4.1. Repointing Mortars
Initially, an attempt was made to design three basic compositions for the deep repointing, responding to the construction phases, and the color and texture of the in situ masonry mortars: one for the main church and the original parts of the narthex, both belonging to the A’ and B’ construction phase of the middle Byzantine period (reddish color), one for the narthex’s rebuilt parts constructed at the end of the 19th century to the beginning of the 20th century (off-white with reddish aggregates), and one for the exonarthex constructed at the 16th century (off-white/beige color).
In a first stage, raw materials from the local market of Chios were used, including lime putty and the available sands. However, both the first trial mixes in the laboratory and on site, revealed that the compositions for the main church and the original parts of the narthex, that had a reddish hue, were not satisfactory. Local sands and commercial ceramic powder, which is usually used for byzantine mortars, could not successfully imitate this particular reddish color.
So, it was decided to use aggregates from a reddish stone of siliceous origin which resembled the aggregates found in the surrounding area of the monument. A specific investigation was carried out for this purpose, as it is presented in what follows.
Moreover, the use of the natural pozzolan called “Hfaisteiaki Gaia” of an off-white color, instead of the slight grey color natural pozzolan “Lava Antica” from Milos Island, used for the exonarthex’s mortar, was also proved necessary from the pilot applications.
In all cases, the choice of the type and size distribution of the aggregates, was based on the granulometric gradation curve of the original mortars, on their color shade, as well as on their physical characteristics, such as their mineralogical origin (limestone-silicate) and aesthetic compatibility to the original materials.
A large number of tests and pilot applications, both in the laboratory and on site, was required for the final selection, since the original mortars, especially in the façades of the monument are complex mixtures of aggregates and binders, with a distinct texture and shade which varies from area to area in masonry, depending on various factors, as the width and depth of the joints, the level of damage or wear and the type of adjacent masonry units (stone or bricks).
It should be noted that, according to the restoration study, the patina of time in the original materials (stones, bricks and mortars), should be preserved in situ. Thus, in each area the adjacent materials and their state of preservation played an important role, in the finish of the restoration mortar, sometimes with minor modifications, influencing the final result. As mentioned above, new repointing mortar was only used to repair the defective joints (with crumbling mortar, or extensive erosion) and to rebuilt areas.
Therefore, as mentioned in the introduction, the choice of the most appropriate composition for application on the monument was based on a combination of criteria regarding both physicochemical compatibility and mechanical strength, as well as aesthetic harmony. The latter related to the compatibility of the final color shade and texture of the applied restoration mortar to the original old mortars and bricks conserved in situ. This was extremely important for the surface pointing mortars, which should not “catch the eye” and create contrast with the historic mortars still preserved in situ (
Figure 1,
Figure 2,
Figure 3 and
Figure 8), aiming at a certain coherence and harmony of the appearance of the monument as a whole.
Figure 8a,c present the NE and the central part of the N façade of the main church, before the restoration intervention; damaged and decayed mortars and bricks can be seen, while some of the recessed bricks under the deteriorated surface mortars are also apparent.
Figure 8b,d present the same parts of the monument 5 years after the intervention. The historic materials preserving the patina of time (stones, bricks and mortars), together with the new mortars and bricks can be seen.
The main difficulties faced were the particular reddish color of the mortars and the fact that the width of the joints to be repointed varied from approximately 3 cm for the majority of the joints, to 9 cm in surface joints between two brick courses covering the internally recessed bricks (
Figure 2 and
Figure 8).
Therefore, special care was taken to ensure an appropriate practical methodology for the application of the repointing in the worksite. To this end, a detailed protocol was drafted in collaboration with the craftsmen, including all the steps to be followed, from the preparation of the joints and the mortar to the placement of the mortar to the joints and the curing of the repointed area. Multiple preparatory applications of mortar in less visible areas, filling the joints in thin layers, repeatedly by hand, using small trowels and specific tools, with stable pressure for compacting them, permitted both finetuning the methodology for the specific needs of this case study, but also selecting the most qualified and experienced craftsmen to execute the repointing works on site. Care was also taken to schedule the works in such a way so that to avoid extreme seasonal conditions (i.e., high and low temperatures), as lime-based mortars are sensitive both to freezing and hot temperatures, as well as to dry and windy conditions.
The procedure of repointing adopted, which is briefly described below, was based on the literature [
45,
46,
47] and on the experience of the Laboratory of DTRR of HMC and the multidisciplinary team supervising the works.
