Pacific Process Engineering Profile
Pacific Process Engineering Profile
Pacific Process Engineering Profile
MISSION
Providing a competitive, efficient and inovative package equipment design and
supply.
COMPANY HISTORY
Pacific Process Engineering Continuously active since establishment in 2011 in
the field of Oil & Gas Industry.
In depth and detailed knowledge over years of experience in the field of Process
equipment packaging.
Engineering Support Petrochina Intl. Jabung Ltd. Gemah Field, Jambi – (Separator Internal)
*Worldwide experience list is available
i.e. Installation supervision, maintenance and
shutdown support and performance
troubleshooting.
INSTALATION BASED :
BOE Hydis
China
Regenerative Thermal Oxidizer (RTO) Semiconductor Fabrication Model: 60,000 SCFM Rotor Concentrator Wheel
Catalytic Oxidizers: Recuperative and with a Thermal Oxidizer
Regenerative Centerpoint Energy Field Services
USA
Thermal Recuperative Oxidizer
Gas Plant Model: 150 - 15,000 (23,550 Nm3/h) Regenerative Thermal
Direct-Fired Oxidizers: Multi-Jet and Oxidizer
Flameless Daxon Technology
Halogenated / Chlorinated Oxidizer Taiwan
Coating Model: 25,000 SCFM Regenerative Thermal Oxidizer Model: Three
Concentrators: Zeolite and Carbon (3) Bed 45,000 SCFM Regenerative Thermal Oxidizer
Remediation Systems Brady Corporation Malaysia Coating Model: 6,000 SCFM Regenerative
Thermal Oxidizer
Self-Cleaning Ceramic Filters Senoro Direct Fired Thermal Formosa Chemical and Fibre Company
Oxidizer – 55,200 Nm3/h Taiwan
Heat Exchangers & Energy Recovery
PTA Chemical Process Models (3): 90,000 SCFM Chlorinated Catalytic
Oxidizers and Scrubbers
ITW Industrial Packaging
Australia
Coating Model: 40,000 SCFM Regenerative Thermal Oxidizer
Senoro Gas Development Project
Indonesia
Gas Processing Plant - AGRU Tail Gas Oxidizer Model: 400 – 35,000 SCFM
(55,200 Nm3/h) Direct Fired Thermal Oxidizer
Catalytic Thermal Oxidizer – US
Based Installation
Ex’d Electric Heater Bundle Type Ex’e Electric Heater Bundle Type
TYPICAL APPLICATIONS:
• Pipeline Stations
• Chemical Plants
• Refineries
• Town Border Stations For
Distribution Systems
• Various Other Industrial Plants
FOX Portofolio:
• Industrial Automation Solution (PLC, DRIVES, CNC.)
• AMC & Segices
• Special Purpose Machines
• Automation IT (Plant, Airport…)
• Products
• Plant Engineering Services
Compressor Skid
Chiller Skid
Air Cooled Condenser
Economizer
Low Temp. Separator Skid
COMPANY EXPERIENCES
PROJECT : CONDENSATE STABILIZER – PONDOK MAKMUR
CLIENT : PT. RPE – PT. PERTAMINA EP
SITE LOCATION : BEKASI – WEST JAVA
COMPLETION : 2016
Economizer
Stabilizer Colum
Stabilizer Reboiler
Condensate Pre-Cooler
Reboiler Electric Immerse Heater
PLC Based Control Panel
COMPANY EXPERIENCES COMPANY EXPERIENCES
PROJECT : SPP GAS STATION PROJECT PROJECT : CRUDE DISTILLATION COLUMN (CDU)
CLIENT : PT. SUMBER PETRINDO PERKASA (PT.SPP) UPGRADING (10,000 BPD)
SITE LOCATION : RANDUBLATUNG (CEPU) – TAMBAK LOROK CLIENT : PT. PERTAMINA REFINERY UNIT (RU) VII
(SEMARANG - INDONESIA) SITE LOCATION : SORONG (WEST PAPUA – INDONESIA)
COMPLETION : 2013 COMPLETION : 2014
Engineering Assistance
Design Engineering and Supply for Top
Head Mist Eliminator, Still Column, and 1 unit Pre Filter
Flash Tank 2 units Dessicant Bed Tower
Supply of all Instrumentation and Manual (2 x 100%)
