Gen Air Test (RGM)
Gen Air Test (RGM)
Gen Air Test (RGM)
Sheet 1 of 12
LIST OF CONTENTS
1.0
PLANT DETAILS
2.0
OBJECTIVE
3.0
PROPOSAL
4.0
SERVICES REQUIRED
5.0
SAFETY PERECAUTIONS
6.0
EMERGENCY PROCEDURE
7.0
8.0
METHOD
9.0
COMPLETION CRITERIA
Station: NTPCRAMAGUNDAM
Sheet 2 of 12
STATUS
PLANT DETAILS
500 MW Generator consists of the following components.
a. STATOR
Stator Frame
End Shields
Stator Core
Stator winding
Hydrogen coolers
b. ROTOR
Rotor Shaft
Rotor windings
Rotor Retaining Rings
Field Connections
c. BEARINGS
d. SHAFT SEALS
1.2
The two pole generator is designed with direct water cooling for
the stator winding, phase connectors and bushings and direct
Hydrogen cooling for rotor winding. Generator losses, such as
iron losses, windage losses and stray losses are also dissipated
through hydrogen. The generator frame is pressure resistant,
gastight and equipped with major components mentioned above.
The hydrogen coolers are arranged vertically inside the turbine
end stator end field.
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 3 of 12
STATUS
1.3
1.4
They are
1.5
ELP 50/42-30/16
588 MVA
500 MW
Current
16.166 KA
Voltage
21KV + 1.05KV
Speed
3000 RPM
Freqency
50HZ
Power Factor
0.85 (Lag)
Hydrogen Pressure
3.5 bar
340 V
4040 A
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 4 of 12
STATUS
OBJECTIVE
The objective of the test is to ensure.
2.1
2.2
2.3
3.0
PROPOSAL
The objective will be achieved through the following proposals.
3.1
3.2
3.3
3.4
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 5 of 12
STATUS
4.0
SERVICES REQUIRED
4.1
4.2
4.3
Availability of
Test pressure gauge of range 0-6 KSC with least scale
division of 0.01 KSC
Mercury Manometer with mm scale
Generator winding Temp Indicator/Recorder in UCB.
Water U Manometer
4.4
4.5
Availability of lighting/communication
4.6
5.0
SAFETY PRECAUTIONS
5.1
5.2
5.3
5.4
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 6 of 12
STATUS
6.0
EMERGENCY PROCEDURES
6.1
6.2
7.0
7.1
7.2
7.3
7.4
7.5
7.6
Stator winding filled with primary water and primary water tank
kept pressure less. All the valves closed in P.W. System. Connect
a U Tube manometer in Waste gas line of P.W. Tank after valve
MKF91 AA 505 and close valve MKF91 AA 506. Open valve
MKF91 AA 513 and AA 505. It is also required to observe for any
leakage into primary water system through stator windings during
air leakage test.
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 7 of 12
STATUS
7.7
7.8
7.9
7.10
7.11
7.12
All the valves provided in H2 Unit are kept open so that all the
lines are pressuirsed during air filling. All valves connected to
vents are kept closed.
7.13
7.14
Vent valves provided in oil drain lines are closed viz., MKA21 AA
502, MKA 22 AA 502, MKA 23 AA 502, MKA 23 AA 512, MKA 24
AA 502.
7.15
Valves provided in gas impulse line for valve A1, A2 in seal Oil
system are opened.
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 8 of 12
STATUS
7.16
7.17
8.0
METHOD
Testing of Pipe between CO2 Bottle Rack and H2 Unit
8.1
Disconnect pipe lines at isolating flanges Nos. 96 and 97. Keep
valve MKG 59 AA 507 open. Blank one end of this pipe line by a
temporary flange. Pressurise the pipe line by N2 gas to a Pr. Of
4.8 bar and observe the leakage rate for 2 hrs. There should not
be any pressure drop. (Subject to temperature condition
remaining same).
Connect back the pipe lines on system after successful
completion of test.
Testing of Pipe between H2 Bottle Rack and H2 Unit.
8.2
Disconnect pipe lines at isolating flange Nos. 94 and 95. Blank
one end of this pipe line by a temporary flange. Pressurise this
pipe by N2 gas to a pressure of 4.8 bar. Observe the leakage rate
for 2 Hrs. There should not be any pressure drop in pipe line.
Check for any leakage during this period by means of soap
solution at all welding joints and rectify any leakage. Connect
back the pipe lines in system after successful completion of test.
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 9 of 12
STATUS
Testing of Pipe Between N2 Bottle Rack and P.W. Tank
Disconnect pipe lines at isolating flange No. 312 and primary
water tank. Blank one end of this pipe line by a temporary flange.
Keep valve (MKP91 AA 502 open. Pressurise this pipe by N2 gas
to a Pr. Of 5 bar. Observe the leakage rate for 2 Hrs. There
should not be any pressure drop in pipe line. Check for any
leakage during this test by means of soap solution at all weld
joints and rectify any leakage. Connect back the pipe lines in
system after successful completion of test.
8.4
8.4.1
8.4.2
During the air leakage test, apply Soap Solution at all joints for
checking leakages in following areas:
Joint and bolt heads on Stator body
Weld joints on generator body
Joints of terminal bushings, manhole covers, H 2 coolers
etc. Gas piping welding joints and flanged joints.
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 10 of 12
STATUS
Passing of valves in the system to atmosphere and
passing through valve glands.
Gas drier shell.
Seal oil Tank Flanged joints.
Impulse line connection for pressure regulating valve in
seal oil system
Connecting joints of all measuring instruments provided in
gas system.
Passing of valves provided in oil/water detector lines.
Sealing joints provided for taking out the stator winding
Temp. terminals.
If any leakage is observed the generator should be depressurised
and same should be attended and test should be repeated.
Ii
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 11 of 12
STATUS
Iii
Observe for any pressure rise in P.W. tank during test by means
of Water U manometer provided for this purpose. If any increase
is observed, stator winding system should be checked for
leakage.
IV
Continue the test till the rate is well within specified limit. If no
leakage is observed, pressure drop should be checked for 72 hrs.
continuously.
8.4.3
273+T1
273 + T2
VG
= Generator volume, m3
P1
P2
Signatures
NTPC
BHEL
Station: NTPCRAMAGUNDAM
Sheet 12 of 12
9.0
STATUS
Pb1
Pb2
T1
T2
COMPLETION CRITERIA
Leakage test should be carried out for 72 hrs at 4 bar and
average air loss should be calculated. The permissible air loss for
a gas tight system is below 2.4m3 at N.T.P. / 24 Hrs.
If air loss is higher, checks should be carried out for detecting the
leakage areas.
Signatures
NTPC
BHEL
PROJECT
PROCEDURE
PURPOSE OF
DOCUMET
DOCUMENT
PS:TSX:183:00:03
Copy No:
Issued to :
00
KJ
MKS
KPTM
17.09.2003
Rev.No.
Prepared by
Reviewed by
Approved by
Date