JP7561402B1 - Document management system, document management method, and document management program - Google Patents

Document management system, document management method, and document management program Download PDF

Info

Publication number
JP7561402B1
JP7561402B1 JP2024034551A JP2024034551A JP7561402B1 JP 7561402 B1 JP7561402 B1 JP 7561402B1 JP 2024034551 A JP2024034551 A JP 2024034551A JP 2024034551 A JP2024034551 A JP 2024034551A JP 7561402 B1 JP7561402 B1 JP 7561402B1
Authority
JP
Japan
Prior art keywords
deliverable
work
document management
user
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2024034551A
Other languages
Japanese (ja)
Inventor
泰宏 前田
孝典 平井
志郎 入嶋
秀貴 小畑
卓人 小林
智也 平井
洋二 井上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2024034551A priority Critical patent/JP7561402B1/en
Application granted granted Critical
Publication of JP7561402B1 publication Critical patent/JP7561402B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

【課題】 本発明は、書類管理システム、書類管理方法、書類管理プログラムに関する。【解決手段】 書類管理システム1は、記憶部と、登録受付部と、を備える。記憶部は、施工現場に関する現場情報と、作業の作業分類を含んだ作業情報と、を対応付けて格納する。登録受付部は、施工現場に対応する複数の作業分類の中から、ユーザに選択された特定作業分類の入力を受け付け、現場情報及び/又は作業情報に基づいて、特定作業分類の作業を担当する担当ユーザを特定する。そして登録受付部は、施工現場と、特定作業分類と、特定された担当ユーザと、を対応付け、担当ユーザが成果物を入力可能な成果物タスクとして記憶部へ登録する。【選択図】図1[Problem] The present invention relates to a document management system, a document management method, and a document management program. [Solution] A document management system 1 includes a memory unit and a registration reception unit. The memory unit stores site information related to a construction site and work information including a work classification of the work, in association with each other. The registration reception unit receives input of a specific work classification selected by a user from among multiple work classifications corresponding to the construction site, and identifies a responsible user who will be in charge of work of the specific work classification based on the site information and/or the work information. The registration reception unit then associates the construction site, the specific work classification, and the identified responsible user, and registers the work in the memory unit as a deliverable task into which the responsible user can input a deliverable. [Selected Figure] Figure 1

Description

本発明は、書類管理システム、書類管理方法、及び書類管理プログラムに関する。 The present invention relates to a document management system, a document management method, and a document management program.

従来から施工現場の作業者は、各施工作業に応じた書類を作成し、当該施工作業の状況について関係者に情報共有や確認作業を行っている。そして昨今では、施工現場における情報共有等について様々な工夫がなされている。 Traditionally, workers at construction sites have prepared documents for each construction task and shared and confirmed information about the status of the construction task with related parties. Recently, however, various ideas have been devised for information sharing at construction sites.

例えば特許文献1には、住宅建設業などにおける作業内容の指示や作業後の確認行為を、作業に関わる人々の役割に応じた各種チェックシートを用いて、タブレット型端末等によりリアルタイムに登録・確認が行え、関係者全員が情報共有出来る遠隔品質管理システムが開示されている。 For example, Patent Document 1 discloses a remote quality control system that enables instructions for work content and post-work confirmation actions in the housing construction industry and the like to be registered and confirmed in real time on a tablet device or the like using various checklists according to the roles of the people involved in the work, allowing all involved parties to share information.

特開2014-157609号公報JP 2014-157609 A

上記の通り、特許文献1の技術を利用することで住宅建築業などでは関係者同士の情報共有が実現できる一方、ある程度規模感のある施工現場では複数の協力会社が複雑な対応関係のもとで作業を行っているため、これら各種作業に関する書類やタスクを適切に管理することは困難である。 As mentioned above, the technology in Patent Document 1 can be used to enable information sharing between related parties in the home building industry, but at construction sites of a certain size, multiple cooperating companies work under complex relationships, making it difficult to properly manage the documents and tasks related to these various types of work.

本発明は、上記従来技術の課題に鑑みて行われたものであって、その目的は、施工現場において、各作業に関連する書類を簡単且つ効果的に管理することができる書類管理システムを提供することにある。 The present invention was made in consideration of the problems with the conventional technology described above, and its purpose is to provide a document management system that can easily and effectively manage documents related to each task at a construction site.

上記課題を解決するために、本発明は、施工現場における作業の成果物を管理する書類管理システムであって、
前記書類管理システムは、記憶部と、登録受付部と、を備え、
前記記憶部は、前記施工現場に関する現場情報と、前記作業の作業分類を含んだ作業情報と、を対応付けて格納し、
前記登録受付部は、前記施工現場に対応する複数の作業分類の中から、ユーザに選択された特定作業分類の入力を受け付け、前記現場情報及び/又は前記作業情報に基づいて、前記特定作業分類の作業を担当する担当ユーザを特定し、
前記施工現場と、前記特定作業分類と、特定された担当ユーザと、を対応付け、該担当ユーザが前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する。
In order to solve the above problems, the present invention provides a document management system for managing work deliverables at a construction site,
The document management system includes a storage unit and a registration reception unit.
The storage unit stores site information related to the construction site and work information including a work classification of the work in association with each other,
The registration reception unit receives an input of a specific work category selected by a user from among a plurality of work categories corresponding to the construction site, and identifies a user in charge of the work of the specific work category based on the site information and/or the work information;
The construction site, the specific work category, and the specified responsible user are associated with each other, and the responsible user is registered in the storage unit as a deliverable task that can input the deliverable.

また、本発明は、施工現場における作業の成果物を管理する書類管理システムが実行する書類管理方法であって、
前記書類管理システムは、記憶部と、登録受付部と、を備え、
前記記憶部が、前記施工現場に関する現場情報と、前記作業の作業分類を含んだ作業情報と、を対応付けて格納するステップと、
前記登録受付部が、前記施工現場に対応する複数の作業分類の中から、ユーザに選択された特定作業分類の入力を受け付け、前記現場情報及び/又は前記作業情報に基づいて、前記特定作業分類の作業を担当する担当ユーザを特定するステップと、
前記登録受付部が、前記施工現場と、前記特定作業分類と、特定された担当ユーザと、を対応付け、該担当ユーザが前記成果物を入力可能な成果物タスクとして前記記憶部へ登録するステップと、を含む。
The present invention also provides a document management method executed by a document management system that manages work deliverables at a construction site, comprising:
The document management system includes a storage unit and a registration reception unit.
The storage unit stores site information related to the construction site and work information including a work classification of the work in association with each other;
The registration reception unit receives an input of a specific work category selected by a user from among a plurality of work categories corresponding to the construction site, and identifies a user in charge of the work of the specific work category based on the site information and/or the work information;
The registration reception unit includes a step of associating the construction site, the specific work classification, and the identified responsible user, and registering the deliverable in the memory unit as a deliverable task into which the responsible user can input the deliverable.

また、本発明は、施工現場における作業の成果物を管理する書類管理プログラムであって、
コンピュータを、記憶部と、登録受付部と、として機能させ、
前記記憶部は、前記施工現場に関する現場情報と、前記作業の作業分類を含んだ作業情報と、を対応付けて格納し、
登録受付部は、前記施工現場に対応する複数の作業分類の中から、ユーザに選択された特定作業分類の入力を受け付け、前記現場情報及び/又は前記作業情報に基づいて、前記特定作業分類の作業を担当する担当ユーザを特定し、
前記施工現場と、前記特定作業分類と、特定された担当ユーザと、を対応付け、該担当ユーザが前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する。
The present invention also provides a document management program for managing work deliverables at a construction site, comprising:
A computer is caused to function as a storage unit and a registration acceptance unit,
The storage unit stores site information related to the construction site and work information including a work classification of the work in association with each other,
The registration reception unit receives an input of a specific work category selected by a user from among a plurality of work categories corresponding to the construction site, and identifies a user in charge of the work of the specific work category based on the site information and/or the work information;
The construction site, the specific work category, and the specified responsible user are associated with each other, and the responsible user is registered in the storage unit as a deliverable task that can input the deliverable.

このような構成にすることで、施工現場において、各作業に関連する書類を簡単且つ効果的に管理することができる。 This configuration allows for simple and effective management of documents related to each task at the construction site.

本発明の好ましい形態では、前記現場情報は、前記施工現場における担当業者の従属関係を含んだ施工体制であり、
前記担当ユーザには、前記施工現場において作業を担当する担当業者が含まれ、
前記登録受付部は、前記ユーザに選択された前記特定作業分類の入力を受け付け、前記施工体制に基づいて、前記特定作業分類の作業を担当する担当業者を特定し、
前記施工現場と、前記特定作業分類と、特定された担当業者と、を対応付け、該担当業者が前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する。
In a preferred embodiment of the present invention, the on-site information is a construction system including subordinate relationships of contractors at the construction site,
The user in charge includes a contractor in charge of work at the construction site,
The registration reception unit receives an input of the specific work category selected by the user, and identifies a contractor in charge of the specific work category based on the construction system,
The construction site, the specific work category, and the specified contractor are associated with each other, and the deliverables are registered in the storage unit as deliverable tasks to which the contractor can input the deliverables.

このような構成にすることで、簡単且つ正確に担当業者(協力会社)を特定し、成果物タスクを登録することができる。 This configuration makes it easy and accurate to identify the responsible contractor (partner company) and register the deliverable tasks.

本発明の好ましい形態では、前記登録受付部は、前記請負業者担当業者に属する個人を含んだ前記施工体制に基づいて、前記特定作業分類の作業を担当する担当者を特定し、
前記施工現場と、前記特定作業分類と、前記担当業者と、特定された担当者と、を対応付け、該担当者が前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する。
In a preferred embodiment of the present invention, the registration reception unit identifies a person in charge of the specific work category based on the construction system including individuals belonging to the contractor's person in charge,
The construction site, the specific work category, the contractor, and the specified person in charge are associated with each other, and the deliverables are registered in the storage unit as deliverable tasks that the person in charge can input.

このような構成にすることで、簡単且つ正確に担当作業者(協力会社に属する作業者)を特定し、成果物タスクを登録することができる。 This configuration makes it easy and accurate to identify the responsible worker (a worker belonging to a cooperating company) and register the deliverable task.

本発明の好ましい形態では、前記書類管理システムは、更に、作成処理部と、承認処理部と、を備え、
前記作成処理部は、前記成果物の書類管理に関連する複数の成果物確認者で構成される回覧グループを作成処理し、
前記承認処理部は、複数の成果物確認者のうち、前記成果物タスクに含まれる成果物の承認権限を有する承認者からの入力に基づいて、当該成果物を承認処理する。
In a preferred embodiment of the present invention, the document management system further comprises a creation processing unit and an approval processing unit,
The creation processing unit creates and processes a circulation group composed of a plurality of deliverable checkers related to document management of the deliverable,
The approval processing unit performs approval processing of the deliverable based on an input from an approver who has approval authority for the deliverable included in the deliverable task, among a plurality of deliverable confirmers.

このような構成にすることで、成果物タスクに回覧グループを紐づけて登録し、且つ回覧グループにおいて当該成果物タスクの進捗を確認、承認することができる。すなわち、複数の成果物確認者から構成される回覧グループを導入することで、誰がどのタイミングで回覧(書類の確認)を完了しているか(または未だ確認していないか)をグループメンバーの全員が自身の端末から共有することができる。その結果、施工現場の回覧において煩雑な作業(紙ベースの書類をそれぞれのメンバーに持参して回覧する作業)をなくすことができる。 With this configuration, a circulation group can be linked to a deliverable task and registered, and the progress of the deliverable task can be confirmed and approved in the circulation group. In other words, by introducing a circulation group consisting of multiple deliverable reviewers, all group members can share from their own devices who has completed the circulation (document review) and when (or has not yet reviewed it). As a result, it is possible to eliminate the cumbersome work of circulating documents at construction sites (the work of having each member bring paper-based documents to circulate them).

