J. Geomec. Geoeng. 1(1): 27-37 (2023)
Journal of Geomechanics and Geoengineering
Available at https://asps-journals.com
Ground Improvement - Selected Tunisian Case Histories
Souhir Ellouze1, Nadia Mezni2, Mounir Bouassida3
1
Assistant Professor, University Sfax, Ecole Nationale d’Ingénieurs de Sfax, GESTE, Tunisia
2
P.E., University Tunis El Manar, Ecole Nationale d’Ingénieurs de Tunis., LRI4ES03.BP 37 Le Belvédère, 1002 Tunis. Tunisia
3 Professor, University Tunis El Manar, Ecole Nationale d’Ingénieurs de Tunis., LRI4ES03.BP 37 Le Belvédère, 1002 Tunis. Tunisia
Received April 24, 2022
Revised July 12, 2022
Accepted July 23, 2022
Published online: November 7, 2022
Keywords
Geo-drains
rigid inclusions
sand piles
settlement
embankment
tank
Abstract: This paper presents a detailed analysis of three Tunisian ground improvement case
histories. The first case addresses the cause of disorders that seriously affected the stability
of an oil tank, initially built on a superficial soft clay layer improved by sand piles. Due to the
underestimated length of sand piles, the oil tank operations stopped after non-admissible
consolidation differential settlement. Retrofit solution using micropiles’ reinforcement
revealed quite satisfactory to restart the functioning of the oil tank after fifteen years. The
second case deals with the reinforcement of compressible silt sand layer by floating stone
columns to reduce the long-term differential settlement of a gas storage facility. Recorded
measurements during the follow-up of stage construction of the storage facility permitted
the assessment of numerical predictions of the settlement of reinforced soil. The third case
studies the stability of access ramps of an interchange in Tunis Centre. Built numerical plane
strain modelling helped for the prediction of the behaviour of embankment access on
improved Tunis soft soil by geodrains. Based on recorded settlements and horizontal
displacements, followed the validation of computed consolidation settlement. Adoption of
suitable parameters of two constitutive models of the behaviour of Tunis soft clay is
discussed.
© 2022 The authors. Published by Alwaha Scientific Publishing Services, ASPS. This is an open
access article under the CC BY license.
1. Introduction
The stability of heavy loaded structures, e.g. high
embankments, and sensitive infrastructures to differential
settlement, for instance gas storage facilities, built on very
thick soft deposits is challenging. In addition to the
verification of bearing capacity, in short-term condition,
embankments construction on saturated clayey soils often
requires a special care because of the evolution of longterm (consolidation) settlement in time. When rigid
inclusions or pile foundations are not intended for such
projects, column-reinforced foundation can be adopted,
under the form of floating inclusions in case the stratum
layer is very deep.
Stone columns, sand-compaction piles and deep soil
mixing are among the most popular techniques enabling
the increase in bearing capacity, the settlement reduction
and the acceleration of consolidation (Bergado et al, 1996).
Mitigation of liquefaction is also another benefit, targeted
by using vibro-compaction and stone column techniques
(Han, 2015), (Bouassida, 2016). The installation of Rammed
Aggregate Pier® (RAP) columns is an alternative mitigation
technique that can increase the soil resistance, accounting
for its lateral stress increase and for the stiffness increase
from soil and RAP composite response (Amoroso et al,
2020).
Reinforcement by floating stone columns or by floating
cement soil columns gained more interest as experienced
Corresponding author. E-mail address:
[email protected]
This work is licensed under a Creative Commons Attribution 4.0. License (CC BY 4.0) http://creativecommons.org/licenses/by/4.0/
JOURNAL OF GEOMECHANICS AND GEOENGINEERING | JGG | ISSN 2716-7992 (PRINT)
Available online at https://asps-journals.com/index.php/jgg
https://doi.org/10.38208/jgg.v1i1.450
28
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
in soft clays, Kitazume (2005), Chai & Carter (2011), Safuan
et al (2017), etc.
2. Insufficient sand piles improvement of Tunis soft
soil
Nowadays, one can note numerous improvement
techniques to reinforce soft-highly compressible deposits.
In particular, geodrains and vacuum consolidation revealed
much more efficient than preloading to accelerate the
consolidation settlement of several infrastructure projects
(Indraratna et al, 2015; Jebali et al, 2017; Priyanka &
Arindam, 2018, etc.).
2.1. Project overview
Further, geogrids reinforcement constitutes a potential
technique to improve the bearing capacity of shallow
foundations.
Geotechnical parameters of soil layers were adopted from
an existing geotechnical survey previously carried out for
an existing similar oil-tank nearby the studied tank. Table 1
schematizes the soil profile comprising six layers including
five compressible silt sand to highly compressible soft clays
(Bouassida et al, 2019). Note that all layers of the soil
profile in Figure 1 are saturated; the soft silt-clay layer
extending from 6 m to 18 m depth is subdivided into three
sub-layers. Table 1 summarizes adopted geotechnical
parameters of the soil profile under the oil tank with
notice that excepting sand layers N° 4 and 5, cohesion and
friction angle values in all remaining layers correspond to
the short-term shear strength (i.e. undrained parameters).