Valves 1 unit After Filter
1 unit Regeneration Gas Heater
1 unit Regeneration Gas Cooler
1 unit Regeneration Gas Scrubber
1 unit Explosion Proof Control Panel
COMPANY EXPERIENCES COMPANY EXPERIENCES
PROJECT : THERMAL OXIDIZER PROJECT : START UP FUEL GAS TREATER PACKAGE –
SENORO GAS DEVELOPMENT PROJECT DONGGI GAS DEVELOPMENT PROJECT
CLIENT : TRIPATRA – SAMSUNG CONSORTIUM CLIENT : PT. REKAYASA INDUSTRI
SITE LOCATION : SENORO (CENTRAL SULAWESI – INDONESIA) SITE LOCATION : DONGGI – (MID SULAWESI – INDONESIA)
COMPLETION : 2015 COMPLETION : 2015
Engineering
Project Management Team
Metering Orifice Type
Gas Chromatograph
Condensate Tank
Filter Coalescer
Piping System
Venting System
All Instrumentation & Manual Valve
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
1 11062 Gas Engine Generator, CNG Peaker Jambi project Supply of Gas Engine Generator Package, consist of: Client : PT Rekayasa Industri
- 1 x 600kW Gas Engine Generator, MWM type TCG2016 End User : PT PLN Area Sumbagsel
Principal : MWM
Site Location : Jambi, Sumatera
Year : Completed, 2012
2 11069 Fuel Gas System and Regulator Package Design and Supply of Fuel Gas Conditioning and Regulator Package, consist of: Client : Konsorsium Medco Power-Dalle Energy-TDIL
PLTMG 20-25 MW, Batam - 1 x Shutdown Valve End User : PT PLN Batam
(10 MMSCFD) - 2 x 100% Pressure Regulator Principal : N/A
- 1 x 100% Fuel Gas Scrubber Site Location : Panaran, Batam
- 2 x 100% Fuel Gas Coalescer Year : Completed, 2012
3 11079 Glycol Dehydration Package Distrik Cilamaya - Bid Proposal Preparation Client : PT Sanggar Sarana Baja
(60 MMSCFD) - Engineering Assistance End User : PT. Pertamina Gas (PERTAGAS)
- Design Engineering and Supply for Top Head Mist Eliminator, Still Column, and Flash Tank Principal : Cameron NATCO
- Supply of all Instrumentation and Manual Valves Site Location : Cilamaya, West Java
Year : Completed, 2013
4 12103 LTRO (Letang Tengah Rawa Optimization) - Engineering Assistance Client : PT Sanggar Sarana Baja
Expansion Project - Perform Pipe Stress Analysis End User : ConocoPhillips (Grissik) Ltd.
- Perform Equipment Foundation Design Principal : N/A
Site Location : Jambi, Sumatera
Year : Completed, 2013
5 12113 A/B Heater Treater Package, Bid Proposal Preparation Client : PT Sanggar Sarana Baja
Rantau Bais GS Upgrade Project Engineering Assistance End User : PT Chevron Pacific Indonesia
Design Engineering and Supply for Mist Eliminator Principal : Mackenzie Hydrocarbon, Australia
Design Engineering and Supply for Unit Control Panel, including BMS Site Location : Duri Field, Sumatera
Supply of Gas Burner and Fuel Gas Train Year : Completed, 2013
Site Commissioning
6 12154 Fuel Gas Package (5 MMSCFD) for Sei Gelam Gas Design and Supply of Fuel Gas Bypass System, including Supply of Fuel Gas Conditioning Client : PT Pembangunan Perumahan
Engine Powerplant Project, Jambi Package, consist of: End User : PT PLN Pembangkitan Sumbagsel
- 1 lot Bypass Pipeline Principal : N/A
- 1 x 100% Fuel Gas Coalescer Site Location : Jambi, Sumatera
Year : Completed, 2013
7 12123 Glycol Dehydration Package (20 MMSCFD), Design and Supply of Dehydration Package (Contactor and Regeneration Package), Client : PT Petroflex Prima Daya
Kuat Gas Facility Project - 1 unit Contactor Tower End User : EMP Mallaca Strait SA
