Diploma Dce PROJECT
Diploma Dce PROJECT
Diploma Dce PROJECT
THOZHUOOR-VALANGIMAN-612804
SMALL BRIDGE
Submitted by
1
144 - GOVERNMENT POLYTECHNIC COLLEGE THOZHUVUR
VALANGAIMAN -612 804
BONAFIDE CERTIFICATION
2
ACKNOWLEDGEMENT
We would like to convey out sincere and whole hearted thanks to all
teaching and non-teaching staff and our students, friends for all their help in
completing this project work.
“SYNOPSIS”
3
The proposed “Bridge” of designing analysis of “Small Bridge” is to be
total area of 230 Sq if and build-up area 128.83 sq.ft area of located at
“MANALOOR” the total approximate estimate on a Bridge Rs. 912256.50/- the
total capacity of load transfering in a bridge 1 tonnes.
The amenities are planed as per general norms from PWD and necessary
elements provision the Bridge against earth quake and theft.
The Bridge elements are disigned by limit state method as per IS 456 –
2000, 275 part – 1, part – 2, 873 part – 5, NBC road and 59 of 1988 current
vechicles load increasing provision are followed current PWD scheduled rates will
be used in the cost of estimation.
Key word :
4
S.NO DISCRIPTION PAGE.NO
01 Introduction
02 Literature review
03 Specification
04 List of symbals
05 Design data
06 Data analysis
07 Detailed estimate
08 Abstract estimate
10 Conclusion
11 Bibliography
5
CHAPTER - 1
INTRODUCTION
The following are some of the advantages of steel bridges that have
contributed to their popularlity in europe and in many other developed
countries.
They could carry heavier loads over longer spans with minimum dead
weight loading to smalley foundations.
6
Greater effciency than concrete structures is invariably achived in resisting
seismic forces and blast loading.
All these frequently loads to low life india there are many engineers who
feel that corrosion is a problem in steel bridges, but in reality it is not so.
Corrosion in steel bridges can be effectively minimised by embloying newly
developed paints and special types of steel. These techniques are followed in
europe and other developed countries.These have been discussed in chapter
2.cycle costs in steel bridges.
These techniques are followed ineurope and other developed countries these
been disussed in chapter.
7
CHAPTER - II
LITERATURE REVIEW
8
Maintenance, Rehabilitation, Strengthening, Repairs and
Durability
GhoshKarbhari et al (2007)
The authors have concluded that the two rehabilitation schemes resulted
in enhancement of capacity of the specimens in conjunction with a better load
distribution resulting in thetransformation of failure mode from punching shear to
more ductile flexural failure. The specimen strengthened with wet layup based
fabric strips had a strength enhancement of around 73% and the specimen
strengthened with pultruded strips had a strength enhancement of around 59%, as
compared to the control specimen.
9
El-Hacha et al (2001)
Triantafillou (2001)
10
enhanced the out-ofplane flexural strength considerably when applied to masonry
walls.
Chiewanichakorn et al (2006)
studied the behavior of a truss bridge, where an FRP deck replaced an old
deteriorated concrete deck experimentally and validated through finite element
models. Finite element the Bentley Creek Bridge was developed using the pre-
processor package, MSC PATRAN and the analysis was performed using the
general purpose FEA package, ABAQUS to determine fatigue life of the bridge
when subjected to dynamic loading caused by AASHTO fatigue live load. Fatigue
life of all truss members, floor-beams and stringers were determined based on a
fatigue resistance formula in the AASHTO-LRFD design specifications. The
numerical results agreed well with experimental results. The results have 16shown
that fatigue life of FRP deck system almost doubled when compared with the
reinforced concrete deck system.
Soudki (1998)
12
flexural and shear capacity; precautions to ensure ductility or deformability; and
calculations of deformation and development length have been presented. Authors
concluded that all the three codes, JSCE, ACI and fib, use the same concept
ancalculating the respective strengths.
proposed a modified Genetic Algorithm (GA) based process for the optimal
design of GFRP bridge deck 19having a pultruded cellular cross-section and
surmised that the developed algorithm is capable of optimizing the structure and
material for GFRP deck system simultaneously. The results of the optimization
indicated that trapezoidal cross-section is an optimum shape for GFRP deck. The
stiffness of deck was identified as a critical parameter for the design. The results of
sensitivity analysis indicated that the geometrical design variables are more
sensitive than those of materials and that the deflection profile was greatly
influenced by the thickness of flanges, while the local buckling load was sensitive
for the dimension of the web.