Whilst, cohesion and friction angle values of sand layers
correspond to effective (drained) shear strength
parameters.
Geocells also represents a reliable technique of soil
reinforcement; it is recommended that the cells size of
geocells should be selected smaller than 0.67 times the
width of footing: Gholamhosein et al, 2019 .
Micropiles are equally efficient in many retrofit
applications to increase the bearing capacity of shallow
and to reduce their settlement: Bouassida et al, 2003.
In the geotechnical Tunisian context, to date, only few
ground improvement techniques are of current practice;
whilst other improvement techniques, worldwide
implemented, yet remain unknown, the vacuum
consolidation is an example (Jebali et al, 2017). Bouassida
& Hazzar (2008) pointed out the lack of experience of
reinforcement by stone columns in Tunisia in comparison
to vertical drains. However, regarding research activities
several contributions were recognized (Guetif et al, 2007;
Bouassida & Hazzar, 2012; Frikha et al, 2015, Jebali et al,
2017, etc).
Main objective of the present paper is to report about
some practiced ground improvement techniques in Tunisia
with focus on the geotechnical context of Tunis City
characterized by the presence of thick soft soil deposits
extending up to 50-60 m depth, especially in the area of
North and South Tunis Lakes.
In this view, analysis of three selected Tunisian ground
improvement case histories aims to capture the learned
lessons (for different infrastructures and geotechnical
conditions) about either unsafe design, unsuitable
foundation solution, or, conversely, successful execution of
some ground improvement technique. Hence, due to the
lack published papers, the synthesis of the three selected
case histories will provide the best highlight to promote
much better the practice of ground improvement
techniques in Tunisia in forthcoming projects.
Early in the nineties, the National Petroleum Company
built an oil cylindrical steel tank of 33 m diameter in the oil
products storage area located at Rades suburb of Tunis
City. The working vertical load of the tank is equal to 100
kPa.
Tank execution was preceded by the improvement using
sand columns of 0.6 m diameter over the first six meters
depth, i.e. the highly compressible sandy silt layer. This
technique is well-known in Tunisia as “sand piles” which
execution starts by the penetration of a metallic casing
inducing a lateral expansion of the soft soil. Then, the
casing is filled by sand without being compacted; a stepby-step withdrawl of the casing along with added sand
forms the sand pile that is mainly viewed for vertical
drainage rather than a reinforcing inclusion (Bouassida &
Klai, 2012).
Table 1: Geotechnical parameters of soil layers
Layer Thickness Cohesion Young Poisson’s Friction Total unit
n°
(m)
ratio
angle
weight,
C (kPa) modulus
E (MPa)
(kN/m3)
(-)
1
6.0
10
2.5
0.33
0
17.5
2a
3.0
15
2.0
0.45
0
17.0
2b
6.0
30
3.0
0.40
10
18.0
2c
3.0
35
5.0
0.35
12
18.5
3
5.0
40
7.0
0.30
13
19.0
4
5.0
0
15.0
0.25
37
18.5
5
7.0
5
10.0
0.33
32
19.0
6
10.0
50
9.0
0.30
15
20.0
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
29
Improvement of the tank foundation comprised the
installation of 481 sand piles of length 6m in a non-regular
pattern with an improvement area ratio equals 11%. This
solution essentially aimed at accelerating the consolidation
settlement in the upper compressible silt-sandy layer,
rather than reinforcement of this crossed layer followed by
an increase in soil bearing capacity (Bouassida, 2016).
Hence, the sand piles overall played the role of vertical
drains by accelerating the settlement of improved
compressible upper layer, as a consequence of induced
upward water drainge due to the dissipation of excess
pore pressure. The overlaying blanket layer, first,
contributed to the evacuation of drained water at the
ground surface. Second role of this blanket layer, of
thickness 1.2 m, was to render the settlement of tank
uniform and, therefore, to minimize the risk of differential
settlements due to unequal excess vertical stresses
generated by the tank load at the ground surface.
Meanwhile, it is obvious that the executed sand piles
improvement could not accelerate the induced long-term
settlement extended at least up to 25 m depth where the
tank of 33 m diameter induced non-negligible excess of
vertical stress.
Using Terzaghi’s method via Equation (1), the calculation
of consolidation settlement (i.e. the oedometer method)
of unreinforced compressible layers, all assumed normally
consolidated, up to 23 m depth is detailed in Table 2.
(1)
From the predicted long-term settlements in Table 2, it
should be emphasized that the long-term settlement of
layers 2a, 2b and 2c is approximately 60 cm,
over a thickness of 12 m. After Bouassida & Hazzar (2008),
Table 2. Prediction of long-term settlement of unreinforced clay
layers.