- 1 unit Glycol Regeneration Package Principal : Rhine Ruhr, Australia
Site Location : Riau, Sumatera
Year : 2013, On-Hold
8 13185 Fuel Gas Package (1 MMSCFD) for Gas Engine Design and Supply of Fuel Gas Conditioning Package, consist of: Client : PT Euroasiatic Jaya
Generator - 1 x 100% Fuel Gas Scrubber End User : PT Pertamina Area Jambi
- 2 x 100% Fuel Gas Coalescer Principal : N/A
- 2 x 100% Fuel Gas Heater Site Location : Jambi, Sumatera
- 1 unit Control Panel Year : Completed, 2013
9 12118 Sub Cooler for Proyek Pemanfaatan Gas Air-Serdang Upgrading Refrigerant Sub Cooler Package Client : PT Titis Sampurna
Beringin End User : PT Titis Sampurna
Principal : Technical Asia Pte Ltd
Site Location : Palembang, South Sumatera
Year : Completed, 2013
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
10 12095 Internal Column for Gundih, PPGJ Project Design and Supply of Internals for Amine System Client : PT Inti Karya Persada Teknik
End User : PT Pertamina EP, PPGJ Project
Principal : Rhine Ruhr, Australia
Site Location : Gundih, Central Java
Year : Completed, 2013
11 13218 Internal Column Pertamina UP VII Sorong Replacement and Material Upgrading of CDU Column Internals Client : PT Pertamina RU VII
End User : PT Pertamina RU VII
Principal : Rhine Ruhr, Australia
Site Location : Sorong, Papua
Year : Completed, 2014
12 13184 CNG Peaker Muara Tawar 1. Bid Proposal Preparation Client : PT Pembangunan Perumahan
(20 MMSCFD CNG Plant) 2. Plant General Arrangement Design and 3D Modelling End User : PT PJB
3. Skid Design and Supply: Principal : N/A
- Plant Inlet Control 7 Flow Limiter Package Site Location : Muara Tawar, Bekasi, West Java
- Pre Treatment Package (Gas Scrubber & Filter), Year : Completed, 2014
- Pre Treatment Package (Gas Dryer),
- Pressure Reducing Unit (PRU) Package
- Hot Water Boiler Package,
- Hot Water Circulation Pump Package
- Ultrasonic Gas Metering Package (including Gas Chromatograph)
4. Site Installation Assistance
5. Commissioning and Start-Up Assistance
13 12104 Fuel Gas Package for Gas Turbine Power Plant Design and Supply of Fuel Gas Conditioning Package, consist of: Client : PT Dalle Engineering Construction
2 x 35 MW, Tanjung Uncang, Batam - 1 x 100% Fuel Gas Scrubber End User : PT Energi Listrik Batam (ELB)
(22 MMSCFD) - 2 x 100% Fuel Gas Coalescer Principal : N/A
- 2 x 100% Fuel Gas Heater Site Location : Tanjung Uncang, Batam
- 1 unit Control Panel Year : Completed, 2014
- 1 unit Closed Drain system
- 1 unit Venting System
- 1 unit Lube Oil Collecting System
14 12106 Gas Supply to Tambak Lorok Bid Proposal Preparation Client : PT Multifabrindo Gemilang
(60 MMSCFD Gas Plant) Review Plant General Arrangement End User : PT Sumber Petrindo Perkasa
Skid Design and Supply: Principal : N/A
- Plant Inlet Control Package Site Location : Randu Blatung & Tambak Lorok, Central Java
- Plant Inlet Metering Package, Year : Completed, 2014
- Slug Catcher Package,
- Compressor Discharge Scrubber Package
- Pig Launcher and Receiver Package
- Fuel Gas Conditioning Package,
- Gas Regulator Package
- Flare Package
- Flare KO Drum Package
- Sump Tank Package
- Instrument Air Receiver Package
- Utility Air Receiver Package
- Gas Filter and Metering Package
Supply of all Off-skid Instrumentation
Site Installation Assistance
