <span class="mw-page-title-main">TC Energy</span> Canadian energy company

    TC Energy Corporation is a major North American energy company, based in the TC Energy Tower building in Calgary, Alberta, Canada, that develops and operates energy infrastructure in Canada, the United States, and Mexico. The company operates three core businesses: Natural Gas Pipelines, Liquids Pipelines and Energy.

    <span class="mw-page-title-main">Canadian Association of Petroleum Producers</span> Canadian oil group

    The Canadian Association of Petroleum Producers (CAPP), with its head office in Calgary, Alberta, is a lobby group that represents the upstream Canadian oil and natural gas industry. CAPP's members produce "90% of Canada's natural gas and crude oil" and "are an important part of a national industry with revenues of about $100 billion-a-year ."

    <span class="mw-page-title-main">Kinder Morgan</span> Energy Transportation Company

    Kinder Morgan, Inc. is one of the largest energy infrastructure companies in North America. The company specializes in owning and controlling oil and gas pipelines and terminals.

    <span class="mw-page-title-main">Petroleum industry in Canada</span>

    Petroleum production in Canada is a major industry which is important to the overall economy of North America. Canada has the third largest oil reserves in the world and is the world's fourth largest oil producer and fourth largest oil exporter. In 2019 it produced an average of 750,000 cubic metres per day (4.7 Mbbl/d) of crude oil and equivalent. Of that amount, 64% was upgraded from unconventional oil sands, and the remainder light crude oil, heavy crude oil and natural-gas condensate. Most of the Canadian petroleum production is exported, approximately 600,000 cubic metres per day (3.8 Mbbl/d) in 2019, with 98% of the exports going to the United States. Canada is by far the largest single source of oil imports to the United States, providing 43% of US crude oil imports in 2015.

    <span class="mw-page-title-main">Keystone Pipeline</span> Oil pipeline in North America

    The Keystone Pipeline System is an oil pipeline system in Canada and the United States, commissioned in 2010 and owned by TC Energy and, as of March 2020, the Government of Alberta. It runs from the Western Canadian Sedimentary Basin in Alberta to refineries in Illinois and Texas, and also to oil tank farms and an oil pipeline distribution center in Cushing, Oklahoma.

    Ecojustice Canada, is a Canadian non-profit environmental law organization that provides funding to lawyers to use litigation to defend and protect the environment. Ecojustice is Canada's largest environmental law charity.

    Dogwood BC is a Canadian non-profit public interest group based in Victoria, British Columbia. The organization works to increase the power of British Columbians over government decision-making. They were instrumental in the fight against Enbridge's Northern Gateway pipeline, introducing a tanker moratorium on BC's north coast and the province's campaign finance reform. The organization currently works to stop Kinder Morgan's Trans Mountain tanker and pipeline expansion in BC, ban U.S. thermal coal exports through BC ports and restore accountability and transparency to the province's democracy by calling for a Corruption Inquiry.

    The Enbridge Northern Gateway Pipelines were a planned-but-never-built project for a twin pipeline from Bruderheim, Alberta, to Kitimat, British Columbia. The project was active from the mid-2000s to 2016. The eastbound pipeline would have imported natural gas condensate, and the westbound pipeline would have exported diluted bitumen from the Athabasca oil sands to a marine terminal in Kitimat for transportation to Asian markets via oil tankers. The project would have also included terminal facilities with "integrated marine infrastructure at tidewater to accommodate loading and unloading of oil and condensate tankers, and marine transportation of oil and condensate." The CA$7.9 billion project was first proposed in the mid-2000s but was postponed several times. The project plan was developed by Enbridge Inc., a Canadian crude oil and liquids pipeline and storage company.

    <span class="mw-page-title-main">National Energy Board</span> Former Canadian government agency

    The National Energy Board was an independent economic regulatory agency created in 1959 by the Government of Canada to oversee "international and inter-provincial aspects of the oil, gas and electric utility industries." Its head office was located in Calgary, Alberta.

    <span class="mw-page-title-main">Kennedy Stewart (Canadian politician)</span> Canadian politician and academic

    Edward Charles Kennedy Stewart is a Canadian academic administrator and politician who served as the 40th mayor of Vancouver from 2018 to 2022. He previously was the member of Parliament (MP) for the riding of Burnaby—Douglas (2011–2015) and Burnaby South (2015–2018), serving in the House of Commons as a member of the New Democratic Party (NDP) caucus.