Layer
n°
Thicknes Compress Initial
s
(m) ion index, void
Cc
ratio,
e0
Effective
vertical
stress σ’v0
(kPa)
Settlem
Excess
ent
of
vertical (cm)
stress,
Δσ (kPa)
2a
3.0
0.600
1.00
55.5
95.0
25.8
2b
6.0
0.572
1.88
90.0
80.0
26.0
2c
3.0
0.365
1.33
126.8
65.0
8.5
3
5.0
0.145
0.67
162.0
52.5
5.3
s = consolidation settlement of soil layer of thickness H; cc
= compression index; e0 = initial void ratio; = excess of
vertical stress due to the tank load and
= effective
overburden stress.
Fig 1. Adopted soil profile of oil tank foundation (Bouassida
et al, 2019)
adopting the coefficient of vertical consolidation of 10-8
m2/s for clay layers 2a, 2b and 2c the estimated degree of
consolidation, after twenty years, is about 35%. Therefore,
the consolidation settlement of the unimproved layers is
still in progress under the tank load. Thus, the
improvement by sand piles, of 6m length, only reduced
and accelerated the settlement of the upper high
compressible sandy silt layer.
Few years after the commencement of tank operations,
on-site observations showed that its cylindrical shell
suffered severe buckling deformation. After fifteen years,
the visually-observed settlement due to the primary
consolidation of compressible layers attained 20 cm. This
was followed by the decision in stopping the tank
operations. Retrofit solution should be foreseen for
repairing the oil tank. Two retrofit solutions were
suggested.
First proposal is a reinforcement by micropiles (MP) of
length reaching the top side of the dense sand layer,
located between 23 and 28 m depth (Figure 1). Second
retrofit option suggested the reinforcement by inclined
rigid inclusions (IRI) embedded in the dense sand layer.
2.2. Reinforcement using micropiles
The dismounting of the entire tank’s shell is required for
the installation, in a concentric polygonal mesh, of seven
30
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
micropiles, (Figure 2). Sixty four (64) micropiles, of 30 cm
diameter and 25 m length, only reacting by the shaft
resistance were installed. To ensure a uniform distribution
of loads throughout the tank area, the micropiles’ heads
are embedded in concentric reinforced concrete beams.
Due to the decreased induced vertical stress in horizontal
distance (from the centre to the tank border) of applied
tank pressure, equal number of micropiles are located on
the polygonal perimeter. Although the reinforcement by
micropiles is a non-cost effective retrofit solution, it
warrants the long-term tank stability without risk of nonadmissible residual settlement.
2.3. Reinforcement by inclined rigid inclusions (IRI)
The installation of inclined rigid inclusions (IRI) embedded
within the sand layer at 23 m depth can be designed to
avoid the entire dismounting of the tank and to proceed
for repairing only the affected areas by buckling.The skin
resistance generated between the soil and the IRI balances
a given proportion of the total weight of the oil tank
structure. Therefore, one can estimate the total allowable
skin resistance developed by the IRI and, then, to deduce
the required number of those inclusions to the adopted
proportion of tank load. Consider this latter estimated as
67%, the remaining 33% of tank load will be balanced by
the consolidated first layer which degree of consolidation
increased by approximately 35% during twenty years of
tank operations. Since the IRI should be covered at the top
by a reinforced concrete raft, an enhanced load
concentration is afforded; therefore, the number of IRI is
lesser than that of the vertical micropiles.
Bouassida & Bouassida (2013) performed an axisymmetric
numerical model, using Plaxis’ 2D software, for studying
the effect of installing the IRI embedded in the sand layer,
on the evolution of consolidation settlement within the
soft silt clay layers (2a, 2b and 2c, Figure 1). The
reinforcement using inclined rigid inclusions is then less
expensive than that of micropiles connected by reinforced
concrete beams. The owner of project favoured the
micropiles’ reinforcement; however, it requires the
dismounting of the entire shell of the oil tank, which also is
time consuming.
3. LGP storage facility on reinforced soil by floating
stone columns
3.1. Project overview
The second case history addresses a storage facility,
located at Ghannouche (South East of Tunisia), comprises
two bullets of butane and five bullets of propane protected
in mounded banks. Figure 3 schematizes the cross section
of the completely integrated embankment. Geotechnical
properties of soil layers are obtained from measured CPT
values during the soil investigation and laboratory tests
results conducted for the project. Table 3 summarizes the
properties of crossed soil layers as identified from
oedometer tests and tip resistance estimated from CPT
results.
Fig 3. Cross section of completely integrated embankment
(dimensions in meter)
Table 3. Geotechnical parameters from soil investigation
Fig 2. Layout of reinforcing micropiles embedded in
reinforced concrete connection beams (Bouassida & Mejri,
2011).