本発明の好ましい形態では、前記登録受付部は、複数の前記確認者から前記書類管理に含まれる成果物の確認済みの入力を受け付け、該確認済みの入力に基づいて、各成果物確認者に確認済みフラグを対応付けて登録する。 In a preferred embodiment of the present invention, the registration reception unit receives inputs of confirmation of deliverables included in the document management from multiple verifyers, and registers each deliverable verifyer by associating a confirmation flag with the verifyer based on the confirmation input.

このような構成にすることで、それぞれの成果物管理者に簡単且つ正確に確認済みフラグを付与することができる。 This configuration allows each deliverable manager to easily and accurately assign a confirmed flag.

本発明の好ましい形態では、前記現場情報は、前記施工現場における担当業者の従属関係と、該担当業者に属する個人と、を含んだ施工体制であり、
前記作成処理部は、前記施工体制に基づいて、複数の成果物確認者を特定して前記回覧グループを作成処理する。
In a preferred embodiment of the present invention, the on-site information is a construction system including a subordinate relationship of a contractor at the construction site and individuals belonging to the contractor,
The creation processing unit identifies a plurality of product checkers based on the construction system and creates and processes the circulation group.

このような構成にすることで、各成果物タスクに対して適切な回覧グループを作成することができる。 This structure allows you to create appropriate circulation groups for each deliverable task.

本発明の好ましい形態では、前記作成処理部は、前記施工体制に基づく成果物確認者の候補から、ユーザからの選択入力を受け付けて複数の成果物管理者を決定する。 In a preferred embodiment of the present invention, the creation processing unit accepts a selection input from a user and determines multiple deliverable managers from among candidates for deliverable inspectors based on the construction system.

このような構成にすることで、ユーザが候補者の中から選択して複数の成果物管理者を決定することができる。 This configuration allows the user to select from among the candidates and determine multiple deliverable managers.

本発明の好ましい形態では、前記登録受付部は、ユーザから、複数の成果物管理者における権限順位の入力を受け付け、
前記作成処理部は、前記権限順位に基づいて、複数の成果物管理者における権限順位が設定された前記回覧グループを作成処理する。
In a preferred embodiment of the present invention, the registration reception unit receives an input of an authority ranking among a plurality of deliverable managers from a user,
The creation processing unit creates and processes the circulation group in which an authority ranking is set among a plurality of deliverable managers based on the authority ranking.

このような構成にすることで、ユーザが自由に権限順位を設定することができる。例えばユーザは回覧グループにおいて、特定の成果物管理者を承認者として設定することができる。 This configuration allows users to freely set the authority ranking. For example, a user can set a specific deliverable manager as the approver in a circulation group.

本発明の好ましい形態では、前記書類管理システムは、更に表示処理部を備え、
前記表示処理部は、各担当ユーザがそれぞれの成果物を入力するための複数の成果物タスクを、前記施工現場に関連するユーザが一覧で閲覧可能に表示処理する。
In a preferred embodiment of the present invention, the document management system further comprises a display processing unit,
The display processing unit processes and displays a plurality of deliverable tasks for each responsible user to input their respective deliverables in a list viewable by users related to the construction site.

このような構成にすることで、ユーザは、自身に関連する複数の成果物タスクを一覧で確認することができる。 This configuration allows users to see a list of multiple deliverable tasks that are related to them.

前記作業情報は、成果物の進捗を示すステータスを含み、
前記表示処理部は、前記施工現場と、前記特定作業分類と、前記担当ユーザと、前記ステータスと、が対応付けられた成果物タスクを表示処理する。
The work information includes a status indicating a progress of a deliverable,
The display processing unit displays a deliverable task in which the construction site, the specific work classification, the responsible user, and the status are associated with each other.

このような構成にすることで、ユーザは、各成果物タスクの進捗状況を簡単に確認することができる。 This structure allows users to easily check the progress of each deliverable task.

本発明の好ましい形態では、前記成果物タスクは、前記施工現場における特定作業分類の作業に関連する複数のユーザが入力可能なコメント欄を含む。 In a preferred embodiment of the present invention, the deliverable task includes a comment field that can be entered by multiple users related to work of a specific work category at the construction site.

このような構成にすることで、1つの成果物タスクに対して、複数のユーザがコメントを入力し、確認することができる。 This configuration allows multiple users to enter and review comments for a single deliverable task.

本発明の好ましい形態では、前記成果物タスクは、属性の異なる複数のユーザが前記成果物を入力可能である。 In a preferred embodiment of the present invention, the deliverable task allows multiple users with different attributes to input the deliverables.

このような構成にすることで、1つの成果物タスクに対して、複数のユーザが成果物を入力し、確認することができる。 This configuration allows multiple users to input and review deliverables for a single deliverable task.

本発明によれば、現場情報及び作業情報を利用して所定の処理を実行することで、書類管理システムに係る新規な技術を提供することができる。 According to the present invention, it is possible to provide a new technology related to a document management system by performing a specified process using on-site information and work information.

本発明の一実施形態に係るシステム構成のブロック図を示す。1 shows a block diagram of a system configuration according to an embodiment of the present invention. 本発明の一実施形態に係る情報処理装置及び端末のハードウェア構成の一例の概略図を示す。1A and 1B are schematic diagrams illustrating an example of a hardware configuration of an information processing device and a terminal according to an embodiment of the present invention. 本発明の一実施形態に係る書類管理システムの処理手順のフローチャートを示す。2 shows a flowchart of a processing procedure of a document management system according to an embodiment of the present invention. 本発明の一実施形態に係る書類管理システムで利用される各情報の一例を示す。3 shows an example of each piece of information used in a document management system according to an embodiment of the present invention. 本発明の一実施形態に係る施工体制の概略イメージ図を示す。FIG. 1 shows a schematic image diagram of a construction system according to one embodiment of the present invention. 本発明の一実施形態に係る書類管理システムで利用される各情報の一例を示す。3 shows an example of each piece of information used in a document management system according to an embodiment of the present invention. 本発明の一実施形態に係る端末における表示処理結果の一例を示す。11 shows an example of a display processing result in the terminal according to an embodiment of the present invention. 本発明の一実施形態に係る端末における表示処理結果の一例を示す。11 shows an example of a display processing result in the terminal according to an embodiment of the present invention. 本発明の一実施形態に係る書類管理システムにおける承認処理の処理手順のフローチャートを示す。1 shows a flowchart of a processing procedure for approval processing in a document management system according to an embodiment of the present invention. 本発明の一実施形態に係る回覧グループの作成画面の一例を示す。13 shows an example of a circulation group creation screen according to an embodiment of the present invention. 本発明の一実施形態に係る回覧グループの作成画面の一例を示す。13 shows an example of a circulation group creation screen according to an embodiment of the present invention. 本発明の一実施形態に係る端末における表示処理結果の一例を示す。11 shows an example of a display processing result in the terminal according to an embodiment of the present invention.

以下、添付図面を参照して、更に詳細に説明する。図面には好ましい実施形態が示されている。しかし、多くの異なる形態で実施されることが可能であり、本明細書に記載される実施形態に限定されない。 The present invention will now be described in more detail with reference to the accompanying drawings, in which preferred embodiments are shown. However, the present invention may be embodied in many different forms and is not limited to the embodiments described herein.

例えば、本実施形態では書類管理システムの構成、動作等について説明するが、実行される方法(ステップ)、装置、コンピュータプログラム等によっても、同様の作用効果を奏することができる。本実施形態におけるプログラムは、コンピュータが読み取り可能な非一過性の記録媒体として提供されてもよいし、外部のサーバからダウンロード可能に提供されてもよい。 For example, the configuration, operation, etc. of a document management system are described in this embodiment, but similar effects can be achieved by the executed method (steps), device, computer program, etc. The program in this embodiment may be provided as a non-transient computer-readable recording medium, or may be provided so as to be downloadable from an external server.

また、本実施形態において「部」とは、例えば、広義の回路によって実施されるハードウェア資源と、これらハードウェア資源によって具体的に実現され得るソフトウェアの情報処理とを合わせたものも含み得る。 In this embodiment, a "part" may also include, for example, a combination of hardware resources implemented by a circuit in the broad sense and software information processing that can be specifically realized by these hardware resources.

本実施形態において「情報」とは、例えば電圧・電流を表す信号値の物理的な値、0又は1で構成される2進数のビット集合体としての信号値の高低、又は量子的な重ね合わせ(いわゆる量子ビット)によって表され、広義の回路上で通信・演算が実行され得る。 In this embodiment, "information" is represented by, for example, the physical value of a signal representing a voltage or current, the high or low value of a signal as a binary bit collection consisting of 0 or 1, or a quantum superposition (so-called quantum bit), and communication and calculations can be performed on a circuit in the broad sense.

広義の回路とは、回路(Circuit)、回路類(Circuitry)、プロセッサ(Processor)及びメモリ(Memory)等を適宜組み合わせることによって実現される回路である。即ち、CPU(Central Processing Unit)、GPU(Graphics Processing Unit)、LSI(Large Scale Integration)、ASIC(Application Specific Integrated Circuit)、FPGA(Field-Programmable Gate Array)等を含むものである。 In the broad sense, a circuit is a circuit that is realized by appropriately combining a circuit, circuitry, processor, memory, etc. In other words, it includes a CPU (Central Processing Unit), a GPU (Graphics Processing Unit), an LSI (Large Scale Integration), an ASIC (Application Specific Integrated Circuit), an FPGA (Field-Programmable Gate Array), etc.

<システム構成>
図1は、本発明の一実施形態に係るシステム構成を示すブロック図である。図1に示すように書類管理システム1は、情報処理装置10及びデータベースDBを備える。書類管理システム1は、ネットワークNWを介して複数の管理端末2(図1では符号2(a)~2(c))、及び作業端末3(符号3(a)~3(c))と通信可能に構成されている。なお、本実施形態において、管理端末2及び作業端末3をあわせてユーザ端末と呼ぶこともある。
<System Configuration>
Fig. 1 is a block diagram showing a system configuration according to an embodiment of the present invention. As shown in Fig. 1, the document management system 1 includes an information processing device 10 and a database DB. The document management system 1 is configured to be able to communicate with a plurality of management terminals 2 (reference numerals 2(a) to 2(c) in Fig. 1) and work terminals 3 (reference numerals 3(a) to 3(c)) via a network NW. In this embodiment, the management terminals 2 and work terminals 3 are sometimes collectively referred to as user terminals.

情報処理装置10は、サーバとして動作し、管理端末2は元請業者などが後述する成果物タスクなどを登録等するために利用する端末であり、作業端末3は協力会社や作業者が成果物タスクへ作業情報を入力等するために利用する端末である。 The information processing device 10 operates as a server, the management terminal 2 is a terminal used by prime contractors and others to register deliverable tasks, which will be described later, and the work terminal 3 is a terminal used by cooperating companies and workers to input work information into deliverable tasks, etc.

ネットワークNWは、本実施形態では、IP(Internet Protocol)ネットワークであるが、通信プロトコルの種類に制限はなく、更に、ネットワークの種類、規模にも制限はない。 In this embodiment, the network NW is an IP (Internet Protocol) network, but there are no restrictions on the type of communication protocol, and there are also no restrictions on the type or size of the network.

