"SSE has confirmed commercial operations of the 1200MW Dogger Bank A offshore wind farm in the UK has been delayed until 2025.
The developer, which owns a 40% stake in the project, said in a stock market announcement that construction remains ongoing at all three phases of the world's largest offshore wind farm at Dogger Bank off the coast of England.
It was originally due online in 2024.
All monopiles and transition pieces have now been installed at Dogger Bank A, with inter-array cable laying also well progressed.
However, turbine installation has been affected by challenging weather conditions, with vessel availability and supply chain delays further impacting progress, SSE said.
A total of 95 GE Haliade-X machines had been targeted to be in place by the second quarter of 2024.
This latest announcement marks a further departure from the original timeline set by the project partners (which include Equinor and Vargronn).
SSE added: "The return of the installation vessel back to site in early May has meant that turbine installation has now resumed and, assuming continued clear weather conditions, it is expected that installation activity will continue uninterrupted over the summer months, with the project targeting full commercial operations during the first half of 2025.
"With the HVDC Transmission system fully commissioned, it is expected that turbine commissioning and export will happen in conjunction with installation. It is not expected that the delays noted will materially affect project returns.""