Layer
Tip
Thickn
Total unit
resistanc
ess
weight, γ
e, CPT
(kN/m3)
(m)
(MPa)
Initial
void
ratio,
e0
Compre
ssion
index
Fine sand
2.5
12.0
--
--
--
Medium sand
with mud & clay 6.5
inclusions
4.0
--
--
--
Clay and sand
partially
cemented
30.0
19.0
0.65
0.100
5.5
Alternating
bedding of fine
sand and clay
30.0
17.0
1.26
0.395
7.5
--
19.0
0.65
0.100
Mostly hard clay
-and sand
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
Reinforcement by stone columns is suitable to reduce the
unallowable settlement as predicted under the applied
embankment load equals 120 kPa. The stability is required
for an allowable residual settlement equals 4 cm, over 15
years in post construction of the storage facility (El Ghabi
et al, 2010).
Hence, significant reduction of settlement associated to
the prescribed margin of security has led to the installation
of floating stone columns of 11 m length, embedded in
medium sand layer. Stone columns of 0.9 m diameter were
installed in a triangular pattern with an improvement area
ratio = 16%.
3.2 Numerical behaviour of the LGP storage facility
Numerical simulation of the embankment behaviour was
carried out by Plaxis 2D software. Built plane strain model
comprised a 7 m embankment height with an upper crest
width equals 56 m and lower base of width equals 88 m.
Foundation of this embankment is described by the soil
profile detailed in Table 3. After project data, 46 stone
columns were installed along the horizontal direction, with
an axis to axis spacing of 1.9 m, and 30 stone columns
were installed, along the perpendicular direction, with an
axis to axis spacing equals 2.2 m, over 64 m length.
Simulation of the behaviour of reinforced ground in plane
strain condition, assumed the modelling of the group of
stone columns by a group of equivalent trenches of
equivalent thickness as calculated by El Ghabi et al, (2010).
Forty-one trenches of stone material are considered in the
31
built numerical model with thickness = 0.3 m; length = 11
m and a spacing between edges of trenches = 1.9 m. Elastic
perfect plastic Mohr-Coulomb constitutive model
describes the behaviour of soil layers.
Table 4 presents the adopted geotechnical parameters of
soil layers, embankment material and reinforcing stone
material. The numerical simulation of embankment
behaviour with staged construction comprised four phases
(Bouassida, 2016).
Figure 4 shows the contours of vertical displacement with
maximum value equals 8 cm at the upper crest of
embankment facility. Whilst, at the surface of reinforced
soil, predicted quasi-uniform settlement equals 6 cm over
the width of upper crest beneath the embankment with an
applied load of 120 kPa.
Table 4. Adopted soil parameters for numerical modelling
Thickness (m)
E
C
(MPa) (kPa)
(°)
sat(
kN/m3)
Backfill
material
6.0
10.0
1
30
20.0
Fine sand
2.5
30.0
5
30
19.0
Soft silty clay
6.5
5.7
2
24
18.0
Firm clay
5.5
60.0
2
24
19.0
Silty clay
7.5
12.0
15
10
18.0
Stiff clay
6.0
80.0
2
24
20.0
Stone
material
11.0
60.0
0
40
20.0
Fig 4. Contours of vertical displacement of embankment on reinforced soil by floating stone columns (Bouassida, 2016).
32
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
Fig 5. Evolution of recorded settlement vs. time at location PR02 (Bouassida, 2016)
Predicted consolidation settlement equals 6.5 cm should
occur in four years. Follow up of the behaviour of storage
facility built on reinforced ground by floating stone
columns was performed by means of data acquisition unit
that connects the pressure sensors, to record the evolution
of settlements, located at the surface of reinforced ground
(Bouassida, 2016).
An axisymetric numerical simulation with a composite cell
model, in oedometer conditions, was also conducted
(Ellouze et al, 2017). The settlement of reinforced soil is 4
cm for a long term analysis of fifteen years after the end of
installation of backfill layer.
Figure 5 displays the evolution of recorded settlement in
function of time at profile PR02. Recorded settlement,
after the installation of the first backfill layer, varied
between 1.0 and 1.7 cm and, then, became stabilized after
a month. Upon the completion of the embankment
construction, the magnitude of measured settlements was
lower than 3.0 cm. Based on this, the floating stone
columns reinforcement experienced at Gannouche’s site
fulfilled the requirement of an admissible consolidation
settlement lower than 4 cm.
It is, therefore, concluded that plane strain predictions are
in a better match with recorded in-situ settlements. This
result sounds obvious because the axisymmetric model
reduced the reinforced soil to a unit cell in oedometer
conditions.
3.3 Observed behaviour of the storage facility
Detailed description of the acquisition unit comprising the
installation of settlement gauges and recorded settlements
was reported
by
El Ghabi et al
(2010).
Measured settlements induced by the acquisition unit data
occurred since the first step of embankment construction,
and, then, eight months after the edification of final
backfill layer, the settlement evolution became stabilized.