なお、情報処理装置10として、汎用のサーバ向けのコンピュータやパーソナルコンピュータ等を利用することが可能である。また、後述の機能構成要素を複数のコンピュータに実現させ、書類管理システム1を構成することも可能である。 In addition, a general-purpose server computer, a personal computer, etc. can be used as the information processing device 10. It is also possible to configure the document management system 1 by implementing the functional components described below on multiple computers.

管理端末2は、元請業者(または元請業者の担当者)などが利用する端末である。管理端末2として、スマートフォンやタブレット端末、パーソナルコンピュータ、ウェアラブルデバイス等を利用することができる。管理端末2は、管理用の書類管理アプリプログラムを記憶し、このアプリプログラムはユーザにおいて成果物タスクなどを登録し、あるいは成果物タスクを閲覧等するための機能を有して構成される。 The management terminal 2 is a terminal used by the prime contractor (or the prime contractor's staff) and the like. A smartphone, tablet terminal, personal computer, wearable device, etc. can be used as the management terminal 2. The management terminal 2 stores a document management application program for management, and this application program is configured with a function for the user to register deliverable tasks, etc., or to view deliverable tasks, etc.

作業端末3は、協力会社や作業者などが利用する端末である。作業端末2として、スマートフォンやタブレット端末、パーソナルコンピュータ、ウェアラブルデバイス等を利用することができる。作業端末3は、作業用の書類管理アプリプログラムを記憶し、作業分類等の入力や選択、及び成果物タスクの入力や閲覧等をするための機能を有して構成される。 The work terminal 3 is a terminal used by cooperating companies, workers, etc. A smartphone, tablet terminal, personal computer, wearable device, etc. can be used as the work terminal 2. The work terminal 3 stores a work document management application program and is configured with functions for inputting and selecting work categories, etc., and inputting and viewing deliverable tasks, etc.

なお、管理端末2及び作業端末3は、それぞれの書類管理アプリプログラムを有していない構成にすることもできる。この場合、管理端末2及び作業端末3はウェブブラウザ等を利用して各情報を閲覧、送信等することができる。 The management terminal 2 and the work terminal 3 may be configured not to have the respective document management application programs. In this case, the management terminal 2 and the work terminal 3 may use a web browser or the like to view and transmit each piece of information.

<ハードウェア構成>
図2(a)は、情報処理装置10のハードウェア構成の一例を示す図である。情報処理装置10は、ハードウェア構成として、制御部11と、記憶部12と、通信部13と、を備える。
<Hardware Configuration>
2A is a diagram showing an example of a hardware configuration of the information processing device 10. The information processing device 10 includes, as the hardware configuration, a control unit 11, a storage unit 12, and a communication unit 13.

制御部11は、CPU等の1又は2以上のプロセッサを含み、本発明に係る書類管理プログラム、OS、その他のアプリケーションを実行することで、情報処理装置10の動作処理全体を制御する。 The control unit 11 includes one or more processors such as a CPU, and controls the overall operation and processing of the information processing device 10 by executing the document management program, OS, and other applications related to the present invention.

記憶部12は、HDD、SSD、ROM、RAM等であって、本発明に係る書類管理プログラム及び、制御部11がプログラムに基づき処理を実行する際に利用するデータ等を記憶する。制御部11が、記憶部12に記憶されている書類管理プログラムに基づき、処理を実行することによって、後述する機能構成が実現される。 The storage unit 12 is a HDD, SSD, ROM, RAM, etc., and stores the document management program according to the present invention and data used when the control unit 11 executes processing based on the program. The control unit 11 executes processing based on the document management program stored in the storage unit 12, thereby realizing the functional configuration described below.

通信部13は、ネットワークNWとの通信制御を実行して、情報処理装置10を動作させるために必要な入力や、動作結果に係る出力を行う。 The communication unit 13 controls communication with the network NW, and performs inputs necessary to operate the information processing device 10 and outputs related to the results of the operations.

図2(b)は端末90(図1における管理端末2及び作業端末3)のハードウェア構成の一例を示す図である。端末90は、ハードウェア構成として、制御部91と、記憶部92と、通信部93と、入力部94と、出力部95と、を備える。 Figure 2 (b) is a diagram showing an example of the hardware configuration of a terminal 90 (the management terminal 2 and the work terminal 3 in Figure 1). The terminal 90 includes, as its hardware configuration, a control unit 91, a memory unit 92, a communication unit 93, an input unit 94, and an output unit 95.

端末90の制御部91は、CPU等の1以上のプロセッサを含み、端末90の動作処理全体を制御する。端末90の記憶部92は、HDD、SSD、ROM、RAM等であって、上述の書類管理アプリプログラム並びに、制御部91がプログラムに基づき処理を実行する際に利用するデータ等を記憶する。 The control unit 91 of the terminal 90 includes one or more processors such as a CPU, and controls the overall operation and processing of the terminal 90. The storage unit 92 of the terminal 90 is an HDD, SSD, ROM, RAM, etc., and stores the document management application program described above, as well as data and the like used when the control unit 91 executes processing based on the program.

端末90の通信部93は、ネットワークとの通信を制御する。端末90の入力部94は、タッチパネル、マウス及びキーボード等であって、ユーザによる操作要求を制御部91に入力する。端末90の出力部95は、ディスプレイ等であって、制御部91の処理の結果等を表示する。 The communication unit 93 of the terminal 90 controls communication with the network. The input unit 94 of the terminal 90 is a touch panel, mouse, keyboard, etc., and inputs operation requests from the user to the control unit 91. The output unit 95 of the terminal 90 is a display, etc., and displays the results of processing by the control unit 91, etc.

<機能構成>
図2(a)に示すように、情報処理装置10は、機能構成として、登録受付部101、送信部102、表示処理部103、作成処理部104、承認処理部105、を備える。これらは、ソフトウェア(記憶部12に記憶されている)による情報処理が、ハードウェア(制御部11等)によって具体的に実現されたものである。
<Functional configuration>
2A, the information processing device 10 includes, as its functional configuration, a registration acceptance unit 101, a transmission unit 102, a display processing unit 103, a creation processing unit 104, and an approval processing unit 105. These are information processing performed by software (stored in the storage unit 12) specifically realized by hardware (the control unit 11, etc.).

登録受付部101は、ユーザ端末から各種情報を受け付けて登録する。本実施形態において登録受付部101は、施工現場に対応する複数の作業分類の中から、ユーザに選択された特定作業分類の入力を受け付け、現場情報及び/又は作業情報に基づいて、特定作業分類(例えば鉄筋における施工計画書や手順書)の作業を担当する担当ユーザを特定する。そして登録受付部101は、施工現場と、特定作業分類と、特定された担当ユーザと、を対応付け、当該担当ユーザが成果物を入力可能な成果物タスクとして記憶部12へ登録する。 The registration reception unit 101 receives and registers various information from the user terminal. In this embodiment, the registration reception unit 101 receives input of a specific task category selected by the user from among multiple task categories corresponding to the construction site, and identifies a responsible user who will be responsible for the work of the specific task category (e.g., a construction plan or procedure manual for rebar) based on the site information and/or task information. The registration reception unit 101 then associates the construction site, the specific task category, and the identified responsible user, and registers the work in the storage unit 12 as a deliverable task for which the responsible user can input a deliverable.

また、登録受付部101は、ユーザに選択された特定作業分類の入力を受け付け、施工体制に基づいて、特定作業分類の作業を担当する担当業者(協力会社)を特定し、施工現場と、特定作業分類と、特定された担当業者と、を対応付け、担当業者が成果物を入力可能な成果物タスクとして記憶部12へ登録する。 The registration reception unit 101 also receives input of the specific work category selected by the user, identifies the contractor (subcontractor) in charge of the specific work category based on the construction system, associates the construction site, the specific work category, and the identified contractor, and registers the work as a deliverable task in the memory unit 12 for which the contractor can input deliverables.

さらに、登録受付部101は、担当業者に属する個人を含んだ施工体制に基づいて、特定作業分類の作業を担当する担当者(協力会社に属する作業者)を特定し、施工現場と、特定作業分類と、特定された担当業者と、特定された担当者と、を対応付け、担当者が成果物を入力可能な成果物タスクとして記憶部12へ登録することもできる。 Furthermore, the registration reception unit 101 can identify the person in charge of work of a specific work category (a worker belonging to a cooperating company) based on the construction system including individuals belonging to the contractor in charge, and can associate the construction site, the specific work category, the identified contractor in charge, and the identified person in charge, and can register them in the memory unit 12 as a deliverable task in which the person in charge can input deliverables.

送信部102は、ユーザ端末へ各種情報を送信する。本実施形態における送信部102は、ユーザからの要求に基づいて、施工現場に対応する複数の作業分類(施工計画書や手順書)を送信する。送信部102は、ユーザが選択可能な複数の作業分類をユーザ端末へ送信することができる。 The transmission unit 102 transmits various information to the user terminal. In this embodiment, the transmission unit 102 transmits multiple work classifications (construction plans and procedures) corresponding to the construction site based on a request from the user. The transmission unit 102 can transmit multiple work classifications that the user can select to the user terminal.

表示処理部103は、管理端末2及び作業端末3の表示画面等を表示処理する。本実施形態における表示処理部103は、各担当ユーザがそれぞれの成果物を入力するための複数の成果物タスクを、施工現場に関連するユーザが一覧で閲覧可能に表示処理する。 The display processing unit 103 performs display processing on the display screens of the management terminal 2 and the work terminal 3. In this embodiment, the display processing unit 103 displays a list of multiple deliverable tasks for each responsible user to input their respective deliverables, so that users related to the construction site can view them.

また、表示処理部103は、施工現場と、特定作業分類(鉄筋における施工計画書や手順書など)と、担当ユーザと、成果物の進捗を示すステータスと、が対応付けられた成果物タスクを表示処理することができる。 In addition, the display processing unit 103 can display and process deliverable tasks that correspond to a construction site, a specific work classification (such as a construction plan or procedure manual for rebar), a responsible user, and a status indicating the progress of the deliverable.

作成処理部104は、書類管理に利用可能なグループなどを作成処理する。本実施形態における作成処理部104は、成果物の書類管理に関連する複数の成果物確認者で構成される回覧グループを作成処理する。 The creation processing unit 104 creates groups that can be used for document management. In this embodiment, the creation processing unit 104 creates a circulation group that is made up of multiple deliverable reviewers related to the document management of the deliverables.

また、作成処理部104は、施工体制に基づく成果物確認者の候補から、ユーザからの選択入力を受け付けて回覧グループにおける複数の成果物管理者を決定することができる。さらに作成処理部104は、ユーザからの入力による権限順位に基づいて、複数の成果物管理者における権限順位が設定された回覧グループを作成処理することもできる。 The creation processing unit 104 can also accept a selection input from the user from among candidates for deliverable inspectors based on the construction system and determine multiple deliverable managers in the circulation group. Furthermore, the creation processing unit 104 can also create and process a circulation group in which the authority rankings of multiple deliverable managers are set based on the authority rankings input by the user.

承認処理部105は、ユーザ端末からの入力に基づいて成果物タスクの承認処理をする。本実施形態における承認処理部105は、複数の成果物確認者のうち、成果物タスクに含まれる成果物の承認権限を有する承認者からの入力に基づいて、成果物タスクの承認処理をする。 The approval processing unit 105 performs approval processing of the deliverable task based on input from the user terminal. In this embodiment, the approval processing unit 105 performs approval processing of the deliverable task based on input from an approver who has approval authority for the deliverable included in the deliverable task, among multiple deliverable reviewers.