Commissioning and Start-Up Assistance
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
15 12169 Thermal Oxidizer Package, Senoro Development Project Design,Supply, Installation Assistance and Commissioning of Regenerative Thermal Oxidizer Client : Tripatra- Samsung Consortium
(35,000 SCFM Acid Gas Flow) (RTO) Package, consist of: End User : JOB PERTAMINA – MEDCO E&P Tomori
- 1 unit Reaction Chamber Principal : Anguil, USA
- 1 unit Flue Gas Stack Site Location : Senoro, Central Sulawesi
- 1 unit Inlet Plenum System Year : Completed, 2016
- 2 units Gas Burner
- 2 units Gas Train
- 2 units Dillution Air Blower
- 2 units Combustion Air Blower
- 1 lot BMS and Control System
16 13205 Production Separator and Test Separator Package 1. Bid Proposal Preparation Client : PT Gatramas Internusa
for Permanent Block Tampi 2. General Arrangement Design and 3D Modelling End User : PT Seleraya Merangin Dua (SRMD)
3. Skid Design and Supply: Principal : N/A
- 2 Units Production Separator Package Site Location : Merangin, Jambi, Sumatera
- 1 Unit Test Separator Package Year : Completed, 2014
4. Site Installation Assistance
5. Commissioning and Start-Up Assistance
17 12159 Gas Dryer Package, South Payao Gas Facilities Design and Supply of Gas Dyer Package (Dessicant type Dehydration Package), consist of: Client : PT Indo Cipta Gemilang
(4.5 MMSCFD) - 1 unit Pre Filter End User : Petrochina International (Bermuda) Ltd
- 2 units Dessicant Bed Tower (2 x 100%) Principal : Pioneer, USA
- 1 unit After Filter Site Location : Sorong, Papua
- 1 unit Regeneration Gas Heater Year : Completed, 2014
- 1 unit Regeneration Gas Cooler
- 1 unit Regeneration Gas Scrubber
- 1 unit Explosion Proof Control Panel
18 12171 Chiller and Condensate Stabilizer Package Design and Supply of Chiller Package, consist of: Client : PT Raga Perkasa Ekaguna
(42 MMSCFD), Pondok Makmur Project - 2 units Refrigerant Compressor package End User : PT Pertamina EP, Pondok Makmur Development
- 1 unit Refrigerant Condenser Principal : Technical Asia Pte Ltd, Rhine Ruhr, EXHEAT UK
- 1 unit Gas Chiller Site Location : Pondok Makmur, Bekasi, West Java
- 1 unit Control Panel Year : Completed, 2016
19 13214 Start Up Fuel Gas Treater package Unit Design and Supply of Gas Treater Package (H2S Scavenger Package), consist of: Client : PT Rekayasa Industri
(1.0 MMSCFD), Donggi Gas Production Facility Project - 1 unit Pre Filter End User : PT Pertamina EP, Matindok Gas Development
- 2 units Scavenger Tower Principal : MI-Swaco (Schlumberger company)
- 1 unit Post Filter Site Location : Donggi, Banggai, Sulawesi
Year : Completed, 2016
20 14242 Fuel Gas Conditioning Unit Package Design and Supply of Fuel Gas Treatment Package, consist of: Client : PT Raga Perkasa Ekaguna
(2 MMSCFD) , Pondok Makmur project - 1 x 100% Fuel Gas Scrubber End User : PT Pertamina EP, Pondok Makmur Development
- 2 x 100% Fuel Gas Coalescer Principal : N/A
- 2 x 100% Fuel Gas Heater Site Location : Pondok Makmur, Bekasi, West Java
- 1 unit Control Panel Year : Completed, 2016
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
21 14238 Dew Point Control Unit Package, Matindok Gas Design and Supply of Refrigeration Package (c/w Gas Chiller and Dehydration Chiller Client : Konsorsium WIKA-Technip