The third phase of numerical staged construction included
a consolidation analysis corresponding to the final height
of embankment. This phase simulates the long-term
behaviour after fifteen years of the construction of storage
facility. Along with the progress of embankment stage
construction, the settlement significantly increases in
different locations and, then, it becomes almost onstant
within the allowable limit of settlement that is 4 cm.This
long-term settlement corresponds to the induced
deformation within unreinforced sub-layers (Bouassida &
Hazzar, 2015). From Figure 5, the recorded settlement
evolution shows the benefit of stone columns in
accelerating the consolidation of soft silty clay layer
illustrated by a stabilized settlement eight months in post
edification of the final backfill layer.
The study of the second case history well demonstrated
the usefulness of floating stone columns reinforcement as
no residual consolidation settlement, occurred in the
unreinforced sub-layers. Hence, one concludes that the
design of foundation of bullets of butane and propane
integrated into an embankment on compressible layers
reinforced by floating stone columns was successful.
Indeed, this design permitted to comply with the allowable
settlement of the foundation over fifteen years as
predicted by the numerical computations. Those
predictions revealed in acceptable agreement with the
measured settlement that remained under 4 cm over 15
years.
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
33
4. Access ramp Foundation on improved Tunis soft
clay by geodrains
Table 5 presents the characterisation of each soil layer,
including the preload embankment, sketched in Figure 6a.
4.1 Project overview
The stability of the preload embankment shown in Figure
6a requires, first, verification of the admissible bearing
capacity and, second, the settlement. Using soil
parameters given in Table 5, by assuming the embankment
as a strip footing with zero embedment, from Terzaghi’s
bearing capacity equation it is easy to check that uniform
embankment load equals 62 kPa is admissible. Meanwhile,
the prediction from Eq (1) of the consolidation settlement
at the axis embankment leads to a non-admissible value
nearly equals 0,5 m. 90% of this settlement is expected to
develop in 300 years! Therefore, it was concluded to
accelerate the long-term settlement by using the
technique of geodrains, of length 18 m, associated with a
preload embankment.
The studied area is the Republic Avenue that extends over
a distance of two kilometres. This Avenue connects
between the North and the South sides of Tunis City by the
highway A1. After collected data from several geotechnical
investigations, Mezni & Bouassida (2019a) conducted the
characterization of the soil profile. Suggested correlation
for soil parameters were adopted to simulate the
behaviour of access ramps of interchange “Cyrus Le
Grand” located at the Republic Avenue of Tunis City.
Validation of predicted settlements aimed to assess, in
particular, the adopted constitutive model and related
Tunis soft clay parameters.
4.2 Geotechnical profile
Figure 6a shows the geotechnical profile under Cyrus Le
Grand interchange that comprises, from the ground
surface, a fill layer (N° 3) of 4.0 m thickness followed by a
soft greyish clay layer (N° 4) of 11m thickness. Then, a
black clay layer (N° 5) of 4m thickness and sandy clay layers
(N° 6) of 40m thickness up to the top level of rigid stratum
layer located at 60 m depth (Mezni & Bouassida, 2019b).
This soil profile is overlaid by by a blanket layer of 0.5 m
thickness on which the preload emabankment of 3.1 m
height is built.
Foundation of the piers and abutments of the main bridge
of this interchange comprises a group of piles, embedded
in the stratum layer. In turn, the access ramps of approach
embankments were built on an improved soft soil by
geodrains to accelerate the consolidation settlement of
Tunis soft clay. Mebradrain geodrains of 18 m length,
installed in square mesh with an axis-to-axis spacing of
1.1m, permitted to accelerate the consolidation of high
compressible soft soil upper layers with a compression
index equals 0.38 to 0.42. Construction of preloading
embankment of 3.1 m total height comprised two phases.
The first phase simulates the preloading during 24 days to
reach an embankment height equals 2m. The second
phase refers to a preloading scheduled for 95 days to reach
a total embankment of height equals 3.1 m (Mezni &
Bouassida, 2019b).
A drainage sand mattress of 0.5 m thickness preceded the
embankment construction at the surface of improved soil
to facilitate the water evacuation from the geodrains
(Figure 6a). This upper sand layer can also contribute in a
better load transfer avoiding differential settlement.
Fig 6. Installed settlement recorders under access
embankment
Table 5. Geotechnical parameters of soil layers and embankment
material
Soil layer
[n°]
Cohesion Friction Total
Thickness Young
(m)
Modulus [kPa]
angle
unit
weight
[MPa]
[°]
[kN/
m3]
Embankment 3.1
[1]
10.0
1
30
20.0
Drainage
blanket [2]
0.5
30.0
5
30
19.0
Fill [3]
4.0
5.7
2
24
18.0
Soft greyish
clay [4]
11.0
6.0
2
24
19.0
12
15
10
18.0
8
2
24
20.0
Black clay [5] 4.0
Sandy clays
[6]
40.0
34
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
4.3 Follow up of accelerated consolidation settlement
Three types of settlement gauges were installed under the
access ramp (Mezni & Bouassida, 2019b). Table 6
summarizes the location of all installed settlement
recorders as follow up instruments under the access
embankment.