<データベースDB>
図1のデータベースDBは、作業者などのユーザに関するユーザ情報、元請会社や協力会社などの会社情報、施工現場に関する施工現場情報、施工作業に関する作業情報、施工現場における施工体制に関する施工体制情報、成果物タスク情報、回覧グループ情報、その他書類管理や書類の承認処理に必要な情報などを格納する。これらの一部又は全部は、記憶部12等に格納されてもよいし、これらの一部が別のデータベース等に格納されてもよい。
<Database DB>
1 stores user information on users such as workers, company information on prime contractors and cooperating companies, construction site information on the construction site, work information on the construction work, construction system information on the construction system at the construction site, deliverable task information, circulation group information, and other information necessary for document management and document approval processing, etc. Some or all of these may be stored in the storage unit 12, etc., or some of these may be stored in another database, etc.

以下、図3~12を参照して、書類管理システム1の説明及び各機能構成要素による処理内容について説明する。 Below, we will explain the document management system 1 and the processing contents of each functional component with reference to Figures 3 to 12.

<書類管理システムの概要>
本実施形態に係る書類管理システム1は、施工現場で実施される施工作業に関連する書類やタスクなどを簡単且つ適切に管理するためのシステムである。書類管理システム1は、ユーザから現場情報や作業情報の入力を受け付けることで、ユーザに複数の書類(成果物タスク、具体的な施工作業に関するタスク、作業分類や書類分類などとも呼ぶ)を提示し、その中からユーザに選択された成果物タスクを登録することができる。
<Document Management System Overview>
The document management system 1 according to the present embodiment is a system for simply and appropriately managing documents and tasks related to construction work carried out at a construction site. The document management system 1 accepts input of site information and work information from a user, presents a plurality of documents (also called deliverable tasks, tasks related to specific construction work, work classifications, document classifications, etc.) to the user, and can register a deliverable task selected by the user from among them.

つまり、ユーザは施工現場に関する現場情報と鉄筋やコンクリートといった大枠の作業情報のみを入力することで、予め用意された具体的な成果物タスクを簡単に設定することができる。 In other words, users can easily set up specific pre-prepared deliverable tasks by inputting only on-site information about the construction site and general work information such as rebar and concrete.

また、本実施形態に係る書類管理システム1は、施工体制を利用して実際に作業を担当する担当ユーザを特定し、成果物タスクに紐づけて登録することができる。つまり、協力会社同士の複雑な従属関係のもとで作業が進められる施工現場において、ユーザはこの複雑な従属関係を考慮しながら担当ユーザを設定する必要はなく、本システムではユーザが成果物タスクを選択することで自動的に担当ユーザを特定(及び登録)することができる。 In addition, the document management system 1 according to this embodiment can use the construction structure to identify the user in charge who will actually be in charge of the work, and register the user in association with the deliverable task. In other words, at a construction site where work is carried out under complex subordinate relationships between cooperating companies, the user does not need to set the user in charge while taking these complex subordinate relationships into consideration; in this system, the user can automatically identify (and register) the user in charge by selecting the deliverable task.

さらに書類管理システム1は、従来にはない新たな概念として回覧グループを有している。従来の施工現場では、施工計画書などの書類に記入された内容は、この作業に関連する部署や団体の対象者(上長や現場監督など)にそれぞれ回覧し、最終的に承認を得る必要がある。 Furthermore, Document Management System 1 has a circulation group, which is a new concept not seen in the past. At conventional construction sites, the contents written in documents such as construction plans must be circulated to the appropriate people (supervisors, site supervisors, etc.) in the departments and organizations related to the work, and ultimately approved.

しかしながら、実際の施工現場では、必ずしも回覧される対象者が毎日現場に訪れているとも限らず、場合によっては本社に常駐している対象者に回覧することもある。この場合、対象者全員に回覧するだけでも多大な時間を要し、また文書をその都度持参する必要があるため、書類や文書を回覧すること自体が非常に煩雑な作業となる。 However, in an actual construction site, the people to whom documents are to be circulated are not necessarily on-site every day, and in some cases documents may be circulated to people who are stationed at the head office. In such cases, it takes a lot of time just to circulate documents to all the people involved, and documents must be brought with them each time, making circulating documents and documents itself a very cumbersome task.

そこで本実施形態に係る書類管理システム1では、複数の回覧対象者(成果物確認者とも呼ぶ)から構成される回覧グループを導入することで、誰がどのタイミングで回覧(書類の確認)を完了しているか(または未だ確認していないか)をグループメンバーの全員が自身の端末から共有することができる。その結果、施工現場の回覧において上記の煩雑な作業をなくすことができる。以下、書類書管理システム1における処理の流れについて詳しく説明する。 Therefore, in the document management system 1 according to this embodiment, a circulation group consisting of multiple circulation targets (also called product reviewers) is introduced, allowing all group members to share from their own terminals who has completed circulation (document review) and when (or has not yet reviewed). As a result, the above-mentioned cumbersome work can be eliminated when circulating documents at construction sites. The process flow in the document management system 1 will be explained in detail below.

<各種情報の登録>
図3には、本発明の一実施形態に係る書類管理システムにおける処理手順のフローチャートを示す。S201において、元請会社や協力会社(及びこれらに属する個人)などのユーザは、事前にユーザ情報を登録する。情報処理装置10の登録受付部101は、書類管理に利用される各種情報を登録する。なお、本実施形態におけるユーザには、元請会社や協力会社に加え、元請会社の現場担当者や協力会社の作業者など(施工作業に関連する人)も含まれる。
<Registering various information>
3 shows a flowchart of a processing procedure in a document management system according to an embodiment of the present invention. In S201, users such as prime contractors and cooperating companies (and individuals belonging to these companies) register user information in advance. The registration reception unit 101 of the information processing device 10 registers various information used for document management. Note that users in this embodiment include not only prime contractors and cooperating companies, but also on-site personnel of prime contractors and workers of cooperating companies (people involved in construction work).

図4(a)に示すように、ユーザ情報は、ユーザの氏名、連絡先、職務に関する情報、保有する資格に関する情報、顔画像、ユーザ特定情報、登録日、ユーザが属する会社(元請会社や請負業者)に関する情報(後述する会社ID)、などの情報を含んでユーザIDで管理される。なお、ユーザには、現場監督や現場管理者の他、例えば実際に施工現場に訪れることはないが現場状況を管理し、または施工作業の承認等を行う責任者(元請会社の本社に属する責任者)なども含まれる。 As shown in FIG. 4(a), user information includes the user's name, contact information, job information, information about qualifications held, facial image, user identification information, registration date, information about the company to which the user belongs (prime contractor or subcontractor) (company ID, described below), and other information, and is managed by user ID. Note that users also include site supervisors and site managers, as well as, for example, responsible persons who do not actually visit the construction site but manage the site situation or approve construction work (responsible persons attached to the headquarters of the prime contractor).

本実施形態における書類管理システム1では、ユーザ情報に加えて、ユーザが属する元請会社や協力会社などに関する会社情報、それぞれの施工現場に関する施工現場情報、及び施工現場における作業に関する作業情報も事前に登録している。 In the document management system 1 of this embodiment, in addition to user information, company information related to the prime contractor or partner company to which the user belongs, construction site information related to each construction site, and work information related to work at the construction sites are also registered in advance.

図4(b)に示すように、会社情報は、A会社やD建設などの会社名、会社の連絡先、会社の住所、元請会社か協力会社かを示す種別、対応可能な職務、などを含んで会社IDで管理される。この会社情報には、例えば一人親方などに関する情報を含めることもできる。 As shown in FIG. 4(b), company information includes the company name (e.g., A Company or D Construction), company contact information, company address, type indicating whether the company is a prime contractor or a subcontractor, available duties, and the like, and is managed by company ID. This company information can also include information about sole proprietors, for example.

また、図4(c)に示すように、施工現場情報は、A施工現場やB施工現場などの現場名、現場住所、施工期間、などを含んで施工現場IDで管理される。さらに、図4(d)に示すように、作業情報は、コンクリートや鉄筋などの作業名称(または工種)、作業計画書や手順書などの作業分類、などを含んで作業IDで管理される。なお、本明細書では、「鉄筋における手順書」のように、工種及び具体的な作業を特定したものを作業分類と表現することもある。 As shown in FIG. 4(c), construction site information includes the site name (e.g., construction site A or construction site B), the site address, the construction period, etc., and is managed by a construction site ID. As shown in FIG. 4(d), work information includes the work name (or type of work), such as concrete or reinforcing steel, and the work classification, such as a work plan or procedure manual, and is managed by a work ID. Note that in this specification, the specified type of work and specific work, such as "procedure manual for reinforcing steel," may also be referred to as a work classification.

図3のS202において、情報処理装置10の登録受付部101は、施工現場における施工体制を取得し、記憶部12へ格納(登録)する。本実施形態では、この施工体制を利用してユーザから選択された特定作業分類の作業を担当する担当ユーザ(協力会社や協力会社に属する担当者)を特定することができる。 In S202 of FIG. 3, the registration reception unit 101 of the information processing device 10 acquires the construction organization at the construction site and stores (registers) it in the memory unit 12. In this embodiment, this construction organization can be used to identify the responsible user (a cooperating company or a person in charge belonging to a cooperating company) who will be in charge of the work of the specific work category selected by the user.

図5には、本発明の一実施形態に係る施工体制の概略イメージ図を示す。同図に示すように、施工体制には元請会社と複数の協力会社同士(請負業者同士)の従属関係が示されている。 Figure 5 shows a schematic image diagram of a construction system according to one embodiment of the present invention. As shown in the figure, the construction system shows the subordinate relationships between a prime contractor and multiple cooperating companies (contractors).

図5における施工体制は、従属関係等が一目で分かるように図式化して表現されている。図5は、本実施形態における施工体制を理解するための概略イメージとして表現している。情報処理装置10の記憶部12は、施工現場の情報、元請会社と複数の協力会社同士の従属関係、などを含んだ施工体制情報を格納する。 The construction system in Figure 5 is diagrammatically represented so that subordinate relationships and the like can be seen at a glance. Figure 5 represents a schematic image for understanding the construction system in this embodiment. The memory unit 12 of the information processing device 10 stores construction system information including information on the construction site, subordinate relationships between the prime contractor and multiple cooperating companies, and the like.

例えば図4(e)に示すように施工体制情報(施工体制に関する情報)は、施工現場情報の施工現場ID、作業ID、会社ID、ユーザID、一次や二次などの会社同士の従属関係に関する情報、親会社の会社ID、対応可能な職務に関する情報、などを含んで施工体制IDで管理される。なお、本明細書では施工体制情報のことを単に施工体制と表現することもある。 For example, as shown in FIG. 4(e), the construction system information (information related to the construction system) includes the construction site ID of the construction site information, the task ID, the company ID, the user ID, information on the subordinate relationships between companies such as primary and secondary, the company ID of the parent company, information on the duties that can be handled, and the like, and is managed by the construction system ID. Note that in this specification, the construction system information may also be referred to simply as the construction system.

図5では元請Aに対し、1次から5次までの協力会社、及びその従属関係が、鉄筋、土木、内装などの職務ごとに示されている。図5では、職務として「鉄筋作業」を行う協力会社として、D建設(1次)、E工務店(2次)が示され、「土木作業」を行う協力会社として、F組(1次)、G工業(2次)、H機工(3次)が示される。また、「内装作業」を行う協力会社として、J内装(1次)、K工務店(2次)、Lハウス(3次)、山田太郎(4次)、佐藤一郎(5次)、中村次郎(5次)が示されている。 In Figure 5, the subcontractors from 1st to 5th tier for prime contractor A and their subordinate relationships are shown for each job function, such as rebar work, civil engineering, and interior work. In Figure 5, D Construction (1st tier) and E Komuten (2nd tier) are shown as subcontractors performing the job "rebar work," while F Group (1st tier), G Kogyo (2nd tier), and H Kiko (3rd tier) are shown as subcontractors performing "civil engineering work." In addition, J Interior (1st tier), K Komuten (2nd tier), L House (3rd tier), Yamada Taro (4th tier), Sato Ichiro (5th tier), and Nakamura Jiro (5th tier) are shown as subcontractors performing "interior work."