Damaged and eroded mortars were carefully removed from the joints, using hand chisels and mash hammers, until the appropriate depth was reached (at least equal to the width of the joint for surface repointing or approximately two times the width of the joint for deep repointing), in order to ensure adequate bonding. If loose or disintegrated materials were noticed beyond this minimum depth, these were also removed, until a clear rectangular space was achieved. The side and rear surfaces of bricks and stones were meticulously cleaned, as the existence of dust and mortar residue would have an inevitably bad effect on bonding. Thorough pre-wetting of the masonry was also ensured to minimize the loss of the mortar’s water due to absorption by the masonry materials. Pre-wetting started at least one day before the application of the repairing mortar, by spraying water without applying pressure, and continued for several times on the day of the application, until just before the application. The objective was that the joints would be dump at the time of filling with the mortar, but not surface wet (the bricks and stones should not be excessively wet and thus shiny).
During the preparation of the mortar, attention was paid to achieve the desired consistency while keeping the water to a minimum, to avoid shrinkage and to facilitate compaction during the application. The mortar should be workable, but relatively firm and “dryish”. Just after completion of the mixing, the mortar should be protected from water evaporation. Thus, it must be placed in a covered container and avoid direct exposure to windy air and sun. Small amounts should be taken progressively by the craftsman and used in each application area.
The filling of joints with mortar was carried out in layers, using small finger trowels of different widths that fitted within the joints, spatulas and other plastering tools. The filling started from the deeper areas and the thickness of each layer was of the order of 2,0 cm or even less in case of friable old mortar being left in the back of the joints, avoiding the application of too much mortar in each layer, as this could provoke shrinkage cracking. For the same reason, for the deep repointing mortar of thick joints, the addition of coarser aggregates (gravel 8–16 mm, 10% of the weight of solid materials of the corresponding mortar) was prescribed, based also on the granulometry of the original mortars, which contain a fraction of 10–15% of such coarse gravel. Additionally, when repointing mortar was used to fill internal lacunas of larger dimensions, especially during the rebuilding of some collapsed areas, it was also necessary to incorporate small pieces of stones or bricks (the so-called “chips”), by pressing them into the mass of the mortar.
The quality of the compaction of the fresh mortar into the joint is crucial, as it directly affects its bond with the existing materials. Each layer of firm dry mortar was tightly compacted with force into the back of the open joint, packing it well into the back corners. A pressing movement of the pointing tool (e.g., pointing iron) should be used instead of a sweeping one. Subsequently, the surface of each inner layer of mortar was scratched (using various shapes) in order to improve its roughness when it hardens, thus leading to better adhesion of the next layer.
Once the mortar has reached thumb-print hardness, another layer of mortar was applied. Depending on the areas, several layers are needed to fill the joint flush with the outer surface of the masonry. It is important to allow each layer to harden before the next layer is applied. Depending on the area and the period (summer-winter), a curing period of several hours or one or more days is necessary between layers to allow the previous one to stiffen and begin hardening. Since most mortar shrinkage occurs during the hardening process, the objective of layering is to minimize the overall shrinkage; thus, as hardening in lime-pozzolan based mortars is slow, during the curing period between layers, mortars must be inspected very frequently and in case shrinkage cracks appear, re-working of the mortars with adequate tools (small spatulas, etc.) and local firm compaction must be applied to seal the cracks.
When the final layer was thumb-print hard, the surface of the joints was tooled, using adequate means and procedures to reach the appropriate finishing, in order to match to the adjacent historic materials.
During the whole procedure and at least for 14 days after the completion of the repointing, the repointed area was carefully covered with wet burlap fabric, sealed with a plastic sheeting and placed in a short distance from the masonry to avoid possible staining of the mortar. The burlap was systematically sprayed with water to keep the new repointed area constantly damp. Besides avoiding shrinkage cracking, this is very important for hydraulic mortars, to ensure that adequate water for the hydration reactions of lime/pozzolan and hydraulic lime is retained.
4.1.1. Production of Mortar Aggregates by Crushing Local Rock Mined for the Purpose
As aforementioned, the reddish color of the majority of original mortars was achieved by using aggregates from a reddish stone of siliceous origin which resembles that of the surrounding area of the monument. To this end, the DTRR/HMC carried out a specific investigation to find an adequate local quarry with the aim to crush the local stones and produce reddish aggregates in suitable granulometry for the restoration mortars of the project.