    <span class="mw-page-title-main">Energy East</span> Cancelled Canadian pipeline project

    The Energy East pipeline was a proposed oil pipeline in Canada. It would have delivered diluted bitumen from Western Canada and North Western United States to Eastern Canada, from receipt points in Alberta, Saskatchewan and North Dakota to refineries and port terminals in New Brunswick and possibly Quebec. The TC PipeLines project would have converted about 3,000 kilometres (1,900 mi) of natural gas pipeline, which currently carries natural gas from Alberta to the Ontario-Quebec border, to diluted bitumen transportation. New pipeline, pump stations, and tank facilities also would have been constructed. The CA$12 billion pipeline would have been the longest in North America when complete.

    Washington state has the fifth highest oil refining capacity of any state. As of 2018, there are 5 refineries in Washington state with a joint capacity of 637,700 b/d. They are, in order of greatest b/d capacity, Cherry Point refinery, Puget Sound refinery, Marathon Anacortes refinery, Ferndale refinery and U.S. Oil refinery.

    Kanahus Manuel, or Kanahus Freedom, is an indigenous activist in British Columbia, Canada. She is a birth keeper and a member of the activist group Tiny House Warriors.

    Melina Laboucan-Massimo is a climate justice and Indigenous rights advocate from the Lubicon Cree community of Little Buffalo in northern Alberta, Canada. Growing up with firsthand experience of the effects of oil and gas drilling on local communities, she began advocating for an end to resource extraction in Indigenous territories but shifted focus to supporting a renewable energy transition after a ruptured pipeline spilled approximately 4.5 million litres of oil near Little Buffalo in 2011.

    Pipelines in Canada are important components of energy infrastructure in Canada as the majority of natural gas and oil deposits are located in landlocked Alberta and need to be transported to ports or terminals to access larger markets.

    The Canadian province of Alberta faces a number of environmental issues related to natural resource extraction—including oil and gas industry with its oil sands—endangered species, melting glaciers in banff, floods and droughts, wildfires, and global climate change. While the oil and gas industries generates substantial economic wealth, the Athabasca oil sands, which are situated almost entirely in Alberta, are the "fourth most carbon intensive on the planet behind Algeria, Venezuela and Cameroon" according to an August 8, 2018 article in the American Association for the Advancement of Science's journal Science. This article details some of the environmental issues including past ecological disasters in Alberta and describes some of the efforts at the municipal, provincial and federal level to mitigate the risks and impacts.

    <span class="mw-page-title-main">Timeline of the petroleum industry in Alberta</span>

    This is a brief timeline covering the history of the petroleum industry Alberta and its predecessor states.