また、図5に示すように、施工体制には元請会社や協力会社の情報を含んだ会社情報、施工作業に関する作業情報、施工現場に関する施工現場情報、及びユーザ情報が紐づけられている。このように、施工体制に会社情報、作業情報、施工現場情報、ユーザ情報を紐づけることで、協力会社同士の複雑な従属関係が生じ得る施工現場において、簡単且つ精度良く成果物タスクの担当ユーザを特定し、この担当ユーザが紐づけられた成果物タスクを登録することができる。 As shown in FIG. 5, the construction system is linked to company information, including information on the prime contractor and cooperating companies, work information related to the construction work, construction site information related to the construction site, and user information. In this way, by linking company information, work information, construction site information, and user information to the construction system, it is possible to easily and accurately identify the user in charge of a deliverable task at a construction site where complex subordinate relationships between cooperating companies may arise, and to register the deliverable task to which this user is linked.

<成果物タスクの登録>
図3のS203において、情報処理装置10の送信部102は、管理端末2へ複数の作業分類を送信する。具体的には、登録受付部101が管理端末2から現場情報(例えばA施工現場)や作業情報(例えば鉄筋やコンクリート、工種など)を受け付け、その後に送信部102は管理端末2から受け付けたA施工現場の鉄筋などの情報に基づいて、ユーザが選択可能な複数の作業分類を管理端末2へ送信する。
<Registering deliverable tasks>
3, the transmission unit 102 of the information processing device 10 transmits a plurality of work classifications to the management terminal 2. Specifically, the registration reception unit 101 receives site information (e.g., construction site A) and work information (e.g., reinforcing bars, concrete, work type, etc.) from the management terminal 2, and then the transmission unit 102 transmits a plurality of work classifications selectable by the user to the management terminal 2 based on the information on the reinforcing bars of construction site A received from the management terminal 2.

例えば現場情報は、A施工現場、B施工現場、C施工現場などの各施工現場を示す情報であり、作業情報は、鉄筋やコンクリートなどの工種(大分類)を示す情報であり、作業分類は、鉄筋における作業計画書や手順書などを示す情報である。 For example, site information is information indicating each construction site, such as construction site A, construction site B, and construction site C, work information is information indicating the type of work (major classification) such as reinforcing bars or concrete, and work classification is information indicating work plans and procedures for reinforcing bars, etc.

例えば手順書には、鉄筋の組み立て作業の複数の手順が記載され、その手順に従って作業者が実際の作業(タスク)を進めることになる。作業者はそれぞれ手順ごとの作業が完了した段階で、この手順書に施工実績(作業実績)を成果物として登録する。 For example, a procedure manual may contain multiple steps for assembling rebar, and workers will follow those steps to carry out the actual work (tasks). When each worker completes a task, they register the construction results (work results) in the procedure manual as a deliverable.

また、登録受付部101は、鉄筋やコンクリートなどの大分類に加えて、「鉄筋の組み立て」や「コンクリートの打ち込み」などの中分類、さらに詳細な作業を示す小分類などの情報を作業情報として受け付けることもできる。このような詳細な情報を受け付けることで、よりピンポイントな作業分類の選択を管理端末2へ提示することができる。 The registration reception unit 101 can also receive information such as medium categories such as "assembling rebar" and "pouring concrete" as well as subcategories indicating more detailed work, in addition to major categories such as rebar and concrete, as work information. By receiving such detailed information, a more pinpointed selection of work categories can be presented to the management terminal 2.

S204において、情報処理装置10の登録受付部101は、ユーザから選択された作業分類を受け付ける。具体的には、登録受付部101は、施工現場に対応する複数の作業分類の中から、ユーザに選択された特定作業分類の入力を受け付ける。例えば、登録受付部101は、施工現場Aに対応するコンクリートの作業計画書や手順書などの複数の作業分類の中から、ユーザが作業計画書を選択した場合、当該コンクリートの作業計画書が特定作業分類となる。つまり、本実施形態における特定作業分類は、ユーザが選択した作業分類を意味する。 In S204, the registration reception unit 101 of the information processing device 10 receives the work classification selected by the user. Specifically, the registration reception unit 101 receives input of a specific work classification selected by the user from among multiple work classifications corresponding to the construction site. For example, when the user selects a work plan from multiple work classifications such as a concrete work plan and a procedure manual corresponding to the construction site A, the registration reception unit 101 sets the concrete work plan as the specific work classification. In other words, the specific work classification in this embodiment means the work classification selected by the user.

図6(a)に示すように、成果物タスク情報は、タスク名(書類名または成果物名称)、施工体制ID、作業ID、管理担当(元請会社の担当者)、作業担当(協力会社の作業者)、作業会社(協力会社)、タスクの完了期限、着手中や完了などのステータス、タスクの進捗を示すためのデータが保存される保存先、コメントの保存先、後述する回覧ID、社内承認などの承認区分、などを含んでタスクIDで管理される。この他にも成果物タスク情報として、管理担当者が所属する元請会社などを含めることもできる。 As shown in FIG. 6(a), deliverable task information includes the task name (document name or deliverable name), construction system ID, work ID, management person (person in charge at the prime contractor), work person (worker at a cooperating company), work company (cooperating company), task completion deadline, status such as in progress or completed, storage destination where data showing the progress of the task is saved, storage destination for comments, circulation ID described below, approval category such as internal approval, etc., and is managed by task ID. In addition, the deliverable task information can also include the prime contractor to which the management person belongs.

また、図6(b)には後述する回覧グループに対応する回覧グループ情報が示されている。回覧グループ情報は、施工体制ID、確認者(成果物確認者)、所長や工場長などの役職、承認者、などを含んで回覧IDで管理される。この回覧グループは、詳細は後述するが、管理端末2から設定することができる。この他にも回覧グループ情報には、承認者の権限順位などを含めることができる。 Also, FIG. 6(b) shows circulation group information corresponding to the circulation groups described below. The circulation group information includes a construction organization ID, a checker (deliverable checker), a position such as a director or a factory manager, an approver, and the like, and is managed by a circulation ID. This circulation group, the details of which will be described later, can be set from the management terminal 2. In addition, the circulation group information can include the authority ranking of the approver, and the like.

そしてS205において、情報処理装置10の登録受付部101は、特定作業分類の作業を担当する担当ユーザを特定処理する。本実施形態における担当ユーザは、作業を担当する協力会社(業者)、あるいは協力会社に属する実際の作業者などを含む。 Then, in S205, the registration reception unit 101 of the information processing device 10 performs processing to identify the user in charge of the work of the specific work category. In this embodiment, the user in charge includes the cooperating company (contractor) in charge of the work, or the actual worker belonging to the cooperating company.

登録受付部101は、ユーザである元請業者の担当者に選択された特定作業分類の入力を受け付け、現場情報及び/又は作業情報に基づいて、特定作業分類の作業を担当する担当ユーザである業者を特定する。本実施形態では、現場情報として上述した施工体制を利用することができる。また、施工体制に基づいて、作業を担当する担当者(協力会社に属する作業者)を特定することもできる。 The registration reception unit 101 receives input of a specific work category selected by the user, who is the person in charge of the prime contractor, and identifies the contractor, who is the user in charge of the work of the specific work category, based on the site information and/or work information. In this embodiment, the above-mentioned construction system can be used as the site information. In addition, the person in charge of the work (a worker belonging to a cooperating company) can also be identified based on the construction system.

例えば、元請業者の担当者に鉄筋の作業計画書が選択されている場合、施工体制(及び作業情報)に基づいて、当該作業計画書の担当ユーザが自動的に特定される。上述のとおり施工体制には、協力会社同士の従属関係や担当業種等が示されており、これらの情報に基づいて担当ユーザを特定することができる。このように本実施形態では、協力会社同士の複雑な従属関係のもとで作業が進められる施工現場において、ユーザはこの複雑な従属関係を考慮しながら担当ユーザを設定する必要はなく、担当者が作業計画書を選択することで自動的に担当ユーザが特定されるのである。 For example, if a rebar work plan is selected by a prime contractor's person in charge, the user in charge of that work plan is automatically identified based on the construction structure (and work information). As described above, the construction structure indicates the subordinate relationships between cooperating companies and the industries in charge, and the user in charge can be identified based on this information. Thus, in this embodiment, at a construction site where work is carried out under complex subordinate relationships between cooperating companies, the user does not need to set the user in charge while taking these complex subordinate relationships into consideration, and the user in charge is automatically identified when the person in charge selects the work plan.

そしてS206において、登録受付部101は、施工現場と、特定作業分類と、特定された担当ユーザと、を対応付け、担当ユーザが成果物を入力可能な成果物タスクを登録する。担当ユーザは、作業端末3を介して登録された成果物タスクに作業実績などを登録することができる。そして元請業者の担当者(管理者)は、管理端末2を介して当該成果物タスクに登録された作業実績等を確認することができる。 In S206, the registration reception unit 101 associates the construction site, the specific work category, and the identified responsible user, and registers a deliverable task into which the responsible user can input a deliverable. The responsible user can register work results and the like in the registered deliverable task via the work terminal 3. The person in charge (manager) of the prime contractor can then check the work results and the like registered in the deliverable task via the management terminal 2.

本実施形態では、図7に示すような複数の項目を備えた成果物タスクを登録することができる(詳細は後述)。この成果物タスクは、管理端末2及び作業端末3のいずれもが閲覧可能である。例えば、同一の成果物タスクに対して複数の作業端末3が編集可能な構成にすることもできる。本実施形態では、S201~S206までの一連の処理を実行することで、所定条件に基づいた担当ユーザが自動で設定され、且つ、ユーザの要求に対応した成果物タスクを簡単に登録、閲覧等することができる。 In this embodiment, a deliverable task having multiple items as shown in FIG. 7 can be registered (details will be described later). This deliverable task can be viewed by both the management terminal 2 and the work terminal 3. For example, the same deliverable task can be configured to be editable by multiple work terminals 3. In this embodiment, by executing a series of processes from S201 to S206, a responsible user based on predetermined conditions is automatically set, and deliverable tasks that meet the user's requirements can be easily registered and viewed.

<表示処理>
図7には、本発明の一実施形態に係るユーザ端末における表示処理結果の一例を示す。図7は、管理端末2における表示処理結果を示している。同図に示すように、表示画面W10には、複数の成果物タスクW20が一覧W30で表示される。情報処理装置10の表示処理部103は、ユーザ端末からの表示要求操作に基づいて成果物タスクを表示処理し、その表示処理の結果をユーザ端末へ送信する。
<Display processing>
Fig. 7 shows an example of a display processing result in a user terminal according to an embodiment of the present invention. Fig. 7 shows a display processing result in the management terminal 2. As shown in the figure, a display screen W10 displays a list W30 of a plurality of deliverable tasks W20. The display processing unit 103 of the information processing device 10 displays the deliverable tasks based on a display request operation from the user terminal, and transmits the display processing result to the user terminal.

この成果物タスクW20は、文書分類(作業分類)、成果物名称、元請担当者、作業担当会社、作業担当者、完了期限、ステータス、保存先、コメント、種別、承認区分、などが並べて表示されている。表示処理部103は、これら複数の項目から、ユーザの選択要求に基づいて選択的に項目を表示処理することもできる。 This deliverable task W20 displays the document classification (work classification), deliverable name, prime contractor, work company, work person, completion deadline, status, save destination, comments, type, approval category, etc. The display processing unit 103 can also selectively display items from these multiple items based on the user's selection request.