Amjad et al (2005)
SreenivasAlampalli (2005)
Studied the structural behaviour and failure modes of a glass fibre reinforced
polymer web core skew bridge superstructure, using the standard FE analysis
16
package ABAQUS and MSC PATRAN, and investigated the shear transfer
capacity and the local buckling behaviour of the bridge superstructure. The
conclusion based on the study is that the FRP bridge design is controlled by
stiffness as reported by other researchers and when the superstructure deflection
meets the AASHTO requirement, the allowable live load is approximately 2 times
of HS-25 live load. It was established that when the superstructure
deflection meets the AASHTO requirement, the Tsai-Hill index is far below the
limit state (unit value). The shear stress failures at the interface of web-to-top or
web-tobottom surface do not occur prior other failure mechanisms and the deck
has significant safety factor to resist shear failure, as reported by the authors.
17
considered the variousfactorsthat affect the FRP box-girder behaviour and
developed a simplified, approximate and computationally efficient procedure for
the analysis of single cell FRP box-girder bridges made of blade angle or T
stiffened panels and validated the results by comparison with values available in
literature andresults obtained from FEA (MSC NASTRAN package). They
considered the stresses due to longitudinal bending moment, shear force, torsion,
distortion, shear-lag and transverse bending as well as instability of the flange
under compression and web under shear to propose the simplified analysis method.
It was mentioned that the simplified procedure is adequately accurate and very fast
for effectively analyzing the FRP box sections in the preliminary and optimum
design stages.
King et al (2012)
outlined the Load and Resistance Factor Design (LRFD) of Fibre Reinforced
Polymer composite (FRP) panel highway bridge deck. The deck would be of a
sandwich construction where 152.4 mm × 152.4 mm × 9.5 mm square pultruded
glass FRP (GFRP) tubes are joined and sandwiched between two 9.5 mm GFRP
plates. The deck would be designed by Allowable Stress Design (ASD) and LRFD
to support AASHTO design truckload HL-93. It was mentioned that there are
currently no US standards 22and specifications for the design of FRP pultruded
shapes including a deck panel therefore international codes and references related
to FRP profiles will be examined and AASHTO-LRFD specifications will be used
as the basis for the final design. Overall, years of research and laboratory and field
tests have proven FRP decks to be a viable alternative to conventional concrete
deck. Therefore, conceptualizing the design of FRP bridge decks using basic
structural analysis and mechanics would increase awareness and engineering
confidence in the use of this innovative material.
18
Experimental and Analytical Studies
19
CHAPTER - III
SPECIFICATION
If any privately owned service for water, electricity, drainage, etc., passing
through the site is affected by the works, the Contractor shall provide a satisfactory
alternative service in full working order to the satisfaction of the owner of the
services and of the Engineer before terminating the existing service. • Drawing and
scheduling the affected services like water pipes, sewers, cables, etc. owned by
various authorities including Public Undertakings and Local Authorities included
in the contract documents shall be verified by the Contractor for the accuracy of
the information prior to the commencement of any work. • Notwithstanding the
fact that the information on affected services may not be exhaustive, the final
position of these services within the works shall be supposed to have been
indicated based on the information furnished by different bodies and to the extent
the bodies are familiar with the final position. The Contractor must also allow for
any effect of these services and alternations upon the works and for arranging
regular meetings with the various bodies at the commencement of the contract and
throughout the period of the works in order to maintain the required co-ordination.
20
During the period of the works, the Contractor shall agree if the public utility
bodies vary their decisions in the execution of their proposals in terms of program
and construction, provided that, in the opinion of the Engineer, the Contractor has
received reasonable notice thereof before the relevant alterations are put in hand. •
No clearance or alterations to the utility shall be carried out unless ordered by the
Engineer. • Any services affected by the works shall be restored immediately by
the Contractor who must also take all measures reasonably required by the various
bodies to protect their services and property during the progress of the works. • The
Contractor may be required to carry out the removal or shifting of certain
services/utilities on specific orders from the Engineer for which payment shall be
made to him. Such works shall be taken up by the Contractor only after obtaining
clearance from the Engineer and ensuring adequate safety measures.