    References

    1. 1 2 3 4 5 6 7 Baum, Judy S.; Marzocco, Ken E.; Hansen, Larry I. (October 5, 1998). "Batching, treating keys to moving refined products in crude-oil line". Oil&Gas Journal. 96 (40): 49. Use of a crude-oil pipeline to transport refined petroleum products can be successful and cost-effective, as the experience of one western Canadian pipeline makes clear Via Gale and Wikipedia Library
    2. "Who We Are". Trans Mountain. n.d. Retrieved January 13, 2022.
    3. 1 2 "Trans Mountain Anchor Loop". Transmountain. Archived from the original on June 16, 2016. Retrieved January 12, 2023.
    4. 1 2 3 Government of Canada (June 18, 2019), "The Government of Canada has approved the Trans Mountain Expansion Project", National Energy Board (NEB), retrieved June 19, 2019
    5. Varcoe, Chris (January 23, 2024). "Varcoe: 'A long time coming': Trans Mountain pipeline expansion aims to be finished in the coming weeks". Calgary Herald.
    6. 1 2 Williams, Nia (May 2, 2024). "Canada's long-delayed Trans Mountain oil pipeline starts operations". Reuters.
    7. "Trans Mountain expansion project's latest cost estimate has climbed 10%, regulatory filing shows". The Globe and Mail. February 28, 2024.
    8. 1 2 3 "Supreme Court dismisses First Nations' challenge against Trans Mountain pipeline". CBC News. July 2, 2020. Retrieved January 12, 2022.
    9. Forester, Brett (August 3, 2023). "RCMP cited Standing Rock protests as 'evidence' to create controversial B.C. unit". www.cbc.ca.
    10. 1 2 3 4 Carmichael, Kevin (February 18, 2022). "Chrystia Freeland closes the door on new funding for Trans Mountain as project costs surge". Financial Post. Retrieved January 12, 2023. Construction costs have surged by some 70 per cent
    11. "Trans Mountain - Trans Mountain Corporation: Who We Are".
    12. Kehraj, Sean (n.d.). "Historical Background Report: Trans Mountain Pipeline, 1947-2013" (PDF). Retrieved June 23, 2024.
    13. 1 2 "Our History". Trans Mountain. n.d. Retrieved January 15, 2023.
    14. 1 2 Jaremko, Gordon (March 19, 2019). "Canada's history of pipeline challenges is longer than you might think". JWN Energy. Retrieved January 16, 2023.
    15. Richard Finnie (director) (June 20, 2010) [1953]. Oil across the Rockies Part 1 (video) (video). Richard Finnie of Canadian Bechtel Limited. Event occurs at 9 min 42 sec. Retrieved January 16, 2023 via YouTube.
    16. Richard Finnie (director) (June 20, 2010) [1953]. Oil across the Rockies Part 4 (video) (video). Richard Finnie of Canadian Bechtel Limited. Event occurs at 9.44 min. Retrieved January 16, 2023 via YouTube.
    17. Mortimer, D. (1993). Receipt Piping Hydraulic Study private report prepared for Petro-Canada, Burrard Products Terminal, Port Moody, B.C. (Report).
    18. 1 2 3 4 5 6 "Why Vancouver Desperately Needs A New Oil Refinery Investing". Oil Sands Magazine. March 3, 2016. Retrieved January 16, 2023.
    19. "U.S. oil refiners raise concerns about quality of crude shipped on Trans Mountain pipeline expansion". The Globe and Mail. June 12, 2024.
    20. "Spill History". www.transmountain.com. June 27, 2017.
    21. "Releases Reported by Trans Mountain - 1961-2016" (PDF). Transmountain. August 31, 2016. Archived from the original (PDF) on December 21, 2016. Retrieved December 8, 2016.
    22. "Abbotsford - Sumas Facility: Ward Road Spill". Transmountain. Archived from the original on December 1, 2016. Retrieved December 1, 2016.
    23. "Westridge 2007 spill". Transmountain. Archived from the original on December 1, 2016. Retrieved December 1, 2016.
    24. "Pipeline Investigation Report P07H0040". Transportation Safety Board of Canada. December 23, 2008. Archived from the original on June 13, 2017. Retrieved June 1, 2017.
    25. Granger, Grant (July 21, 2017). "The day oil rained down on Burnaby".
    26. "3 companies plead guilty to Burnaby oil spill - CBC News".
    27. "Burnaby Tank 82 2009 Spill". Transmountain. Archived from the original on December 1, 2016. Retrieved December 1, 2016.
    28. "Abbotsford - Sumas Facility: Tank 121 2012 Spill". Transmountain. Archived from the original on December 1, 2016. Retrieved December 1, 2016.
    29. "Trans Mountain Pipeline spill in Abbotsford estimated at up to 190,000 litres of crude oil". CBC News. June 14, 2020. Retrieved June 15, 2020.
    30. "About Us". Trans Mountain. Archived from the original on September 28, 2015. Retrieved September 27, 2015.
    31. "Trans Mountain Proposed Expansion". Trans Mountain. 2013. Archived from the original on April 23, 2016. Retrieved May 16, 2016.