Development (61.61 MMSCFD) Package), consist of: End User : PT Pertamina EP, Matindok Gas Development
(Direct order to Technical Asia Pte Ltd) - 2 units Refrigerant Compressor package Principal : Technical Asia Pte Ltd
- 1 unit Refrigerant Condenser Site Location : Matindok, Banggai, Sulawesi
- 2 units Feed Gas Chiller Year : Completed, 2016
- 1 unit Dehydration Chiller Package
- 1 unit Control Panel
22 14249 H2S Scavenger Unit Package, Matindok Gas Design and Supply of Chemical Injection Package (Liquid H2S Scavenger Injection Package), Client : Konsorsium WIKA-Technip
Development consist of: End User : PT Pertamina EP, Matindok Gas Development
- 1 unit Chemical Tank Principal : MI-Swaco (Schlumberger Company)
- 3 unit Injection Pumps Site Location : Matindok, Banggai, Sulawesi
- 1 unit Control Panel Year : On Progress
23 14263 Internal Column for RU VII Sorong Replacement and Material Upgrading of CDU Column Internals Client : PT Pertamina RU VII
End User : PT Pertamina RU VII
Principal : Rhine Ruhr, Australia
Site Location : Sorong, Papua
Year : Completed, 2016
24 14262 Design & Supply of Internals for various process Design, Internals Supply and CFD Simulation of : Client : Saipem-Tripatra-Chiyoda-Hyundai (STC) Consortium
Equipment, Jangkrik Plafform, ENI Muara Bakau - 1 unit Main Slug Catcher End User : ENI Muara Bakau BV
- 1 unit NE Slug Catcher Principal : Rhine Ruhr, Australia
- 1 unit MP Separator Site Location : Jangkrik Platform, Muara Bakau, East Kalimantan
- 1 unit LP Separator Year : Completed, 2016
- 3 units LT Separator
- 3 units Booster Compressor Suction Scrubber
- 1 unit Flash Gas Compressor 1st stage Suction Scrubber
- 1 unit Flash Gas Compressor 2nd stage Suction Scrubber
- 1 unit Flash Gas Compressor 3rd stage Suction Scrubber
- 1 unit HP Fuel Gas KO Drum
- 1 unit LP Fuel Gas KO Drum
- 1 unit Closed Drain Drum
25 13223 Gas Engine Generator, LNG Plant Wunut project Supply of Gas Engine Generator Package, consist of: Client : PT Nortech Asia Engineering
- 2 x 1500kW Gas Engine Generator, MWM type TCG2020-V16K End User : PT Bumi Tangguh Selaras
Principal : MWM
Site Location : Wunut, East Java
Year : On Progress
26 12171A Gas Engine Generator, Pondok Makmur project Supply of Gas Engine Generator Package, consist of: Client : PT Raga Perkasa Ekaguna
- 3 x 1200kW Gas Engine Generator, MWM type TCG2020-V12K End User : PT Pertamina EP, Pondok Makmur Development
Principal : MWM
Site Location : Pondok Makmur, Bekasi, West Java
Year : Completed, 2016
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
27 15274 EPC Manyar Offtake Station, Supply for EPC Manyar Offtake Station, consist of: Client : PT Yuan Sejati
Gresik-Lamongan-Tuban Gas Distribution Pipeline - PMT (Project Management Team) Contractor : PT PP (Persero)
(CP21A) Project - Engineering Works End User : PT PGN (Persero)
- Gas Filter Package Principal : N/A
- Gas Metering Package Site Location : Manyar, Gresik, East Java
- Gas Pressure Regulator Package Year : On Progress
- Electrical System
- CCTV & Telecommunication and PAGA System
- SCADA System
28 15281 Fuel Gas System for Repowering Supply Indocement Design and Supply of Fuel Gas System Package, consist of: Client : PT Dalle Engineering Construction
Project, Cibinong, West Java - 1 x 100% Fuel Gas Scrubber End User : PT Indocement Tunggal Prakarsa, Tbk.