本実施形態では、成果物タスクにおいて進捗状況を共有するためのコメント機能(コメント欄)を有する。成果物タスクは、施工現場における特定作業分類の作業に関連する複数のユーザが入力可能なコメント欄を含む。このコメント欄は、元請業者の担当者(管理者)と協力会社の作業者が情報を共有するために利用し、あるいは、後述する回覧グループに属するメンバー同士が情報を共有するために利用することもできる。例えば、このコメント欄において、現場に属する全てのメンバーで情報を共有し、あるいは所定条件に関連するメンバーで情報を共有することができる。図7では、未読のコメントの件数が表示されている。本実施形態においてコメントを利用する際、メンション先のユーザを指定することができる。また、例えばメンションされ、且つ未読の場合に、表示処理部103がその部分(アイコン)を強調表示させることで、ユーザに注意を促す(気づきやすくする)こともできる。 In this embodiment, the deliverable task has a comment function (comment field) for sharing progress. The deliverable task includes a comment field in which multiple users related to work of a specific work category at the construction site can enter comments. This comment field can be used by the person in charge (manager) of the prime contractor and the workers of the cooperating company to share information, or by members belonging to a circulation group described later to share information. For example, in this comment field, information can be shared by all members belonging to the site, or by members related to a specified condition. In FIG. 7, the number of unread comments is displayed. When using comments in this embodiment, the user to be mentioned can be specified. In addition, for example, when a comment has been mentioned and has not been read, the display processing unit 103 can highlight that part (icon) to alert the user (to make it easier to notice).

図7において、ユーザがコメントマーク部分(未読件数の左隣に位置するマーク)をタッチ操作すると、別ウィンドウで新たなコメント(及びコメントの履歴)が表示される(図示は省略)。このようにコメント機能を設け、表示処理部103がユーザの要求操作に応じて各ユーザの端末に表示処理することで、施工作業において適切な進捗確認(及び情報共有)を行うことができる。その結果、当該タスクにおける作業ミスを抑制することができる。 In FIG. 7, when the user touches the comment mark (the mark located to the left of the number of unread comments), a new comment (and comment history) is displayed in a separate window (not shown). By providing a comment function in this way and having the display processing unit 103 perform display processing on each user's terminal in response to a user's request, it is possible to appropriately check the progress of construction work (and share information). As a result, it is possible to reduce work errors in the task.

図7の表示画面W10では、例えば文書分類、元請担当者、作業担当者、ステータスなどを選択的に成果物タスクとして表示することもできる。この場合、表示処理部103は、ユーザ端末からの選択要求に基づいて指定された項目を含んだ成果物タスクを表示処理し、その表示処理結果を管理端末2へ送信する。 In the display screen W10 of FIG. 7, for example, document classification, prime contractor, worker, status, etc. can be selectively displayed as deliverable tasks. In this case, the display processing unit 103 displays the deliverable tasks including the items specified based on a selection request from the user terminal, and transmits the display processing results to the management terminal 2.

また、ユーザの希望に応じて一覧W30における成果物タスクW20の並び替えを行うこともできる。例えば、完了期限が近い順に並び替えを行うことができる。表示処理部103は、ユーザからの入力に基づいて所定条件で並び替えられた成果物タスクを表示処理し、その表示処理結果をユーザ端末へ送信する。このように本実施形態における成果物タスクの一覧W30では、ユーザが希望する項目に基づいて成果物タスクW20を表示でき、さらにユーザの選択要求に基づいて選択された複数の成果物タスクW20を一覧W30で表示することができる。 The deliverable tasks W20 in the list W30 can also be rearranged according to the user's wishes. For example, they can be rearranged in order of the closest completion deadline. The display processing unit 103 displays the deliverable tasks rearranged according to predetermined conditions based on input from the user, and transmits the display processing results to the user terminal. In this way, in the list W30 of deliverable tasks in this embodiment, the deliverable tasks W20 can be displayed based on the items desired by the user, and multiple deliverable tasks W20 selected based on the user's selection request can be displayed in the list W30.

表示画面W10には、「追加・編集」ボタン、「回覧・承認」ボタン、「データ出力」ボタン、「設定」ボタン、「リセット」ボタン、「高度な検索」ボタン、などを設けることもできる。 The display screen W10 may also have an "Add/Edit" button, a "Circulate/Approve" button, a "Data Output" button, a "Settings" button, a "Reset" button, an "Advanced Search" button, and so on.

「設定」ボタンは、ユーザからのタッチ操作に基づいて各種設定を行うための設定画面へ遷移するためのボタンであり、「リセット」ボタンは、ユーザが選択や編集などの実行途中で初期画面(図7に表示される表示画面)へ戻すためのボタンである。「データ出力」ボタンは、成果物タスクW20を、所定のフォーマットに落とし込んで出力等するためのボタンである。本実施形態では、施工現場において成果物タスクを紙ベースで提出するために、施工現場ごとのフォーマットに合わせた成果物タスクを出力することができる。 The "Settings" button is a button for transitioning to a settings screen for making various settings based on a touch operation by the user, and the "Reset" button is a button for returning the user to the initial screen (the display screen shown in FIG. 7) in the middle of selection, editing, etc. The "Data Output" button is a button for converting the deliverable task W20 into a specified format and outputting it, etc. In this embodiment, in order to submit the deliverable tasks on paper at the construction site, it is possible to output deliverable tasks that match the format of each construction site.

「検索」ボタンは、元請担当者などの検索項目W40を選択(スクロール)した後に成果物タスクの検索を実行するためのものである。図7では、文書分類、元請担当者、作成担当者、ステータス、などに基づいて成果物タスクの検索が可能である。「追加・編集」ボタンは、成果物タスクを追加し、あるいは編集するためのボタンである。「回覧・編集」ボタンは、後述する回覧グループを作成し、承認処理等を実行する際に利用されるものである。 The "Search" button is used to search for deliverable tasks after selecting (scrolling) a search item W40 such as the prime contractor responsible person. In FIG. 7, it is possible to search for deliverable tasks based on document classification, prime contractor responsible person, creation responsible person, status, etc. The "Add/Edit" button is used to add or edit deliverable tasks. The "Circulate/Edit" button is used to create a circulation group (described later) and perform approval processing, etc.

本実施形態では、完了期限までの期間が所定期間である場合(所定条件に該当する場合)に、「残り3日」などの表示を行うことができる。表示処理部103は、成果物タスク情報(完了期限、条件)に基づいて、残り期間を表示処理することができる。表示処理部103がこのような表示処理をすることで、ユーザは複数の成果物タスクの中から、期限の近い成果物タスクの状況を迅速に把握することができる。 In this embodiment, if the period until the completion deadline is a specified period (if specified conditions are met), a message such as "3 days remaining" can be displayed. The display processing unit 103 can display the remaining period based on the deliverable task information (completion deadline, conditions). By the display processing unit 103 performing such display processing, the user can quickly grasp the status of deliverable tasks with an approaching deadline from among multiple deliverable tasks.

図7において、ユーザから「高度な検索」W50のタッチ操作を受け付けると、図8に示すように、より詳細な検索を行うためのスペースが表示される。なお、図8では、「データ出力」ボタンなどの「高度な検索」W50の説明に不要なボタンを省略して図示している。 In FIG. 7, when a touch operation of "Advanced Search" W50 is received from the user, a space for performing a more detailed search is displayed as shown in FIG. 8. Note that in FIG. 8, buttons that are not necessary for explaining "Advanced Search" W50, such as the "Data Output" button, are omitted.

例えば図8では、作業担当者、完了期限、種別、承認区分、などの成果物タスクとして表示されている項目が検索項目として新たに表示される。このように本実施形態では、成果物タスクとして表示される全ての項目においてユーザが検索し、その結果を表示処理することができる。また、表示画面W10に「高度な検索」W50を設けることで、ユーザが不要なときにはこれら複数の項目を表示せず、必要に応じて適宜検索項目を表示させることができる(簡略化された閲覧しやすい画面を表示できる)。 For example, in FIG. 8, items displayed as deliverable tasks, such as the person in charge, completion deadline, type, and approval category, are newly displayed as search items. In this manner, in this embodiment, the user can search all items displayed as deliverable tasks and display the results. Furthermore, by providing an "Advanced Search" W50 on the display screen W10, the user can avoid displaying these multiple items when not needed, and can display search items as needed (a simplified, easy-to-view screen can be displayed).

なお、図7では管理端末2における表示処理結果を示しているが、例えば作業端末3でも同様の表示処理結果を閲覧することができる。この場合、対象となる成果物タスクに紐づけられた作業者(作業端末3)のみが当該成果物タスクを閲覧することができる。 Note that while FIG. 7 shows the display processing results on the management terminal 2, the same display processing results can also be viewed on, for example, the work terminal 3. In this case, only the worker (work terminal 3) associated with the target deliverable task can view the deliverable task.

例えば担当ユーザとしてのXX組(作成担当会社)が作業端末3から成果物タスクを閲覧する場合、図7(及び図8)において作成担当会社が「XX組」である成果物タスクのみ(1行目の「作業計画書」と4行目の「その他」)を閲覧することができる。 For example, when the responsible user, XX Group (creation company), views the deliverable tasks from the work terminal 3, he/she can view only the deliverable tasks for which the creation company is "XX Group" in Figure 7 (and Figure 8) ("Work plan" in the first line and "Other" in the fourth line).

<回覧グループ>
次に成果物タスクに対応する回覧グループについて説明する。図9には、本発明の一実施形態に係る書類管理システム1における承認処理の処理手順のフローチャートを示す。
<Circulation Group>
Next, a circulation group corresponding to a deliverable task will be described. Fig. 9 is a flowchart showing the procedure of approval processing in the document management system 1 according to an embodiment of the present invention.

S301において、情報処理装置10の作成処理部104は、回覧グループのメンバーを決定する。上述のとおり、この回覧グループを利用することで、すなわち、複数の回覧対象者(成果物確認者とも呼ぶ)から構成される回覧グループを導入することで、誰がどのタイミングで回覧(書類の確認)を完了しているか(または未だ確認していないか)をグループメンバーの全員が自身の端末から共有することが可能となる。 In S301, the creation processing unit 104 of the information processing device 10 determines the members of the circulation group. As described above, by using this circulation group, that is, by introducing a circulation group consisting of multiple circulation targets (also called deliverable reviewers), it becomes possible for all group members to share from their own terminals who has completed the circulation (document review) and when (or has not yet reviewed it).

図10には、本実施形態における回覧グループの作成画面の一例を示す。図10では、表示処理部103が回覧グループの作成画面を、表示画面W10に重ねて別ウィンドウとして表示させている。同図に示すように、ユーザから管理端末2を介して選択操作を受け付けることで、成果物タスクごとに回覧グループに含まれる成果物確認者を選択することができる。 Figure 10 shows an example of a circulation group creation screen in this embodiment. In Figure 10, the display processing unit 103 displays the circulation group creation screen as a separate window superimposed on the display screen W10. As shown in the figure, by accepting a selection operation from the user via the management terminal 2, it is possible to select a deliverable reviewer to be included in the circulation group for each deliverable task.

作成処理部104は、成果物タスク(及び/またはその他の書類管理)に関連する複数の成果物確認者で構成される回覧グループを作成処理する。具体的には、作成処理部104は、施工体制に基づいて、複数の成果物確認者を特定して回覧グループを作成処理することができる。 The creation processing unit 104 creates and processes a circulation group consisting of multiple deliverable checkers related to the deliverable task (and/or other document management). Specifically, the creation processing unit 104 can create and process a circulation group by identifying multiple deliverable checkers based on the construction system.