3.2As-Built :
ontractor shall maintain a fully detailed record of all changes from the approval to
facilitate easy and accurate preparation of the As-Built Drawing. Irrespective of the
other contractual prerequisites no Section of the Works will be considered
substantially completed until the Engineer has approved the respective As-Built
Drawings.ications.
21
3.3 National Specifications :
The Contractor may propose that the materials and workmanship be defined
in accordance with the requirements of other equivalent National Specifications
and he may execute the works in accordance with such National Specifications as
may be approved by the Engineer. A copy of the National Specification, together
with its translation into the English language if the National Specification is in
another language, shall be submitted to the Engineer along with the request for its
adoption.
Along with the commencement of the contract, the Contractor shall provide
in his site office at least one complete set of all National Specifications referred to
in these Specifications, if they are for the Sections applicable to the works. This set
shall be made available for use by the Engine.
Units of Measurement:
22
The Symbols for units of measurement are used in these Specifications as they are
given below.
M micron = m x 10-6
Mm = millimetre
M = meter
Km = kilometre
ha hectare
lit or I litre
rad radian
°C degrees Celsius
kg kilogram
g gram = kgx10-3
mg milligram = kg x 10-
23
Lin. m Linear meter
Max Maximum
Min Minimum
CR Crushing Ratio
dia Diameter
hr Hour
LS Linear Shrinkage
MC Moisture Content
min Minute
No Number (order) as in No 6
PI Plasticity Index
PL Plastic Limit
sec Second
SG Specific Gravity
TS Tensile Strength
UC Uniformity Coefficient
wt Weight % Percent
loss on 5 cycles
TS Tensile Strength
UC Uniformity Coefficient
wt Weight % Percent
25
3.4 QUALITY CONTROL
2.4.1Scope
direct This Section covers the Quality Control System and procedures,
Quality Assurance Plan, program of tests, trials, and general procedures for
acceptance as well as Laboratory arrangements and related facilities which are
required for the selection and control of the quality of materials and workmanship.
Testing Procedures And Set Of Tests For ensuring the quality of the work, the
materials and the workmanship shall be subjected to testing in accordance with
procedures, sets of tests and frequencies as specified in respective Sections of these
Specifications. The specified testing frequencies are not restrictive. The Engineer
shall for the tests to be carried out as frequently as deemed necessary that the
materials and workmanship comply with their Specifications
(a) Concrete
Laboratory trials for concrete mixes shall be carried out by the Contractor to
demonstrate that the composition of the mixes proposed for the concrete meets the
requirements of the Specifications.
Reports The Contractor shall prepare and submit four copies of Progress
Report on a monthly basis. The Reports shall highlight the targeted and achieved
progress, problems at site, and brief description of the claims during the month and
the Engineer's response, and other information relevant to the Project. It shall be
supplemented with necessary charts, tables, data, and at least 36 photographs. On
26
completion of the Works, the Contractor shall prepare and submit a Completion
Report that shall deal comprehensively on all aspects covered in the Monthly
Report. Additional information such as improvement in construction
methods/techniques, lessons learnt from the Project, important considerations for
maintenance, etc. should also be highlighted
The cost for these works shall be covered by the Contractor's overhead
included in unit rates of other items in the BOQ.
(C)Quality Of Materials
The materials supplied and used in the works shall comply with the
requirements of these Specifications. They shall be new, except as provided
elsewhere in the contract or permitted by the Engineer in writing. The materials
shall be manufactured, handled and used skilfully to ensure completed works to
comply with the contract.
(d)Cement
Ordinary and High Strength Portland Cement (OPC and HSPC), Portland
Slag Cement (PSC), Portland Pozzolana Cement (PPC) shall be sampled according
to IS 3535 and tested according to IS 4031.
Limes shall be sampled and tested in accordance with BS 890 and shall
comply with all requirements specified therein.
28
Normal curing of test
(ix) specimens (20° C BS 1881-111
method)
Accelerated curing of
(x) test specimens BS 1881-112
Making test cubes from BS 1881-108
(xi) fresh concrete
3.4.4Reinforcing Steel
3.4.5. Bricks
3.4.6. Mortar
29
3.5.1. Definitions
A pour refers to the operation of placing concrete into any mould, bay or
formwork, etc. and also to the volume which has to be filled. Pours in vertical
succession are referred to as lifts.