(18 MMSCFD) - 2 x 100% Fuel Gas Coalescer Principal : N/A
Site Location : Cibinong, Bogor, West Java
Year : Completed, 2016
29 15285 Purad and Dyes System & Avtur Coalescer for New 1. Design and Supply of Purad Injection Package, consist of: Client : PT Dalle Energy
Gantry System and End-to-End Data Automation project, - 1 Unit Purad Storage Tank End User : PT Dwi Sura Prima - PT. Pertamina Patra Niaga
Terminal BBM Rewulu, DIY - 2 x 100% Purad Injection Pump, Electric Motor driven Principal : N/A
2. Design and Supply of Dyes Injection Package, consist of: Site Location : Rewulu, Bantul, DIY
- 1 Unit Dyes Storage Tank Year : Completed, 2016
- 2 x 100% Dyes Injection Pump, Electric Motor driven
3. Design and Supply of Avtur Coalescer Package, consist of:
- 1 Unit Coalescer Vessel
- 1 lot Field Instrumentation
30 - Chiller and Condensate Stabilizer Package Design and Supply of Chiller Package, consist of: Client : PT Pertamina EP
(42 MMSCFD), Pondok Makmur Project - 2 units Refrigerant Compressor package End User : PT Pertamina EP, Pondok Makmur Development
- 1 unit Refrigerant Condenser Principal : Technical Asia Pte Ltd, Rhine Ruhr, EXHEAT UK
- 1 unit Gas Chiller Site Location : Pondok Makmur, Bekasi, West Java
- 1 unit Control Panel Year : Completed, 2016
31 - Fuel Gas Conditioning Unit Package Design and Supply of Fuel Gas Treatment Package, consist of: Client : PT Pertamina EP
(2 MMSCFD) , Pondok Makmur project - 1 x 100% Fuel Gas Scrubber End User : PT Pertamina EP, Pondok Makmur Development
- 2 x 100% Fuel Gas Coalescer Principal : Rhine Ruhr, Exheat
- 2 x 100% Fuel Gas Heater Site Location : Pondok Makmur, Bekasi, West Java
- 1 unit Control Panel Year : Completed, 2016
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
32 14247 Production Separator and Test Separator Package 1. Bid Proposal Preparation Client : PT Prakarsalanggeng Majubersama
(8 Unit package) 2. Basic & Detail Engineering End User : Petrochina International Jabung Limited (PIJL)
3. Internal Design and Supply: Principal : N/A
4. Field Instrument Supply Site Location : Betara Gas Plant (BGP), Jambi, Sumatera
5. Control Panel Design & Supply Year : Completed, 2015
6. Instrument Installation and Hook-Up
7. Factory Acceptance Test (FAT)
8. Site Acceptance Test (SAT)
9. Site Commissioning
10. Project Planning, Control, Execution and Monitoring
33 15282 Production Separator Package 1. Bid Proposal Preparation Client : PT Prakarsalanggeng Majubersama
(1 Unit package) 2. Basic & Detail Engineering End User : Petrochina International Jabung Limited (PIJL)
3. Internal Design and Supply: Principal : N/A
4. Field Instrument Supply Site Location : Gemah PPF (Permanent Production Facility, Jabung, Jambi
5. Control Panel Design & Supply Year : Completed, 2016
6. Instrument Installation and Hook-Up
7. Factory Acceptance Test (FAT)
8. Site Acceptance Test (SAT)
9. Site Commissioning
10. Project Planning, Control, Execution and Monitoring
34 C11025 Design & Supply of Internals for Pembelian & Design and Internals Supply of : Client : PT Indo Turbine
Pemasangan Fasilitas Kompresor Untuk Gas Musi Timur - 2 units MP Separator (V-010/V-020) End User : PT Pertamina EP (Persero)
Field Pendopo, PERTAMINA EP - 2 units LP Separator (V-011/V-021) Principal : Rhine Ruhr, Australia
(Direct to Rhine Ruhr Pte Ltd) - 4 units MP Scrubber (V-213/V-223/V-233/V-243) Site Location : Musi Timur, Field Pendopo, South Sumatra
- 4 units LP Scrubber (V-216/V-226/V-236/V-246) Year : Completed, 2016
- 1 unit Fuel Gas Scrubber (V-200)
- 1 unit Gas KO Drum (KO-610)
35 15327 KO Drum Emergency Flare Vessel Design and Internals Supply of : Client : PT Asta Ragam Bina Tehnik
- 1 units KO Drum emergency Flare Vessel (TK-4800) End User : Petrochina JOB Tuban
- 1 units KO Drum emergency Flare Vessel (TK-4810) Principal : Rhine Ruhr, Australia
Site Location :Tuban - Jawa Timur
Year : Completed, 2016
36 15282 Production Separator for Gemah PPF Petrochina Engineering Service, Project management, Internal Supply and Process Warranty Client : PT Prakarsa Langgeng maju Bersama
End User : Petrochina International Jabung Limited
Principal : Rhine Ruhr, Australia
Site Location : Gemah - Jambi
Year : Completed, 2016
37 15291 Fuel Gas System (10 MMSCFD) , 1 set of Pressure Control Package Client : PT Yuan Sejati
Gorontalo (Peaker) Gas Fired Powerplant 100MW project 1 set of Gas Metering Package Fabricator : PT Prakarsalanggeng Majubersama
1 set of Fuel Gas Package EPC Contractor : PT Rindang Pari
1 lot Interconnecting Piping Main Contractor : PT. PP (Persero), Tbk
End User : PT PLN (Persero)
Site Location : Gorontalo, North Sulawesi
Year : Completed, 2016
PROJECT EXPERIENCE LIST - PT. PACIFIC PROCESS ENGINEERING (OCTOBER 2016)
38 16334 8 Units Fuel Gas System for Truck Mounted Gas Turbine Engineering and Project Management Team for Eight (8) area project : Client : PT Yuan Sejati
Power Plant 500MW - Tarahan, Lampung, Fabricator : PT Prakarsalanggeng Majubersama
- Jungkat-Pontianak, EPC Contractor : PT PP (Persero) Tbk.