    32. "Expansion Project". www.transmountain.com. June 21, 2017. Retrieved January 23, 2021.
    33. "Trans Mountain pipeline expansion not supported by B.C. government". Transmountain. CBC News. January 11, 2016. Archived from the original on December 7, 2016. Retrieved December 8, 2016.
    34. "Government of Canada announces pipeline plan that will protect the environment and grow the economy" (Press release). Government of Canada. November 29, 2016. Archived from the original on December 1, 2016. Retrieved December 8, 2016.
    35. "B.C. approves Trans Mountain pipeline expansion - The Star". The Toronto Star. January 11, 2017.
    36. 1 2 "TMX cost balloons to $12.6B". Global News. February 7, 2020. Retrieved January 12, 2023.
    37. Rosane, Olivia (July 23, 2020). "Trans Mountain Pipeline's Lead Insurer Zurich Drops Coverage". Ecowatch. Retrieved July 24, 2020.
    38. Crawford, Tiffany (February 7, 2020). "Cost of Trans Mountain pipeline expansion project in B.C. soars". Vancouver Sun. Retrieved January 12, 2023.
    39. 1 2 3 4 Healing, Dan (September 15, 2020). "Trans Mountain pipeline expansion on schedule, on budget: CEO". Global News via Canadian Press. Retrieved October 26, 2020.
    40. Luz, Andres Guerra (October 21, 2020). "Oil Prices Slump on US Fuel Supply Build". Bloomberg Rigzone. Retrieved October 26, 2020.
    41. 1 2 3 Franklin, Michael (January 12, 2023). "Trans Mountain expansion on track, despite comments from Alberta premier". CTV News. Calgary. Retrieved January 12, 2023.
    42. "Trans Mountain pipeline expansion costs surge 44% to $30.9 billion". financialpost.com. Retrieved March 13, 2023.
    43. "Trans Mountain says expansion project is now 50% complete". April 19, 2022.
    44. "Trans Mountain Corporation Releases Third Quarter 2022 Results". Trans Mountain. November 29, 2022. Retrieved January 12, 2023.
    45. 1 2 3 Nickel, Rod (January 3, 2024). "Canada's long-delayed Trans Mountain pipeline plans line fill for March or May".
    46. "What the Trans Mountain pipeline will mean for B.C.'s coast". The Globe and Mail. 2017. Retrieved August 30, 2018.
    47. "Trans Mountain Pipeline: The truth about construction" (PDF). Stand.earth. Vancouver, British Columbia. September 2019. Retrieved October 26, 2020.
    48. "Pipelines much safer than shipping oil by rail, Fraser Institute (a private organization funded by the Koch Brothers) study says". Financial Post. Archived from the original on December 2, 2016. Retrieved December 1, 2016.
    49. "Kinder Morgan's Trans Mountain pipeline benefits questioned". CBC News. November 10, 2014. Archived from the original on December 4, 2016. Retrieved May 16, 2016.
    50. Lundy, Matt (November 27, 2018). "Why Alberta's latest oil-price plunge is unprecedented". The Globe and Mail. Retrieved December 28, 2018.
    51. Brusstar, Dan; Putnam, Bluford (December 21, 2015). "U.S. Oil Exports Could Narrow WTI-Brent Spread - CME Group". Archived from the original on July 16, 2016. Retrieved January 8, 2019.
    52. Hoekstra, Gordon (November 26, 2016). "Yes could still be no as Kinder Morgan awaits Trudeau's nod on its multibillion-dollar pipeline expansion". The Vancouver Sun. Archived from the original on December 9, 2016. Retrieved December 8, 2016.
    53. "B.C. slams Ottawa's defence of Trans Mountain pipeline expansion". The Globe and Mail. Retrieved February 9, 2018.
    54. "'No province can impinge on the national interest', federal minister says as pipeline feud simmers". CBC News. Retrieved February 9, 2018.
    55. "B.C. creates more uncertainty for Trans Mountain with bitumen restriction". CBC News. Retrieved February 9, 2018.
    56. "B.C. not backing down on fight against pipeline expansion despite Alberta's threats". CBC News. Retrieved February 9, 2018.
    57. "Cheers! B.C. wine industry celebrates end of Alberta ban". CBC News. Retrieved April 18, 2018.
    58. "Alberta demands 'concrete action' from Ottawa to get Trans Mountain pipeline moving". CBC News. Retrieved April 18, 2018.
    59. "Alberta unveils bill that could wreak havoc on B.C. gas prices in trade war". CBC News. Retrieved April 18, 2018.
    60. "New law would allow Alberta to restrict flow of oil and gas as Trans Mountain battle escalates". Financial Post. April 16, 2018. Retrieved April 18, 2018.
    61. "Alberta premier 'prepared to turn off the taps' now that legislation approved". Edmonton Journal. May 17, 2018. Retrieved August 30, 2018.