Fine aggregate shall be clean hard and durable and shall be natural sand,
crushed gravel sand or crushed rock sand complying with IS 383. AH the material
shall pass through a 4.75 mm IS sieve and the grading shall be in accordance with
IS 383. In order to achieve an acceptable grading, it may be necessary to blend
materials from more than one source. The deviation from the initial fineness
modulus shall be no more than ± 0.30 for ordinary concrete and ± 0.20 for high
quality concrete.
30
Coarse aggregate shall be clean hard and durable crushed rock, crushed
gravel or natural gravel corresponding to the following classes:
Class B: Aggregate shall consist of crushed quarry rock other than Class A
from an approved source.
3.5.2General
Mortar Mortar
31
shall comply with IS 2250-1981; Code of Practice for preparation and use of
masonry mortar. The mortar used in work shall have the strength not less than 5
N/mm2 or 7.5 N/mm2 at 28 days as specified. However, if provided in the
Contract, cement and sand may also be mixed in specified proportions. Cement
shall be proportioned only by weight, by taking its unit weight as 1.44 ton per
cubic meter and sand shall be proportioned by volume after making due allowance
for bulking. Mixing The mixing shall be done in a mechanical mixer unless hand-
mixing is permitted by the Engineer. If hand-mixing is allowed, the operation shall
be carried out on a clear watertight platform. in the required proportion cement and
sand shall be first mixed dry to obtain an uniform colour. Then required quantity of
water shall be added and the mortar shall be mixed to produce workable
consistency. The mortar shall be mixed for at least three minutes after addition of
water in the case of mechanical mixing
3.5.3Fine Aggregate
Fine aggregate shall be clean hard and durable and shall be natural sand,
crushed gravel sand or crushed rock sand complying with IS 383. AH the material
shall pass through a 4.75 mm IS sieve and the grading shall be in accordance with
IS 383. In order to achieve an acceptable grading, it may be necessary to blend
materials from more than one source. The deviation from the initial fineness
modulus shall be no more than ± 0.30 for ordinary concrete and ± 0.20 for high
quality concrete.
32
3.5.4 Coarse Aggregate
Coarse aggregate shall be clean hard and durable crushed rock, crushed
gravel or natural gravel corresponding to the following classes:
Class B: Aggregate shall consist of crushed quarry rock other than Class A
from an approved source.
33
.
3.6.1Tree cutting
3.6.2Removal of roots
In the site all trees up to 300 mm girth, stumps and roots shall be removed to
a depth of not less than 900 mm below the finished level and a minimum of 500
mm below the original ground level whichever is lower. Except in borrow areas
the cavities resulting from the grubbing shall be backfilled with approved material
and compacted to a density not less than the density of the surrounding ground.
3.6.3Site cleaning
Clearing shall consist of the cutting, removing and disposal of all trees,
bushes, shrubs, grass, weeds, other vegetation, anthills, rubbish, fences, top organic
soil not exceeding 150 mm in thickness and all other objectionable material,
resulting from the clearing and grubbing. It shall also include the removal and
34
disposal of structures that obtrude, encroach upon or otherwise obstruct the work.
The moving of a certain amount of soil or gravel material may be inherent to or
unavoidable during the process of clearing and no extra payment shall be made for
this. Clearing shall include the removal of all rocks and boulders of up to 0.15 m3
in size exposed or lying on the surface.
Conservation of Top Soil Where suitable topsoil exists within the limits of
the area to be cleared and grubbed, the Contractor shall, if ordered by the Engineer,
remove the topsoil together with any grass and other suitable vegetation. If not
used immediately, the topsoil shall be transported and deposited in stockpiles for
later use. Conservation of Flora Where provided for in the contract, certain
designated flora encountered in the road reserve and borrow areas shall be
carefully protected by the Contractor. In his tendered rate for Site Clearance, he
shall include for the careful removal and planting of the flora in a protected and
fenced-off area and, on completion of the road, for the replanting of the flora in
suitable positions in the road reserve in accordance with the Engineer's
instructions. Execution of Work Stumps, embedded logs, roots and all other
vegetation growth and accumulated rubbish of whatsoever nature and all other
objectionable material shall be completely removed to a specified depth.