図10に示すように、施工体制(現場情報)に基づいて、成果物タスクに関連する成果物確認者の候補者が複数表示される。ユーザは、この候補者の中から適宜選択(回覧グループへの追加または削除)をすることができる。例えば図10のように、役職などの条件ごとに候補者の一覧を並び替えることもできる。 As shown in FIG. 10, multiple candidates for deliverable reviewers related to the deliverable task are displayed based on the construction system (site information). The user can select from these candidates as appropriate (add or remove from the circulation group). For example, as shown in FIG. 10, the list of candidates can be sorted according to criteria such as job title.

成果物確認者(回覧者)としては、例えば所長、工事長、課長など、現場を管理等する役職を有する担当者が該当する。なお、成果物確認者の役職はこれらに限られず、施工現場や成果物タスクの種別に応じて適宜設定することができる。また、作成処理部104は、施工体制に基づいて、成果物タスクに応じて自動で(施工体制に基づいて、複数の成果物確認者を特定して)回覧グループに属する成果物確認者を決定することもできる。 The deliverable reviewer (circulator) may be a person in charge of managing the site, such as a site manager, construction manager, or section manager. The title of the deliverable reviewer is not limited to these, and can be set appropriately depending on the type of construction site or deliverable task. The creation processing unit 104 can also automatically determine the deliverable reviewers who belong to the circulation group according to the deliverable task based on the construction system (by identifying multiple deliverable reviewers based on the construction system).

そして図11のように、選択された成果物確認者の中から、最終承認者を決定することができる。例えば従来であれば、成果物タスク(書類や文書)に記入された内容は、この作業に関連する部署や団体の対象者(上長など)にそれぞれ回覧し、最終的に承認を得る必要があるところ、この回覧グループを利用することで、回覧の手間を軽減可能なので、煩雑な作業をなくすことができる。この回覧グループは、元請会社や協力会社同士の複雑な従属関係を有する施工現場で利用することで、特に大きな効果を発揮する。 As shown in Figure 11, the final approver can be selected from among the selected deliverable reviewers. For example, conventionally, the contents entered in the deliverable task (paperwork or document) would have to be circulated to the appropriate individuals (such as superiors) in the departments and organizations related to the work, and ultimately approved. However, by using this circulation group, the effort required for circulation can be reduced, eliminating cumbersome work. This circulation group is particularly effective when used at construction sites with complex subordinate relationships between prime contractors and partner companies.

S302において、作成処理部104は、承認者を決定する。図11では、複数の成果物確認者のうち、「所長の田中一郎」が最終承認者として選択されている。この承認者は必ずしも1人である必要はなく、成果物タスクに応じて複数人を設定することもできる。例えば回覧グループに属する複数の成果物確認者に、権限順位を設定することもできる。この場合、権限順位に応じて後述する承認処理が可能となる。 In S302, the creation processing unit 104 determines the approver. In FIG. 11, "Director Tanaka Ichiro" is selected as the final approver from among multiple deliverable checkers. This approver does not necessarily have to be one person, and multiple people can be set depending on the deliverable task. For example, an authority ranking can be set for multiple deliverable checkers belonging to a circulation group. In this case, the approval process described below can be performed depending on the authority ranking.

S303において、作成処理部104は、管理端末2からの操作に基づいて、成果物タスクの回覧グループを登録する。図11では、成果物確認者及び最終承認者が選択済みであるので、ユーザが「回覧・承認申請」をタッチ操作することで、特定の成果物タスクに紐づけて回覧グループが登録される。 In S303, the creation processing unit 104 registers a circulation group for the deliverable task based on the operation from the management terminal 2. In FIG. 11, the deliverable reviewer and final approver have already been selected, so when the user touches "Circulation/Approval Request", a circulation group is registered in association with a specific deliverable task.

S304において、作業者(作業端末3)は回覧グループに回覧(及び承認)の申請をする。この回覧の申請は、作業者による全ての作業が完了したタイミングであっても良いし、あるいは作業の途中段階において行うようにすることもできる。 In S304, the worker (work terminal 3) applies for circulation (and approval) to the circulation group. This application for circulation may be made when the worker has completed all of the work, or may be made at an intermediate stage of the work.

図12には、回覧グループの申請に関する申請画面W60の表示処理結果の一例を示す。同図に示すように作業者は、作業端末3を介して申請を希望する成果物タスクW20を選択することができる。また、作業者は複数の成果物タスクW20を選択し、一括して申請操作を行うこともできる。このように複数の成果物タスクを一括して申請できるようにすることで、複数の施工作業等を担当する作業者の利便性を向上させることができる。 Figure 12 shows an example of the display processing result of the application screen W60 for a circulation group application. As shown in the figure, the worker can select the deliverable task W20 for which he/she wishes to apply via the work terminal 3. The worker can also select multiple deliverable tasks W20 and perform the application operation all at once. By being able to apply for multiple deliverable tasks all at once in this way, it is possible to improve the convenience of workers in charge of multiple construction tasks, etc.

なお、ユーザ(元請業者の担当者等)は、申請画面W60における「回覧者・承認者の選択」をタッチ操作することで、上述した図10の回覧グループの作成画面に遷移することができる。 The user (such as the person in charge at the prime contractor) can move to the circulation group creation screen shown in Figure 10 described above by touching the "Select viewer/approver" button on the application screen W60.

図9のS305において、回覧グループの各メンバーによる確認処理が行われる。本実施形態において各メンバーの確認処理の段階では、成果物タスクのステータスが回覧中となる。図11では、「田中一郎、山川武志、高橋健一、山田次郎、佐藤花子、伊藤明子」のメンバーが成果物確認者であるので、これらのメンバーは自身の管理端末2から成果物タスクの進捗等を確認し、確認を終えた段階で確認済みであることを示す確認済みフラグ(図示は省略)を設定することができる。登録受付部101は、複数の成果物確認者から書類管理に含まれる成果物の確認済みの入力を受け付け、この確認済みの入力に基づいて、各成果物確認者に確認済みフラグを対応付けて登録する。 In S305 of FIG. 9, confirmation processing is performed by each member of the circulation group. In this embodiment, at the confirmation processing stage of each member, the status of the deliverable task is circulating. In FIG. 11, the members "Tanaka Ichiro, Yamakawa Takeshi, Takahashi Kenichi, Yamada Jiro, Sato Hanako, and Ito Akiko" are the deliverable checkers, so these members can check the progress of the deliverable task from their own management terminals 2 and set a confirmation flag (not shown) indicating that the deliverable has been checked when they have finished checking. The registration reception unit 101 receives input of confirmation of deliverables included in the document management from multiple deliverable checkers, and registers each deliverable checker by associating it with a confirmation flag based on this confirmation input.

そしてS306において、予め設定した承認者による承認処理が行われる。承認処理部105は、複数の成果物確認者のうち、成果物タスクに含まれる成果物の承認権限を有する承認者からの入力に基づいて、当該成果物タスクを承認処理する。この承認処理が行われると、成果物タスクのステータスが完了となる。 Then, in S306, approval processing is performed by a preset approver. The approval processing unit 105 approves the deliverable task based on input from an approver who has approval authority for the deliverable included in the deliverable task, among multiple deliverable reviewers. When this approval processing is performed, the status of the deliverable task becomes completed.

本実施形態では、承認者以外の成果物確認者が確認中の場合であっても承認処理をすることができる。この場合、当該成果物タスクの進捗を未確認の成果物確認者に対し、送信部102がアラームを送信するように構成しても良い。例えば、承認処理部105は、承認者以外の成果物確認者の全員が確認を終えた後でなければ承認処理を受け付けない構成にすることもできる。 In this embodiment, approval processing can be performed even if a deliverable checker other than the approver is currently checking the deliverable. In this case, the sending unit 102 may be configured to send an alarm to a deliverable checker who has not yet checked the progress of the deliverable task. For example, the approval processing unit 105 may be configured not to accept approval processing until all deliverable checkers other than the approver have finished checking.

以上のように本発明に係る書類管理システム1によれば、現場情報及び作業情報を利用して所定の処理を実行することで、施工現場における書類管理を簡単且つ効果的に実現することができる。元請業者は、成果物タスクを簡単に設定することができ、さらに本書類管理システムではユーザが成果物タスクを選択することで自動的に担当ユーザを特定することができる。さらに回覧グループを利用することで、施工現場における成果物タスクの回覧で生じていた煩雑な作業をなくすことができる。 As described above, the document management system 1 according to the present invention can easily and effectively manage documents at construction sites by using site information and work information to execute specified processes. Prime contractors can easily set deliverable tasks, and this document management system can automatically identify the responsible user by having the user select a deliverable task. Furthermore, by using circulation groups, it is possible to eliminate the cumbersome work that occurs when circulating deliverable tasks at construction sites.

また、本実施形態では施工現場における書類管理について説明したが、書類書管理システム1を施工現場以外の他の分野で利用する場合にも本発明と同様の効果を得ることができる。 In addition, although this embodiment describes document management at a construction site, the same effects as the present invention can be obtained when the document management system 1 is used in fields other than construction sites.

1 書類管理システム
2 管理端末
3 作業端末
10 情報処理装置
11 制御部
12 記憶部
13 通信部
90 端末(管理端末2、作業端末3)
91 制御部
92 記憶部
93 通信部
94 入力部
95 出力部
101 登録受付部
102 送信部
103 表示処理部
104 作成処理部
105 承認処理部
NW ネットワーク
W10 表示画面
W20 成果物タスク
W30 一覧
W40 検索項目
W50 高度な検索
W60 申請画面
1 Document management system 2 Management terminal 3 Work terminal 10 Information processing device 11 Control unit 12 Memory unit 13 Communication unit 90 Terminal (management terminal 2, work terminal 3)
91 Control unit 92 Storage unit 93 Communication unit 94 Input unit 95 Output unit 101 Registration reception unit 102 Transmission unit 103 Display processing unit 104 Creation processing unit 105 Approval processing unit NW Network W10 Display screen W20 Deliverable task W30 List W40 Search item W50 Advanced search W60 Application screen

Claims (14)