Comparative analyzes were carried out at the Institute of Geological and Mineral Research on behalf of DTRR/HMC, between the aggregates of authentic mortars and aggregates collected from the surrounding area of the monument, and the aggregates from two old quarries of Chios, Stenakas and Fyrolakas. The aggregates of Stenakas were selected for use in the construction site. As presented in
Table 8, aggregates collected from the surrounding area have a similar composition to the aggregates of original mortars (compare values of
Table 8 with values of
Table 3), with the difference that minerals such as dolomite and muscovite were also detected. In general, the samples had a relatively similar mineralogical composition, which indicates their common origin.
Regarding the Fyrolakas and Stenakas quarry samples, X-Ray diffraction analysis (XRD) concluded that the Stenakas sample presents a mineralogical composition that is more similar to the aggregates of the historic mortars, compared to the sample from Fylorakas. The differences lie in both qualitative and quantitative analysis results.
Due to the fact that the quarry of Stenakas was inactive, DTRR/HMC made in 2005 the necessary request to the local Authorities, and a specific permission was issued to quarry the necessary volume of rock for the production of aggregates to be used for the restoration mortars of this unique monument.
Thus, a sufficient quantity of rock was quarried and sent to a crusher to obtain fractions for use in mortar compositions. These fractions were sand 0–4 mm, gravel 4–8 mm and gravel 8–16 mm.
It should be noted that such a special permission was granted only because of the great importance of the monument, as well as the detailed and experimentally documented request.
4.1.2. Repointing Mortars to Be Applied to the Exonarthex, Narthex and Main Church
The first mortar that was designed to have adequate properties for repointing the exonarthex’s North, South and West walls, was of an off-white/beige color. After a series of Laboratory and in situ pilot applications, the composition M1 was selected for implementation. The composition of mortar M1 and all other repairing mortars designed for the restoration works is presented in
Table 9.
Figure 9a presents the granulometric curve of a representative original mortar from the exonarthex (sample 48) in comparison to the curve of aggregates mixture of pointing mortar M1, which was selected for application on this part of the monument.
Figure 9b presents the granulometric curves of three representative existing mortars which were used in the past to rebuild collapsed parts of the narthex (no. 16, 33, 36), in comparison to the curve of the aggregate’s mixture of the repointing mortar M2, which was selected for these parts of the monument.
A first composition for deep repointing and local reconstructions of the main church and original parts of the narthex was initially designed on the basis of an extended pilot application program. This initial composition was further improved during the course of the works and evolved into composition M3, containing a variety of sands and gravels in order to achieve, in the best possible way, the reddish color of the original mortar.
Regarding the surface repointing mortar, composition M4 was finally designed as the basic mortar. It has to be underlined that in order to achieve the best possible result in surface repointing of the facades, slight modifications were proved necessary to match the specific color and texture existing in each specific area.
Figure 10 illustrates the grading curves of the aggregates of original mortars of the main church (no. 17,26) together with the curves of aggregates mixtures that have been used in the mortar composition M3 for the deep repointing of the main church. As mentioned above, it was recommended that coarser gravel could be added in the composition (max 10% of the total weight of solids), when relatively thick joints or internal big empty spaces had to be filled (e.g., in the areas of local reconstructions of heavily damaged parts of the external façades, etc.). To this end, this quantity was identified per mortar batch, so that the technicians and masons would be able to easily use it in the worksite.
The same graphic plot (
Figure 10) presents the grading curves of the aggregates of composition M4, that was designed for surface repointing of the narthex and main church façades. Composition M4 is quite similar to M3, but as expected, it contains finer aggregates than the respective deep repointing composition.
Table 9 summarizes the aforementioned repointing and deep repointing mortar compositions, to be used in the various areas of the monument. The ratio of binder/aggregates ranges between 1/1.85 and 1/2, whereas the water to binder ratio varies from 0.5 to 0.7. The flexural and compressive strength of the mortars applied, at a curing age of 28 days, is also given in
Table 9. Of note, the measured strength values of the lime pozzolan mortars are very good, as they reached a compressive strength (28 days) of 3.5–4.2 MPa, values which are in accordance with the relevant literature [
47], when a fine and reactive pozzolan and coarse aggregates are used and moist curing conditions are ensured.