3.6.5 Turfing
The area from where the grass roots are to be obtained shall be specified by
the Engineer-in-Charge at the time of execution of the work and no royalty shall be
charged on this account from the contractor. The soil shall be suitably moistened
and then the operation of planting grass shall be commenced. The grass shall be
dibbled at 10 cm, 7.5 cm, 5 cm apart in any direction or other spacing as described
in the item. Dead grass and weeded shall not be planted. The contractor shall be
35
responsible for watering and maintenance of levels and the lawn for 30 days or till
the grass forms a thick lawn free from weeded and fit for moving whichever is
later. Generally planting in other direction at 15 cm, 10 cm, spacing is done in the
case of large open spaces, at 7.5 cm spacing in residential lawn and at 5cm spacing
for Tennis Court and sports ground lawn. During the maintenance period, any
irregularities arising in ground levels due to watering or due to trampling by
labour, or due to cattle straying thereon, shall be constantly made up to the proper
levels with earth as available or brought from outside as necessary, Constant watch
shall be maintained to ensure that dead patches are replanted and weeds are
removed
In ordinary soil, including refilling earth after mixing with oil cake, manure
and watering. Holes of circular shape in ordinary soil shall be excavated to the
dimensions described in the items and excavate soil broken to clods of size not
exceeding 75 mm in any direction, shall be stacked outside the hole, stones, brick
bats, unsuitable earth and other rubbish, all roots and other undesirable growth met
with during excavation shall be separated out and unserviceable material removed
from the size as directed. Useful material, if any, shall be stacked properly and
separately. Good earth in quantities as required to replace such discarded stuff shall
be brought and stacked at site by the contractor. The tree holes shall be manured
with powdered Neam/castor oil cake at the specified rate along with farm yard
manure over sludge shall be uniformly mixed with the excavated soil after the
manure has been broken down to powder, (size of particle not be exceeded 6 mm
in any direction) in the specified proportion, the mixture shall be filled in to the
hole up to the level of adjoining ground and then profusely watered and enable the
soil to subside the refilled soil shall then be dressed evenly with its surface about
36
50 to 75 mm below the adjoining ground level or as directed by the Engineer-in-
charge. Tree Guard The tree guard shall be 450 mm in diameter and 1 meter high
above ground level and 25 cm in below ground level. The tree guard shall be
framed of 4 nos. 20 x 3 mm MS. Flat welded to 50x50 wire mesh. The entire tree
guard shall be given two coats of synthetic enamel paint of approved brand and
manufacturer of required shade brand and manufacturer of required shade over a
priming coat of ready mixed steel primer of approved brand and manufacturer.
The job includes the activities like soil investigation works, bore hole of
required depth including mobilization and demobilization of drilling machines
(Rotary or percussion), Field test (SPT, Field density test,vane shear test), lab test