The settlement recorders were installed at 5 m in front of
the abutment of the main bridge and at 10m behind it. In
the front of this abutment, rod settlements TT1, TT2 and
TT3, TT4 and TT5, were installed at the embankment axis,
on the right side and on the left side, respectively. Behind
the abutment C1, rod settlement TT6 was installed at the
embankment axis, TT7 and TT8 on the right side, TT9 and
TT10 on its left side.
Fig 7. Recorded settlement under access embankment
Hydraulic settlement TH1 and multipoint settlement TM1
were installed at the embankment axis; TH2 and TH3
hydraulic settlements were installed on the right and on
the left side, respectively. Figure 6 shows the locations of
some settlement gauges along a vertical cross section of
the access embankment, i.e. perpendicular to the traffic
direction..
Follow-up of the settlement took a period of three months.
Unfortunately, after this short period there were no
recorded settlements. Figures 7, 8 and 9 show the
evolution of recorded settlements, at the axis and the two
extremities of instrumented preload embankment. At the
axis of embankment, the recorded settlements are higher
than those measured at the embankment crest and toe
(Figures 7 and 8).
Fig 8: Evolution of recorded settlement by hydraulic
settlement gauges
Further, Figure 7 shows that recorded settlement
variations by TT2 and TT4 are quite similar. As for TT3 and
TT5 rod settlement recorders quasi-identical settlement
evolution is noted. Such a behavior is attributed to the
symmetrical locations of those settlement recorders with
respect to the longitudinal axis of preload embankment.
Table 6. Locations of the installed settlement recorders under
access embankment
Type
Rod
settlement
Hydraulic
settlement
Multipoints
settlement
Axis
TT1, TT6
TH1
TM1, TM5
Crest
TT2,
TT7,
TT4, TT9
TH2, TH3
--
Toe
TT3,
TT8,
TT5, TT10
--
--
Location
Fig 9. Observed settlement at the axis, left and right sides
of embankment
The multipoint settlement (TM), along the embankment
axis, recorded a value of 37.6 cm after 95 days (Figure 10).
However, by the hydraulic settlement the recorded value
was limited to 24 cm after 94 days. Consideration of
recorded values by the multipoint settlement gauge calls
for caution. Indeed, on-site observation indicated that the
vertical displacement of the probe of the multipoint
settlement was prevented due to the lateral deformation
of the tube (MEHAT, 2007). Recorded values by the rod
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
settlement were in-between 26.7 cm and 35 cm after 90
days over a distance of 15m between TT1 and TT6
recorders. The rod settlement recorded values were in
between the provided measurements by the hydraulic
settlement and the multipoint settlement.
Mezni & Bouassida (2019b) carried out a numerical
simulation, using Plaxis software, to predict the evolution
of settlement under the ramp of access embankment. Built
plane strain model served for the validation of the
predicted behaviour of the ramp of access embankment
when compared to the observed settlement evolution. The
soft soil model (SSM) was considered to describe the
behaviour of compressible layers. Table 7 summarizes the
geotechnical parameters of the soft soil model, including
the compression index Cc, the swelling index Cs, initial void
ratio, isotropic permeability and long-term shear strength
characteristics, adopted for the soft clay and greyish clay
layers. Detailed description of the geotechnical parameters
and method of determination can be found in Klai et al,
2015.
Numerical predictions of settlements under the ramp
access embankment in different locations led to quasi
similar by the SSM. It was, then, concluded, for the studied
case history, the SSM revealed suitable to describe the
behaviour of Tunis soft clay (Mezni & Bouassida, 2019b).
Indeed, the comparison between predicted settlements by
the SSM and the recorded values during the follow-up of
embankment were in acceptable agreement in particular
when consider the recorded settlement values by the
multipoint settlement (Figure 10). It was also checked that
the installation of geodrains provided a good acceleration
of consolidation settlement in comparison to the predicted
settlement of unimproved soil.
Fig 10. Evolution of predicted settlements by the SSM and
recorded data
35
Table 7. Geotechnical parameters of the softening soil model
(SSM) adopted for Tunis soft clay
Parameters
(kN/
(kN/
)
)
(m/day)
Soft
greyish
clay
Black
clay
Soft
greyish
clay
Black
clay
17.0
18.0
17.0
18.0
19.0
20.0
19.0
20.0
1.5 10-4
1.0 10-4
1.5 10-4
1.0 10-4
0.420
0.380
0.420
0.380
0.056
0.057
0.056
0.057
1.20
1.04
1.20
1.04
C’
-
-
6
8
'(°)
-
-
20
21
ψ(°)
-
-
0
0
Ψ = angle of dilatancy
Meanwhile, from Figures 7, 9 and 10, the maximum
recorded accelerated settlement approximates 35 cm.