- Air Anyir-Bangka, Main Contractor : PT. GE Operation Indonesia (GE Energy)
- Jeranjang-Lombok End User : PT PLN Bright Batam
- Gunung Sitoli-Nias Site Location : Lampung, Pontianak, Bangka, Belitung, Lombok, Nias, Medan, Duri
- Suge-Belitung Year : On Progress
- Paya Pasir-Medan
- Duri-Riau
39 15328 Condensate Tanks and Accessories (Cap. 1 m3) for Fuel Design and Supply of Condensate Tank Package, consist of: Client : PT Dalle Engineering Construction
Gas System, Repowering Supply Indocement Project, - 1 unit Condensate Tank End User : PT Indocement Tunggal Prakarsa, Tbk.
Cibinong, West Java - 1 lot Instrumentation and Manual Valves Principal : N/A
(18 MMSCFD) Site Location : Cibinong, Bogor, West Java
Year : Completed, 2016
40 16344 Pengadaan Empat (4) Units ISO Tank LNG Design and Supply of ISO LNG Tank, Water Capacity 20 m3, 20ft-Container size, consist of: Client : PT Pertagas Niaga
- 4 units ISO Tank LNG End User : PT Pertagas Niaga
- 4 lot of Flexible Hose connection Principal : CIMC Sanctum
Site Location : Arun, Lhokseumawe, Aceh
Year : Completed, 2016
41 16359 Internal Column Pertamina UP VII Sorong Replacement of CDU Column 1-C-01 Internals, Tray#1-#7, Tray #13-#36 Client : PT Pertamina RU VII
End User : PT Pertamina RU VII
Principal : Rhine Ruhr, Australia
Site Location : Sorong, Papua
Year : Completed, 2016
42 16368 FC5 Prototye Plant Project, New Zealand Detail Engineering Design for LGN Distillation and Cyrene Purification, including: Client : Rhine Ruhr Pte Ltd
- Pipe Sizing & Pipe Thickness Calculation End User : Norske Skog, New Zealand
- Pipe Routing Site Location : Tasmania, New Zealand
- Pipe Stress Analysis Year : On Progress, 2016
- 3D Drawing
Techno Park Industrial Estate | Sector XI, Block G2, No. 5 | Bumi Serpong Damai (BSD)
City 15322 Telp. (+62-21) 7588 1945 | Fax. (+62-21) 7588 1940
[email protected]
http://pacificproeng.com
is to certify that the
Quality Management System
Of
ISO 9001:2008
This certificate valid for the following scope of operation :
Provision of Construction of residential and non-residential buildings,
Construction of roads and motorways, Construction of bridges and tunnels,
Construction of water projects, Electrical installation, Plumbing, heat and air-
conditioning installation
EAC: 28
NACE: 41.20, 42.11, 42.13, 42.91, 43.21, 43.22
-
Signed on behalf of IMS-Indonesia
IMS-Indonesia
«3l?A.l-"IA l?IPllllU'§, Ruko Anggrek Blok D-1 No.11
JI. Boulevard Raya Grand Depok City, Depok - Indonesia
Phone/ Fax: (021) 77831348 / 7783 5773
Website : www.ims-indonesia.co.id
Email : [email protected] (11 W IE:S 1
~
- --- Q U A LITY