(consolidation, direct shear test, unconfined compression test, chemical
test ,specific gravity test, seive analysis, moisture content, atterbergs limits tests
etc.) and preparation of soil analysis report
LIST OF SYMBOLS
a - Lever arm
37
Df - Thickness of flange
DL - Dead load
d - Effective depth
EL - Earthquake load
e - Eccentricity
F - Resisting force
fd - Design strength
hs - Heigth of stem
K -Stiffness of member
Ld - Development length
LL - Live load
M -Bending moment
Mr -Moment of resistance
39
m -Modular ratio
q - Shear stress
Q -design coefficient
r - Radius
Sv - Spacing of stirrups
T - Torsional moment
V - Shear force
WL - Wind load
Z - Modulus of section
g - Displacement
φ- Diameter of bar
ψ- Creep coefficient
ϑ - Possion's ratio
DEIGN SLAB
LENGTH =6m
KREBS = 200mm
ALLOWEABLE STRESS
Σ SI=200 N/MM2
DEPTH OF SLAB
=10.8 KN/m2
43
Impact factor of class AA tracked vehicle is 25% for 5ms pan decreasing linearly
to 10% for 9m span for 6.4m span
=20.5%
Be =kx (1-x/l)+bw
44
[4.18/9]
= [126.34 – 42.58]
= 83.75 KN.m
=83.75 + 55.44
=139.19 KN.m
Be =2.29m
=54.03 KN
=35.77
=89.8KN
45
DESIGN OF DECK SLAB
D=
√[ ]n
QB
D =355mm
= [139.19 x10^6]/[200x0.90x385]
=244mm c/c
= [0.3x83.75+0.2x55.44]
=36.21 KN.m
= 367.5mm
46
AST = [36.21x10^6]/[240x0.90x367.5]
= 456 mm2
=248~250mm c/c
Where,
B=width of section
D=effective depth
= [89.8x103/1000x385]
=0.23 N/MM2
AS = [1000x491/300]
= 1636.66mm2
P =[100AS/bd]
=163666/385000
=0.425
K1 = [1.14-6.7d]
= [1.14- (0.7x0.385)]
47
=0.8705
K2 = [0.5+0.25x0.425]
=0.606
τc = [k1,k2, τc]
=[0.8705x0.40]
=0.3482 N/mm2
SINCE τ<τC ,The shear stress are with in safe permissible limits
PIER DESIGN
P =207.26 KN/M2
=2487 KN
=2487 *1.5
=3730 KN
AC=Ag -Asc
AC =0.99AC
48
PU = 0.4x25x0.99Ag +0.67x415x0.01Ag
3730*10^3 =12.68Ag
Ag =2941640 N/mm2
SINCE it is rectangular column assume the breath to depth ratio as 0.2B =0.5D
Ag=B*D
Ag=0.5D*D
=0.5D2
= [294.152*10^3/0.5] =D2
0.2B=0.5xD
=0.5x800
B= [0.5x800]/2
=2000mm~1900mm
SIZE =800x1900mm
STEP:2
Ag= 800x1900=1520x103
Pu=0.4fckAC+0.67 FyAsc
AC= Ag -Asc
AC=1520x10^3-Asc
Asc=42790.52mm2
=0.8x1520x103
Asc min=12160mm2
= [6/100]x1520^3
=912000mm2
Ascmini<Asc<Asc max
12160<42790<91200 Hence ok
STEP:3
=[42790.52/[π/4][252]]
=[42790.52/[0.785x625]]
= 87 bars
=42706mm2
=1/4x 25
50
=6.25mm
Pitch:
SPACING:-
Spacing,s={B-2[CC]-φ/2-φ/2 }/2
S= {1900-2(40)-(25/2)-(25/2)}/2
=897mm
DESIGN OF FOOTINGS
Rectangular footing (uniformly distributed)
DATA:
10/100x3730=373 KN
=10/100x3730=373 KN
=20.51mm2
51
STEP :3
= lxb
=1900/800
=2.3
l=2.3b
areaqd =2.3bxb
20.53 =2.3b2
B=√ ¿)
=2.9~3m
L=3x2.3
=6.67m~6m
STEP :4
=3730x1.5/1.8=310KN/m2
52
STEP:5
Design bending moment [mu] since it is rectangular footing calculating the design
b.m along both xx &gg and along yy
Myy = q0 [ Area at hatched portion x distance between ( G and face of the column)
Lp = ((60000-1900)/2) =2050mm
Mu = Qubd2
D= √
Mu
Qub
√ ¿ ¿= 3000
= 434 mm ~ 450 mm
D1 = 50 + 25/2 = 62.5
D’ = 62.5 mm
53
Overall depth is not sufficient to take care of shear so increase the depth by a 2
times.
= 2 x 15 = 30mm
STEP 7 :
1954 x 106 = 0.87 x 415 x Ast x 970 (1- 415 xAst)/(25 x 300)
X1 = 169531.96 x2 =5769.24mm2
= 5769.24/3.14/4 x 625
= 5769.24/0.785 x 625
= 5769.24/490.625
= 11.75 ~ 12 bars.