Adopting this latter and compared to the total estimated
consolidation settlement of 50 cm, one deduces that a
global degree of consolidation of 70% is achieved in three
months. Then, one concludes that the completed
consolidation by the geodrains is expected to end from six
to nine months after the edification of preload
embankment.
5. Conclusion
This paper addressed three Tunisian ground improvement
case histories. Each case history is associated to a specific
ground improvement technique which design complies
with the long-term stability of an oil tank, embankment
storage facility and access embankment for interchange
project, respectively. From those case histories, it follows
the learned lessons and recommendations hereafter
summarized.
After the studied first case history, Insufficient design of
improvement using sand piles, for the oil tank project,
resulted from the lack of data to consider from a specific
geotechnical survey and an unsuitable design of
improvement characterized by short sand piles of length
6m. This improvement technique revealed unsuccessful
due to non-admissible consolidation settlement that
affected the serviceability of the oil tank, as ceased after
15 years. Hence, successful retrofit technique
reinforcement using micropiles of length 25 m was
necessary to transfer the load tank to deeper soil layers
thereby by passing the consolidating layers.
36
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
Second case history discussed the reinforcement by
floating stone columns of compressible layers at
Ghannouche site. Stage construction of the storage facility,
comprising two bullets of butane and five bullets of
propane protected in mounded banks, was simulated by
Plaxis software in four phases. Using an equivalent 2D
modelling of reinforced ground by floating trenches of
length 11 m, the prediction of behaviour of the storage
facility showed that the prescribed residual settlement,
occurring after the end of stage construction, did not
exceed 3.5 cm as observed from recorded settlements
during the follow up of storage facility. This prediction
fulfilled the required value of residual settlement equals to
4 cm over fifteen years.
Third case history addressed the acceleration of
consolidation of Tunis soft clay by geodrains for the
embankment access of Cyrus Le Grand interchange. The
efficacy of geodrains, in accelerating the consolidation of
soft soil up to 18 m depth, is proven from the follow-up of
settlement recorded by three types of settlement
recorders. Those in-situ data permitted to assess numerical
predictions of the settlement after implementation of a
plane strain modelling, in which the soft soil model
suitably describes the behaviour of Tunis soft clay. The two
modelling led to comparable predictions of the accelerated
settlement evolution.
Nomenclature
LGP
SSM
Liquefied Petroleum Gas
soft soil model
Bouassida M. & Mejri A. (2011). Etude pathologique d’un
réservoir fondé sur sol mou renforcé par pieux de sable.
Séminaire Franco Maghrébin, Rabat (Maroc). 22 – 26
novembre.
Bouassida, M. & Hazzar, L. (2012). Novel tool for optimised
design of reinforced soils by columns. Ground Improvement:
Proc. ICE, London 165 (1), 31–40.
Bouassida, M & Klai, M. (2012). Challenges and Improvement
Solutions of Tunis Soft Clay. Int. Journal of Geomate, Tsu,
Mie, Japan ISSN:2186-2982 (Print) 2186-2990 (Online) Sept.
3 (1), 296-305.
Bouassida, M. & Bouassida, W. (2013). Soil Reinforcement by
Rigid Inclusions: Contamination of an Oil Storage Tank. Proc.
of 7th ICCHSMGE, Paper No. 2.55, Chicago 27th – 30th April.
Bouassida, M. & Hazzar, L. (2015). Performance of soft clays
reinforced by floating columns. Book “Ground Improvement
Cases Histories, Embankments with Special Reference to
Consolidation and Other Physical Methods. Editors
Indraratna et al, Chap 16. Part Two: Sands and Gravel Piles,
Stone Columns and Other Rigid Inclusions. Butterworth
Heinemann publications. 2015 Elsevier, 433-449.
Bouassida, M. (2016) Design of Column-Reinforced
Foundations. J. Ross Publishing (FL, USA), September. 224
pages.
Bouassida, M. & Ellouze, S., (2018). Optimized design of
foundations on soil reinforced by floating columns. Special
Issue: XVI DECGE Proc. of 16th Danube European Conference
on Geotechnical Engineering June 2018. 165-176.
Disclosures
Free Access to this article
SARL ALPHA CRISTO INDUSTRIAL.
Bouassida M. & Hazzar L. (2008). Comparison between Stone
Columns and Vertical Geodrains with Preloading
Embankment Techniques. Proc. 6th Int. Conf. on Case
Histories in Geotechnical Engineering. Arlington VA (USA),
11-18 August, Paper No. 7.18a.
is
sponsored
by
References
Amoroso S., Rollins K.M., Andersen P. & Gottardi G, (2020). Blastinduced liquefaction in silty sands for full-scale testing
of ground improvement methods: Insights from a
multidisciplinary study. Engineering Geology.