    62. "Liberals to buy Trans Mountain pipeline for $4.5B to ensure expansion is built". CBC News. Retrieved May 30, 2018.
    63. "Ottawa is buying Trans Mountain. What does that mean? A guide". The Globe and Mail. Retrieved May 29, 2018.
    64. Weichel, Andrew (May 29, 2018). "B.C. premier, Indigenous groups respond to Trans Mountain purchase". CTV News British Columbia. Retrieved May 30, 2018.
    65. "Kinder Morgan Canada shareholders vote to sell Trans Mountain pipeline to Ottawa with project in limbo". CBC News. Retrieved August 30, 2018.
    66. "Federal Court of Appeal quashes construction approvals for Trans Mountain, leaving project in limbo". CBC News. Retrieved August 30, 2018.
    67. "Trans Mountain pipeline approval quashed by court". Financial Post. August 30, 2018. Retrieved August 30, 2018.
    68. 1 2 3 4 5 6 Hunter, Justine (November 8, 2018). "Limited public access to new hearings on the Trans Mountain pipeline project". The Globe and Mail. Victoria. Retrieved January 8, 2019.
    69. 1 2 Tarasko, Mike (November 20, 2018). "New Trans Mountain hearings begin in Calgary". My McMurray. Calgary. Retrieved January 7, 2019.
    70. "Trudeau committed to building Trans Mountain despite new legal challenges". CBC News. Retrieved September 7, 2018.
    71. 1 2 "Prime Minister says Ottawa still committed to build Trans Mountain pipeline expansion". August 31, 2018. Retrieved September 7, 2018.
    72. 1 2 Keller, James (May 2, 2014). "B.C. First Nation launches legal challenge over Kinder Morgan pipeline". Canadian Televisions News. Archived from the original on May 8, 2014.
    73. Azpiri, Jon (April 25, 2018). "Summer jobs controversy reheats over posting calling to 'stop the Kinder Morgan pipeline'". Global News . Retrieved July 18, 2018.
    74. The Canadian Press (June 4, 2018). "Rallies planned across Canada to protest Kinder Morgan buyout". News 1130 . Retrieved July 18, 2018.
    75. "Pipeline protesters block Trans Mountain oil tanker from Ironworkers Memorial Bridge". July 3, 2018. Retrieved September 7, 2018.
    76. Hernandez, Jon (September 28, 2021). "Treetop camp protesting Trans Mountain pipeline dismantled". CBC News. Retrieved October 7, 2021.
    77. 1 2 Kilawna, Kelsie (October 24, 2020). "Secwépemc Matriarch cuts off her hair in defense of her lands and waters". APTN National News. Retrieved October 26, 2020.
    78. 1 2 3 Laferte, Boston (October 23, 2020). "Secwepemc set up new camp in hopes of halting TMX construction, leads to five arrests". The Martlet. Retrieved October 26, 2020.
    79. Brake, Justin (July 19, 2018). "Tiny House Warriors establish new village to resist pipeline, assert Secwepemc sovereignty". APTN National News. Retrieved October 26, 2020.
    80. 1 2 Rothenburger, Mel (October 24, 2020). "ROTHENBURGER: Protests and arrests were played out in a familiar script". CFJC Today. Retrieved October 26, 2020.
    81. Sperling, Jill (October 5, 2020). "Camp set up near Mission Flats Road in protest of Trans Mountain pipeline expansion project". CFJC Today. Retrieved October 26, 2020.
    82. 1 2 "5 arrested after standing in way of Trans Mountain pipeline construction in B.C. Interior". CBC News. October 16, 2020. Retrieved October 26, 2020.
    83. Kergin, Brendan (October 18, 2020). "Tk'emlups te Secwepemc leadership releases statement on TMX arrests". Castanet.net. Archived from the original on October 23, 2020. Retrieved October 26, 2020.
    84. 1 2 Verenca, Tereza (December 10, 2018). "Three arrested as judge consults with Indigenous groups about Trans Mountain project". Burnaby Now. Retrieved January 7, 2019.
    85. 1 2 3 4 Tasker, John Paul (June 18, 2019). "Trudeau cabinet approves Trans Mountain expansion project". CBC News. Retrieved January 12, 2023. Federal officials say construction of the $7.4 billion pipeline is likely to begin in 2019
    86. "Orders In Council", Government of Canada, no. 2019–0820, June 18, 2019, retrieved June 19, 2019
    87. 1 2 "Trans Mountain Expansion Project Order in Council P.C. 2019-0820 Project update: Letter from NEB to Trans Mountain and Tsleil-Waututh Nation", National Energy Board (NEB), Calgary, Alberta, June 18, 2019, retrieved June 19, 2019
    88. Kestler-D'Amours, Jillian; O'Toole, Megan (December 5, 2019). "Nations divided: mapping Canada's pipeline battle". Al Jazeera website. Retrieved December 5, 2019.
    89. Schmunk, Rhianna. "Supreme Court of Canada will not hear B.C. groups' challenges against Trans Mountain pipeline expansion". CBC News. CBC. Retrieved September 30, 2024.