Along xx
1125.3 x 106 = 0.87 x 415 x Ast x 970 (1- 415x Ast/25 x600 x970)
X1 = 347359.27 X2 = 3243
54
Ast = 3243 m2
B=2
= 4.40 ~5 Nos
= 3243-2162/2
= 540.5 mm2
= 1.1 ~1 Nos
STEP 8 :
Ld = 0.87 fy φ / 4τ bd x 1.6
= 9026.25/8.96
55
Projection Length along yy = 2050mm
STEP 9 :
= 0.31 x 3000
Vu = 483.6 KN
= 483/2910000
= 0.160 N / mm2
Τc = 100Ast/bd
Τc = 576.924/2910000
56
= 0.31 x 6000 x 90
= 167.4 KN
= 0.057 N / mm2
= 100 Ast / bd
= 3245900/2910000
= 0.11 N/MM2
= 0.29 ForHenebook
= K =1
= 4 x 106 N
= 1.37 N / mm2
τc = 0.25√ fck
57
= 0.25√ 25
Ks = 0.5 + fc
= 800/1900 = 0.42
Ks = 0.75 + 0.42
= 1.17
STEP 10:
DATA ANALYSIS
58
SL.NO
DESCRIPTION PER RATE
1. Mason I class Each RS.550/day
2. Mason II class Each RS.500/day
59
720KG Cement 8240 Tonne 5932.80
1m
3
Sand 606.4 1m
3
606.4
60
1 m3 Mixing charges 130 1 m3 130
RATE FOR 1 m2=310.952/ m2
61
21 Nos Mazdoor I class 400 Each 8400
35 Nos Mazdoor II class 350 Each 12250
RATE FOR 1 m3=6709.84/m3
62
24 Nos Mazdoor II class 350 Each 8400
RATE FOR 1 m3=64460.33
64
RATE FOR 1 m3= 3377.83
65
CC 1:4:8 USING 40mm HBG FOR FOUNDATION AND BASEMENT
10m3
66
BRICK MASONARY IN cm 1:6 USING I CLASS BRICK FOR
FOUNDATION & BASEMENT -1Om3
68
1.1 No Mazdoor II class 350 Each 385
Sundrise 10.00
TOTAL RATE = 2123.14/10m2
69
2.7 Nos Mazdoor II class 350 Each 945
Sundrise 35.00
TOTAL RATE = 2179.79/100m3
70
TOTAL RATE = 438588/100 KG
71
DETAILED ESTIMATE
S.
Description of N Lengt Breadt Dept
N Quantity
Work o h h h
o
1 Earth Work in 1 7 3.5 2.15 52.67 m³
Excavation 4 2 0.30 0.30 0.72 m³
i) Foundati
on
72
ii) Wing
Walls
53.39 m³
Sand Filling
i) Foundati
2 on
ii) Wing 1 605 3 0.15 2.925 m³
Walls 4 2 0.23 0.15 0.276 m³
3.201 m³
P.C.C. 1:4:8 in
Foundation
3
i) Foundation 1 6.5 3 0.15 2.925 m³
ii) P.C.C. Retain 4 2 0.23 0.15 0.276 m³
3.201 m³
Designing [1:1:2]
i) Foundati
on
4
Concrete 1 6.5 3 0.45 8.775 m³
ii) Piers 3 3.05 0.40 1.90 6.954 m³
iii) Slab 1 6 2 0.3 3.6 m³
Parapet Wall
5
Post[1:1:2] 6 0.23 0.23 0.60 0.190 m³
6 Parapet Wall 8 2.6 0.076 0.152 0.140 m³
73
Hand Slab
19.759 m³
½xbxh
Side Slope
7 ½x3x3
Area
4 4.5 m² 18 m²
Wing Walls
8
[1:1:2] 4 2 0.23 0.60 1.104 m³
Wearing Coat
9
[1:1:2] 1 6 2 0.100 1.2 m³
2.304 m
³
Shuttering [Foundation]
10 i) Length 2 6.5 0.45 5.85m²
ii) Breadth 2 3 0.45 2.7 m²
Pire
i) Length 6 1.90 3.05 34.77 m²
ii) Breadth 6 0.40 3.05 7.32 m²
Slab Shuttering
i) Length 2 6 0.3 3.6 m²
ii) Breadth 2 2 0.3 1.2 m²
Parapet Wall 24 0.23 0.60 3.31 m²
Returns Wall 4 2 0.60 4.8 m²
74
11 Slab Centering 2 2.4 1.90 9.12 m²
72.67 m²
White Washing
Pire
12
i) Length 6 1.90 3.05 34.77 m²
ii) Breadth 6 0.40 3.05 7.32 m²
Slab
i) Length 2 6 0.30 3.6 m²
ii) Breadth 2 2 0.30 1.2 m²
Parapet Wall 24 0.23 0.60 3.31 m²
Parapet Wall Hand Slab 8 2.6 0.152 0.39 m²
50.59 m²
75
ABSTRACT ESTIMATE
76
ABSTRACT (ROD DETAILES QUNATITY)
TOTAL
PER 12.19 TOTAL
METER
DIAMETE NUMBER METER METER METER
OF
R OF BAR OF BARS OF BARS OF BARS OF BAR
(D^2/162)
WEIGTH WEIGTH WEIGTH
BAR
0.996
8 mm 12.15/12.19 =1nos 0.395 4.815 4.815
16.50
10 mm 201.15/12.19 =17nos 0.617 7.525 127.925
46.95
12 mm 572.66/12.19 =47nos 0.888 10.825 508.775
14.76
16 mm 180/12.19 =15nos 1.58 19.263 288.948
TOTAL 930.463
WEIGTH (kg)
77
S.N QYANTIT
DESCRIPTION RATE UNIT AMOUNT
o Y
Earth work
1 53.39 500 m3 26,695
excavation
Earth work sand m3
2 3.201 606.7 1,942.04
filling
Plain cement m3
3 3.201 5743.6 18,385
concrete 1:4:8
Rain force cement m3 2,12,073.3
4 19.759 10733
concrete 1:1:2 5
Side slope cement m3