施工現場における作業の成果物を管理する書類管理システムであって、
前記書類管理システムは、記憶部と、登録受付部と、を備え、
前記記憶部は、前記施工現場における担当業者の従属関係及び該担当業者に属する個人を含んだ施工体制と、前記作業の作業分類を含んだ作業情報と、を対応付けて格納し、
前記登録受付部は、前記施工現場に対応する複数の作業分類の中から、ユーザに選択された作業分類を示す特定作業分類の入力を受け付け、前記施工体制及び前記作業情報に基づいて、前記特定作業分類の作業を担当する担当ユーザを特定し、
前記施工現場と、前記特定作業分類と、特定された担当ユーザと、を対応付け、該担当ユーザが前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する、
書類管理システム。
A document management system for managing work deliverables at a construction site,
The document management system includes a storage unit and a registration reception unit.
The storage unit stores a construction organization including a subordinate relationship of a contractor at the construction site and individuals belonging to the contractor, in association with work information including a work classification of the work,
The registration reception unit receives an input of a specific work classification indicating a work classification selected by a user from among a plurality of work classifications corresponding to the construction site, and identifies a user in charge of the work of the specific work classification based on the construction organization and the work information ;
The construction site, the specific work classification, and the specified responsible user are associated with each other, and the responsible user is registered in the storage unit as a deliverable task that can be input by the deliverable task.
Document management system.
前記担当ユーザには、前記施工現場において作業を担当する担当業者が含まれ、
前記登録受付部は、前記ユーザに選択された前記特定作業分類の入力を受け付け、前記施工体制に基づいて、前記特定作業分類の作業を担当する担当業者を特定し、
前記施工現場と、前記特定作業分類と、特定された担当業者と、を対応付け、該担当業者が前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する、
請求項1に記載の書類管理システム。
The user in charge includes a contractor in charge of work at the construction site,
The registration reception unit receives an input of the specific work category selected by the user, and identifies a contractor in charge of the specific work category based on the construction system,
The construction site, the specific work category, and the specified contractor are associated with each other, and the specific contractor is registered in the storage unit as a deliverable task that can be input by the contractor.
The document management system according to claim 1 .
前記登録受付部は、前記担当業者に属する個人を含んだ前記施工体制に基づいて、前記特定作業分類の作業を担当する担当者を特定し、
前記施工現場と、前記特定作業分類と、前記担当業者と、特定された担当者と、を対応付け、該担当者が前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する、
請求項2に記載の書類管理システム。
The registration reception unit identifies a person in charge of the specific work classification based on the construction system including individuals belonging to the responsible contractor,
Correlating the construction site, the specific work classification, the contractor, and the specified person in charge, and registering the deliverable in the storage unit as a deliverable task that the person in charge can input.
The document management system according to claim 2 .
前記書類管理システムは、更に、作成処理部と、承認処理部と、を備え、
前記作成処理部は、前記成果物の書類管理に関連する複数の成果物確認者で構成される回覧グループを作成処理し、
前記承認処理部は、複数の成果物確認者のうち、前記成果物タスクに含まれる成果物の承認権限を有する承認者からの入力に基づいて、当該成果物を承認処理する、
請求項1に記載の書類管理システム。
The document management system further includes a creation processing unit and an approval processing unit.
The creation processing unit creates and processes a circulation group composed of a plurality of deliverable checkers related to document management of the deliverable,
the approval processing unit performs approval processing of the deliverable based on an input from an approver who has approval authority for the deliverable included in the deliverable task, among a plurality of deliverable confirmers;
The document management system according to claim 1 .
前記登録受付部は、複数の前記成果物確認者から前記書類管理に含まれる成果物の確認済みの入力を受け付け、該確認済みの入力に基づいて、各成果物確認者に確認済みフラグを対応付けて登録する、
請求項4に記載の書類管理システム。
the registration reception unit receives inputs of confirmation of the deliverables included in the document management from the plurality of deliverable checkers, and registers each deliverable checker by associating a confirmation flag with each deliverable checker based on the confirmation inputs;
The document management system according to claim 4.
前記作成処理部は、前記施工体制に基づいて、複数の成果物確認者を特定して前記回覧グループを作成処理する、
請求項4に記載の書類管理システム。
The creation processing unit identifies a plurality of product checkers based on the construction system and creates and processes the circulation group.
The document management system according to claim 4.
前記作成処理部は、前記施工体制に基づく成果物確認者の候補から、ユーザからの選択入力を受け付けて複数の成果物管理者を決定する、
請求項6に記載の書類管理システム。
the creation processing unit accepts a selection input from a user and determines a plurality of deliverable managers from among candidates of deliverable checkers based on the construction system;
The document management system according to claim 6.
前記登録受付部は、ユーザから、複数の成果物管理者における権限順位の入力を受け付け、
前記作成処理部は、前記権限順位に基づいて、複数の成果物管理者における権限順位が設定された前記回覧グループを作成処理する、
請求項4に記載の書類管理システム。
the registration reception unit receives an input of an authority ranking among a plurality of deliverable managers from a user;
the creation processing unit creates and processes the circulation group in which authority rankings among a plurality of deliverable managers are set based on the authority rankings;
The document management system according to claim 4.
前記書類管理システムは、更に表示処理部を備え、
前記表示処理部は、各担当ユーザがそれぞれの成果物を入力するための複数の成果物タスクを、前記施工現場に関連するユーザが一覧で閲覧可能に表示処理する、
請求項1に記載の書類管理システム。
The document management system further includes a display processing unit,
The display processing unit displays a plurality of deliverable tasks for each user to input their respective deliverables in a list viewable by users related to the construction site.
The document management system according to claim 1 .
前記作業情報は、成果物の進捗を示すステータスを含み、
前記表示処理部は、前記施工現場と、前記特定作業分類と、前記担当ユーザと、前記ステータスと、が対応付けられた成果物タスクを表示処理する、
請求項9に記載の書類管理システム。
The work information includes a status indicating a progress of a deliverable,
The display processing unit displays a deliverable task in which the construction site, the specific work classification, the responsible user, and the status are associated with each other.
The document management system according to claim 9.
前記成果物タスクは、前記施工現場における特定作業分類の作業に関連する複数のユーザが入力可能なコメント欄を含む、
請求項1に記載の書類管理システム。
The deliverable task includes a comment field that can be input by a plurality of users related to work of a specific work classification at the construction site,
The document management system according to claim 1 .
前記成果物タスクは、属性の異なる複数のユーザが前記成果物を入力可能である、
請求項1に記載の書類管理システム。
The deliverable task allows a plurality of users with different attributes to input the deliverables.
The document management system according to claim 1 .
施工現場における作業の成果物を管理する書類管理システムが実行する書類管理方法であって、
前記書類管理システムは、記憶部と、登録受付部と、を備え、
前記記憶部が、前記施工現場における担当業者の従属関係及び該担当業者に属する個人を含んだ施工体制と、前記作業の作業分類を含んだ作業情報と、を対応付けて格納するステップと、
前記登録受付部が、前記施工現場に対応する複数の作業分類の中から、ユーザに選択された作業分類を示す特定作業分類の入力を受け付け、前記施工体制及び前記作業情報に基づいて、前記特定作業分類の作業を担当する担当ユーザを特定するステップと、
前記登録受付部が、前記施工現場と、前記特定作業分類と、特定された担当ユーザと、を対応付け、該担当ユーザが前記成果物を入力可能な成果物タスクとして前記記憶部へ登録するステップと、を含む、
書類管理方法。
A document management method executed by a document management system that manages work deliverables at a construction site, comprising:
The document management system includes a storage unit and a registration reception unit.
The storage unit stores a construction organization including a subordinate relationship of the contractors at the construction site and individuals belonging to the contractors in association with work information including a work classification of the work;
The registration reception unit receives an input of a specific work classification indicating a work classification selected by a user from among a plurality of work classifications corresponding to the construction site, and identifies a user in charge of the work of the specific work classification based on the construction organization and the work information ;
The registration reception unit associates the construction site, the specific work classification, and the specified responsible user, and registers the deliverable in the storage unit as a deliverable task that the responsible user can input.
Document management methods.
施工現場における作業の成果物を管理する書類管理プログラムであって、
コンピュータを、記憶部と、登録受付部と、として機能させ、
前記記憶部は、前記施工現場における担当業者の従属関係及び該担当業者に属する個人を含んだ施工体制と、前記作業の作業分類を含んだ作業情報と、を対応付けて格納し、
前記登録受付部は、前記施工現場に対応する複数の作業分類の中から、ユーザに選択された作業分類を示す特定作業分類の入力を受け付け、前記施工体制及び前記作業情報に基づいて、前記特定作業分類の作業を担当する担当ユーザを特定し、
前記施工現場と、前記特定作業分類と、特定された担当ユーザと、を対応付け、該担当ユーザが前記成果物を入力可能な成果物タスクとして前記記憶部へ登録する、
書類管理プログラム。
A document management program for managing work deliverables at a construction site,
A computer is caused to function as a storage unit and a registration acceptance unit,
The storage unit stores a construction organization including a subordinate relationship of a contractor at the construction site and individuals belonging to the contractor, in association with work information including a work classification of the work,
The registration reception unit receives an input of a specific work classification indicating a work classification selected by a user from among a plurality of work classifications corresponding to the construction site, and identifies a user in charge of the work of the specific work classification based on the construction organization and the work information ;
The construction site, the specific work classification, and the specified responsible user are associated with each other, and the responsible user is registered in the storage unit as a deliverable task that can be input by the deliverable task.
Document management program.
JP2024034551A 2024-03-07 2024-03-07 Document management system, document management method, and document management program Active JP7561402B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2024034551A JP7561402B1 (en) 2024-03-07 2024-03-07 Document management system, document management method, and document management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2024034551A JP7561402B1 (en) 2024-03-07 2024-03-07 Document management system, document management method, and document management program

Publications (1)

Publication Number Publication Date
JP7561402B1 true JP7561402B1 (en) 2024-10-04

Family

ID=92909798

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2024034551A Active JP7561402B1 (en) 2024-03-07 2024-03-07 Document management system, document management method, and document management program

Country Status (1)

Country Link
JP (1) JP7561402B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004355526A (en) 2003-05-30 2004-12-16 Toshiba Corp Job navigation system and its method
JP2005242849A (en) 2004-02-27 2005-09-08 Okumura Corp Labor management system
WO2017130446A1 (en) 2016-01-29 2017-08-03 日揮株式会社 Project management device, project management system, project management method and program
JP2019091212A (en) 2017-11-14 2019-06-13 アズビル株式会社 Project management system and project management method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004355526A (en) 2003-05-30 2004-12-16 Toshiba Corp Job navigation system and its method
JP2005242849A (en) 2004-02-27 2005-09-08 Okumura Corp Labor management system
WO2017130446A1 (en) 2016-01-29 2017-08-03 日揮株式会社 Project management device, project management system, project management method and program
JP2019091212A (en) 2017-11-14 2019-06-13 アズビル株式会社 Project management system and project management method

Similar Documents

Publication Publication Date Title
US9070104B2 (en) Cross-context task management
US8302096B2 (en) Methods and systems to perform individual tasks as a composite task
US8631021B2 (en) Systems and methods for managing organizational information
WO2014013551A1 (en) Workflow management device and workflow management method
JP7561414B2 (en) Construction management system, construction management method, and computer program for construction management
US20190266544A1 (en) Techniques for managing process-flows across an enterprise
JP7277877B2 (en) Signboard-based business processing device and business processing method
JP2010231286A (en) Pharmaceutical student practice training support system
JP7561402B1 (en) Document management system, document management method, and document management program
JP2017182405A (en) Business management device, information processing method, and business management program
JP2002021327A (en) Construction inspection system, construction inspection information display device, and construction inspection method for building
JP2017016307A (en) Workflow information management device and program for the same
US11481702B1 (en) Worksite information management system
KR20230040312A (en) Management server for members of union for proceeding reconstruction project and operation method of the same
US20170185932A1 (en) Computer System and Method for Organizing Project Data
JP7270943B1 (en) Chat management program, chat processing program, chat management device, chat system, and chat processing method
JP2007079900A (en) Human resource matching system and matching method
KR102356358B1 (en) Method and Computer-Readable Medium for Cooperation Platform that Provides a Management Interface for Work of Project Type with Milestone Information
JP2015132985A (en) Meeting setting system
JP7244037B1 (en) CONSTRUCTION MANAGEMENT SYSTEM, CONSTRUCTION MANAGEMENT METHOD, AND CONSTRUCTION MANAGEMENT PROGRAM
JP7072957B1 (en) Programs, information processing equipment, and information processing methods
US20240127145A1 (en) System and Method for Labor Scheduling and Jobsite Management
JP2023167488A (en) Information service system, information service method and program
WO2024171525A1 (en) Processing device, processing program, and processing method
JP2002041741A (en) Business process management system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20240402

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20240402

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240618

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240808

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240910

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240912

R150 Certificate of patent or registration of utility model

Ref document number: 7561402

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150