Bergado D.T., Anderson L.R., Miura N. & Balasubramaniuam A.S.
(1996). Soft Ground Improvement in lowland and other
Environments. ASCE Press. New York.
Bouassida, M. Ben Ouezdou, M., Haffoudhi, S. & Ben Saïd, B.
(2003). Renforcement des fondations du pont rail sur oued
El Akarit en Tunisie. Actes du 13ème Congrès Régional
Africain de la Géotechnique. Marrakech (Maroc) 8-11
décembre 2003. Sahli, Bahi et Kalid Edit. 147-153.
Bouassida M., Ellouze, S. & Bouassida, W. (2019). Optimized
foundation design in geotechnical engineering. Book
“Optimization of design for better structural capacity,
Belguesmia Editor, IGI Global, 222-234. DOI: 10.4018/978-15225-7059-2.ch009.
Chai, J. & Carter, J.P. (2011). Deformation analysis in soft ground
improvement. Springer, Dordrecht.
El Ghabi B., Hermges T., Lambert S., Ellouze S., M. Bouassida & A.
Mejri (2010). Comparison between predicted settlement of a
group of stone columns foundation and in- situ records. 2nd
Int. Conf. on Geotech. Eng. October 25-27, 2010, Tunisia:
255-264 ISBN code 978 - 9973-9997-1-9. (1), 347-357.
Ellouze, S. Bouassida, M. Bensalem, Z. & Znaidi, MN (2017)
Numerical analysis of the installation effects on the
behaviour of soft clay improved by stone columns,
Geomechanics and Geoengineering, 12:2, 73-85.
Ellouze et al. / J. Geomec. Geoeng. 1(1): 27-37 (2023)
Frikha, W., Tounekti, F., Kaffel, W., and Bouassida, M. (2015).
"Experimental study for the mechanical characterization of
Tunis soft soil reinforced by a group of sand columns." Soils
and Foundations, 55 (1), 181-191.
Gholamhosein T. M., Behrad, R. & Moghaddas Tafreshi, SN
(2019). Scale effect on the behaviour of geo-cell reinforced
soil. Geotextiles and Geomembranes 47 (2): 154-163.
Guetif, Z.; Bouassida; M. & Debats, J. M. (2007). Improved Soft
Clay Characteristics Due to Stone Column Installation.
Computers and Geotechnics. 34 (2); 104-111.
Han, J. (2015). Principles and practice of ground improvement.
ISBN: 978-1-118-25991-7. Copyright © 2000-2019
by John Wiley & Sons.
Indraratna, B., Chu, J. & Rujikiatkamjorn, C. (2015). Ground
Improvement Cases Histories, Embankments with Special
Reference to Consolidation and Other Physical Methods.
Vol. 1 & 2, Editors, Butterworth Heinemann publications.
2015 Elsevier, ISBN: 978-0-08-100192-9.
Jebali, H., Frikha, W., & Bouassida, M. (2017). Experimental study
of Tunis soft soil improved by vacuum consolidation
associated with geodrains Journal: Geomechanics and
Geoengineering (TGEO). 12 (4).
Kanoun, F. & Bouassida, M. (2008). Geotechnical aspects of Rades
La Goulette project (Tunisia). ISSMGE Bulletin, 2 (3). 6-12.
37
Kitazume, M. (2005). The Sand Compaction Pile Method, CRC
Press, 143982469X, 9781439824696, 232 pages.
Klai, M., Bouassida, M. & Tabchouche S (2015). Numerical
modelling of Tunis soft clay. Geotechnical Engineering
Journal of the SEAGS & AGSSEA 46 (4) December, 87-95.
MEHAT, (2007). Travaux de l'échangeur Cyrus Le grand - R. Ghana
Liaison Nord-Sud. Rapport de suivi de consolidation des
rampes. Direction générale des Ponts et Chaussées. Tunis.
Mezni, N. & Bouassida M. (2019a) Contribution to the Study of
Geotechnical Characterization and Behaviour of Tunis Soft
Clay. In: Hemeda S., Bouassida M. (eds) Contemporary Issues
in Soil Mechanics. GeoMEast 2018. Sustainable Civil
Infrastructures.
Springer,
Cham.
https://doi.org/10.1007/978-3-030-01941-9_14.
Mezni, N. & Bouassida, M. (2019b). Geotechnical characterization
and behaviour of Tunis soft clay. Geotechnical Engineering
Journal of the SEAGS & AGSSEA 46 (4) December, 87-95.
Priyanka Talukdar & Arindam Dey, (2018). Influence of the rate of
construction on the response of PVD improved soft ground.
Indian Geotechnical Conference, IGC.
Safuan, A. Rashid, Beng Hong Kueh & Hisham Mohamad, (2017)
Behaviour of soft soil improved by floating soil–cement
columns. International Journal of Physical Modelling in
Geotechnics 18(2) :1-22 · January 2017.