Regarding the deep repointing of the extrados of the vaulted roof of the narthex, rebuilt after the 1881 earthquake, two natural hydraulic lime mortar compositions were selected (M5 and M6), which are also included in
Table 9. The two compositions are similar; the only difference being that M6 contains coarser aggregates, as it is designed to be used in the case of wider joints or void spaces.
Moreover, mortar compositions M7 and M8, both of reddish color, were designed for the purpose of sealing cracks and installing injection tubes in areas where historic pointing mortars were to be preserved in situ, but grouting should be applied for strengthening the structure. Similarly, composition M9 was proposed for sealing cracks and installing injection tubes in the internal faces of the walls, where an off-white color was preferable over a reddish one.
Figure 11 presents characteristic images of a pilot application of mortars M1 to M3, while
Figure 8b,d show mortar M4 applied on the upper part of the South East corner and the central part of the N façade of the main church, respectively. Pictures were taken 5 years after the application of surface repointing and other restoration works.
For the coating of the extrados of the vaulted roof of the exonarthex, a premixed mortar, named Albaria Struttura, was used according to the manufacturer’s instructions. Albaria Struttura is a cement-free pozzolanic lime mortar with natural siliceous aggregates with a maximum diameter of 2 mm. It guarantees a compressive strength >15 MPa and is therefore classifiable as an M15 type masonry mortar according to the European standard EN 998/2 [
71]. Specimens of this material taken at the worksite and tested in the laboratory had flexural strength of 4.1 MPa and compressive strength of 18.80 MPa, at the curing age of 9 months.
4.3. Design and Application of Grout Compositions
Taking into account the requirements of the restoration project, the necessary laboratory tests were carried out by DTRR/HMC to determine the compositions of (a) a high injectability grout for filling cracks and voids of a nominal minimum width (W
nom) equal to 0.2 mm, characterizing the monuments masonry [
48], and (b) of an injectable mortar, suitable for the filling of large voids left in the masonry due to the disintegrated timber laces. Given the importance of the monument’s decorative elements consisting of various materials, as well as the existence of byzantine frescoes in the internal face of the majority of the walls [
48,
54,
56,
58], it was decided, in both cases, to use hydraulic lime-based grouts instead of low cement content ternary compositions. A hydraulic lime (named Calx Romana and described by the manufacturer as hydraulic lime containing pozzolanic material) was used, after having examined its chemical and mineralogical characteristics, summarized in
Table 11.
Laser grain size analysis (carried out by (CERECO S.A.), using a Malvern Instruments Laser particle analyser) has shown that the diameter at 99% passing (d
99) of the hydraulic lime was less than 76 μm (d
99 < 76 μm) and the diameter at 85% passing (d
85) was less than 32 μm (d
85 < 32 μm); thus taking into account the penetrability criteria [
48,
67], it could be used for preparing grouts able to penetrate in a masonry characterized by an estimated nominal minimum width of voids, W
nom, approximately equal to 200 μm. For the preparation of the injection mortars, silicate aggregates in various particle sizes were added, with a max diameter of grains <0.8 mm or <1.25 mm, alternatively.
As aforementioned, a holistic design of hydraulic lime-based grouts was performed with the aim to ensure high injectability under low pressure, even in cracks of minimum nominal width of two tenths of millimeter (Wnom~200 μm). For this purpose, the penetrability, fluidity and stability characteristics of the suspensions were fully examined for various water/solids ratios, with or without the use of superplasticizers, using the testing methods described above.
The criteria set for the selection of the optimal compositions of the high injectability grout were the following: For the sand column injectability test, a sand of 1.25–2.5 mm was used, simulating a W
nom = 0.2 mm [
48,
67]. The grout was considered to be injectable if it had the capacity not only to reach the top of the column (360 mm) in a time (T
36) less than 50 s, but also when there was a continuous flow of grout from the sand column in the adjacent measuring vessel of at least 20 mL, as requested by EN 1771 [
66] and the relevant literature [
48,
67]. Regarding the fluidity, the Fluidity Factor had to be higher than 0.7 × 10
3 mm/s [
68] and the flow time (t
d = 4.75 mm) of 500 mL of grout, out of 1000 mL inserted in the Marsh cone with 4.75 mm nozzle diameter, had to be less than 45 s and greater than 20 s [
48,
68]; a maximum acceptable limit of 5% was set for the bleeding test; no segregation had to be present [
48,
70].