5 14.4 5743.6 82,707.84
1:1:2
6 1.104 Returns walls 1:1:2 10733 m3 11,849..23
7 1.2 Wearing coat 1:1:2 393.34 m3 472.008
Shuttering &
8 72.67 150 m2 10,900.50
Centerings
White washing &
9 50.59 1.4 m2 708.25
Painting
10 930.46 Steel 50 ton 46523
TOTA 4,12,256.5
11
L 0
5,00,000.0
12 L.S L.S L.S
0
TOTAL 9,12,256.5
13
AMOUNT 0
78
REAL MODEL VIEW
79
80
81
CONCLUSION
CONCLUSION
82
83
BIBLIOGRAPHY
BIBLIOGRAPHY
84
1343:2012) revision)
Code of practice for concrete structures for storage
(IS3370(Part
of liquids: Part 1 General requirements (first
1):2009)
revision)
Code of practice for concrete structures for storage
IS 3370(Part
of liquids: Part 2 Reinforced concrete structures (first
2):2009
revision)
Code of practice for concrete structures for the
IS 3370(Part
storage of liquids: Part 3 Prestressed concrete
3):1967
structures
IS 3370(Part Code of practice for concrete structures for the
4):1967 storage of liquids: Part 4 Design tables
Code of practice for general construction in steel
IS 800:2007
(third revision)
Code of practice for use of cold formed light gauge
steel structural members in general building
IS 801:1975 construction (first revision)
Code of practice for use of structural steel in
overhead 1transmission line towers, Part 1 Materials,
IS 802):1995
Loads and
1/Sec
permissible stresses Section 1 Materials and Loads
(third revision)
IS 802):1992 Code of practice for use of structural steel in
1/Sec overhead 2transmission line towers Part 1 : Material,
loads and permissible stress Section 2 Permissible
85
stress (third revision)
Code of practice for use of structural steel in
overhead transmission line towers: Part 2
IS 802(Part Fabrication, galvanizing, inspection and packing 6 IS
2):1978 802(Part 3):1978 Code of practice for use of
structural steel in overhead transmission line towers:
Part 3 Testing
Code of practice for design, fabrication and
IS 803:1976 erection of vertical mild steel cylindrical welded oil
storage tanks (first revision)
Specification for rectangular pressed steel tanks
IS 804:1967
(first revision)
IS 7215:1974
Tolerances for fabrication of steel structures
87
Criteria for earthquake resistant design of
IS 1893(Part
structures: Part 4 Industrial structures including
4):2005
stack-like structure
IS Code of practice for earthquake resistant design
4326:2013 and construction of buildings (third revision)
IS Recommendations for seismic instrumentation for
4967:1968 river valley projects
IS Criteria for blast resistant design of structures for
4991:1968 explosions above ground
88
loads - Unit weights of building material and stored
materials (second revision) (Incorporating IS:1911-
1967)
Code of practice for design loads (other than
IS 875(Part
earthquake) for buildings and structures: Part 2
2):1987
Imposed loads (second revision)
Code of practice for design loads (other than
IS 875(Part
earthquake) for buildings and structures: Part 3 Wind
3):1987
loads (second revision)
Code of practice for design loads (other than
IS 875(Part
earthquake) for buildings and structures Part 4 Snow
4):1987
loads (second revision)
Code of practice for design loads (other than
IS 875(Part earthquake) for buildings and structures Part 5
5):1987 Special loads and load combinations (second
revision)
[IS 875(Part 3):1987]
Explanatory Handbook on Indian Standard Code of practice for
Design Loads (Other than Earthquake) for Buildings and Structures:
Part 3 Wind Loads
89
90
THANK YOU TO ALL
91