Table 12 presents the compositions of the best-performing grouts selected to be applied on the monument, together with their injectability (fluidity, penetrability, stability) and mechanical characteristics. All values measured satisfy the criteria set for such type of grouts as presented in the literature [
48].
The grout to fill the empty spaces left after the disintegration of some of the timber laces was applied first, using injection tubes installed for this purpose in two levels along the length of the timber laces. The injection tubes were installed mainly externally, but also internally, in some areas determined together with the specialized Conservators of the frescoes to allow for the grout to be injected and the air to escape without difficulty. The same tubes also served for collecting the overflow of the grout during the injections.
After the completion of the filling of the voids of the timber laces, a second injection campaign was carried out with the aim to fill internal voids and discontinuities of the three-leaf masonry, homogenize the masonry and improve its mechanical characteristics. Due to the rich decorative brick ornamentation of the façades of the walls and the existence of cracked frescoes on most of the internal surfaces, the installation of the appropriate grid of the injection tubes was realized very carefully, in collaboration with the specialized Conservators. The preparation of the masonry and the installation of the grouting tubes and all the necessary works and procedures for the application of grouting followed the methodology applied to the restoration of the Byzantine Katholikon of Daphni Monastery [
72,
73], and the practical recommendations presented and discussed in the relevant literature [
48].
The following criteria were used for selecting the positions of drilling holes for placing the grouting inflow and outflow tubes:
the distance of consecutive mortar joints, (horizontal and vertical) of the brick and stone masonry),
the thickness of the wall and its construction characteristics,
the injectability of the designed grout in relation to the minimum nominal width of voids to be filled,
the spatial correlation between possible cracks on inner and outer faces of the wall and the locations of severe damage, as well as the locations of timber laces,
the decoration of most of the internal faces of masonry with frescoes.
As suggested in the literature [
48], a dense grid of holes was drilled in the masonry and grouting tubes were installed. Due to the existence of frescoes on the interior faces, the injections should be mainly realized from the exterior façades, thus a denser grid of tubes was installed on them. Moreover, tubes installed in the masonry form the external façades should penetrate depths equal to 1/3, 1/2 and 2/3 of the thickness of masonry, to reach the interfaces of the infill material with the external and internal leaf, as well as the middle of the infill material. Thus, holes were drilled following the closest pattern forming a rhombus of unequal diagonals, with the horizontal one from 20 to 40 cm and the vertical from 40 to 70 cm. The drilling of holes was usually located in selected mortar joints, after careful visual inspection and observation of the masonry, in collaboration with the specialized Conservators, in order to avoid severe or unnecessary damages.
In all cases, it was necessary to install a smaller number of tubes internally, mainly for air exit and grout outflow, but also for the entrance of grout in case of wide cracks. Moreover, the existence of grout outflow tubes on the internal façades, decorated with frescoes, was crucial to monitor the movement of the grout behind the frescoes and to avoid any uncontrollable grout leakage or pressure built up [
48,
73].
Subsequently, transparent plastic tubes were installed into the drilled holes, externally and internally, having an internal diameter of 10 mm or smaller (6, 4, 1.8 mm), especially in the areas with frescoes (
Figure 12).
When repointing is applied, the mortar used for the repointing is also used for the installation of injection tubes. In areas where the tubes are installed in existing historic pointing mortars on the external or the internal façades or in the areas of frescoes, adequate mortar compositions with fine aggregates have been designed, as presented in
Table 9,
Section 4.1.2.
Figure 12a presents the grouting tubes installed in the north façade of the Church of Panagia Krina, while
Figure 12b presents the grouting tubes of an internal face of a wall. The tubes are numbered and marked with different color of tape to indicate their depth in the masonry and are fixed upwards with the help of wires installed for this purpose [
48], as shown in
Figure 12a,b. In
Figure 12b, one can see the tubes installed in areas of frescoes, where the specialized Conservators have been installed, and finer injection tubes with a small diameter, necessary for the evacuation of air and possible outflow of the grout.
After the completion of grouting, all the tubes were removed, and the holes were filled with the repointing mortar corresponding to each area. As can be seen in
Figure 13b (in comparison with
Figure 13a), but also in
Figure 8b,d presenting the monument after the completion of the restoration works, the grouting intervention is invisible. One of the advantages of this technique is that no traces are left after its application.