Introductory Text
PART 1 PRELIMINARY
1.Citation and commencement
2.Interpretation
PART 2 PRINCIPAL POWERS
3.Development consent granted by the Order
4.Maintenance of authorised development
5.Maintenance of drainage works
6.Operation of the authorised development
7.Limits of deviation
8.Benefit of this Order
9.Consent to transfer benefit of the Order
PART 3 STREETS
10.Street works
11.Application of the 1991 Act
12.Power to alter layout, etc., of streets
13.Temporary closure, alteration, diversion and restriction of use of streets
14.Permanent stopping up of streets
15.Access to works
16.Use of private roads
17.Agreements with street authorities
18.Traffic regulation measures
PART 4 SUPPLEMENTARY POWERS
19.Powers in relation to relevant navigations or watercourses
20.Discharge of water
21.Authority to survey and investigate the land
22.Protective work to buildings
23.Felling or lopping of trees
24.Removal of human remains
PART 5 POWERS OF ACQUISITION AND POSSESSION OF LAND
25.Compulsory acquisition of land
26.Compulsory acquisition of land – incorporation of the mineral code
27.Time limit for exercise of authority to acquire land compulsorily
28.Private rights
29.Power to override easements and other rights
30.Application of the 1981 Act
31.Modification of Part 1 of the 1965 Act
32.Acquisition of subsoil or air-space only
33.Temporary use of land for carrying out the authorised development
34.Temporary use of land for maintaining the authorised development
35.Statutory undertakers
36.Apparatus and rights of statutory undertakers in stopped up streets
37.Recovery of costs of new connections
38.Disregard of certain improvements, etc.
39.Set-off for enhancement in value of retained land
PART 6 MISCELLANEOUS AND GENERAL
40.Disapplication of legislative provisions, etc.
41.Amendment of local legislation
42.Planning permission, etc.
43.Application of landlord and tenant law
44.Defence to proceedings in respect of statutory nuisance
45.Protective provisions
46.Deemed marine licence
47.Certification of documents, etc.
48.Service of notices
49.Arbitration
50.Procedures in relation to approvals, etc., under Schedule 2
51.No double recovery
52.Guarantees in respect of payment of compensation
53.Crown rights
54.Offshore ornithology compensation provisions
55.Harbour seal compensation measures
Signature
SCHEDULES
SCHEDULE 1
AUTHORISED DEVELOPMENT
SCHEDULE 2
REQUIREMENTS
PART 1 REQUIREMENTS
1.Interpretation
2.Time limits
3.Detailed design approval
4.Detailed design (appearance)
5.Parameters of authorised development
6.Landscape and ecological mitigation strategy
7.Archaeology
8.Highway access
9.Surface and foul water drainage
10.Contamination
11.Code of construction practice
12.Construction hours
13.Construction traffic management plan
14.Flood risk emergency plan
15.Phasing of construction and commissioning of Work Nos. 1 and 2
16.Operational lighting scheme
17.Operational vehicle movements
18.Waste hierarchy scheme
19.Control of operational noise
20.Notice of start of commissioning and notice of date of final commissioning
21.Combined heat and power
22.Decommissioning
23.Amendments to approved details
24.Electricity generation cap
25.Tonnage caps
PART 2 PROCEDURE FOR DISCHARGE OF REQUIREMENTS
26.Applications made under Part 1
27.Further information
28.Fees
29.Register of requirements
30.Appeals to the Secretary of State
31.Anticipatory steps towards compliance with any requirement
32.Interpretation of Part 2 of Schedule 2
SCHEDULE 3
STREETS SUBJECT TO STREET WORKS
SCHEDULE 4
STREETS SUBJECT TO ALTERATION OF LAYOUT
PART 1 PERMANENT ALTERATION OF LAYOUT
PART 2 TEMPORARY ALTERATION OF LAYOUT
SCHEDULE 5
TEMPORARY CLOSURE, ALTERATION, DIVERSION AND RESTRICTION OF THE USE OF STREETS
SCHEDULE 6
PERMANENT STOPPING UP OF STREETS AND PUBLIC RIGHTS OF WAY
SCHEDULE 7
LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
SCHEDULE 8
PROTECTIVE PROVISIONS
PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
1.For the protection of the utility undertakers referred to in...
2.In this Part of this Schedule— “alternative apparatus” means alternative...
On street apparatus
3.This Part of this Schedule does not apply to apparatus...
Apparatus in stopped up streets
4.(1) Where any street is stopped up under article 14...
Protective works to buildings
5.The undertaker, in the case of the powers conferred by...
Acquisition of land
6.Regardless of any provision in this Order or anything shown...
Removal of apparatus
7.(1) If, in the exercise of the powers conferred by...
Facilities and rights for alternative apparatus
8.(1) Where, in accordance with the provisions of this Part...
Retained apparatus
9.(1) Not less than 28 days before starting the execution...
Expenses and costs
10.(1) Subject to the following provisions of this paragraph, the...
11.(1) Subject to sub-paragraphs (2) and (3), if by reason...
Cooperation
12.Where in consequence of the proposed construction of any part...
13.Nothing in this Part of this Schedule affects the provisions...
PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
14.For the protection of any operator, the following provisions have...
15.In this Part of this Schedule— “the 2003 Act” means...
16.The exercise of the powers conferred by article 35 (statutory...
17.(1) Subject to sub-paragraphs (2) to (4), if as the...
PART 3 FOR THE PROTECTION OF HIGHWAYS AND TRAFFIC UNDERTAKERS
18.(1) The provisions of this Part of this Schedule have...
19.(1) Before commencing the construction of, or the carrying out...
20.(1) The undertaker must not alter, disturb or in any...
21.The undertaker must not remove any soil or material from...
22.(1) If the relevant highway authority, after giving to the...
23.(1) The undertaker shall not, except with the consent of...
24.The undertaker must not, except with the consent of the...
25.The undertaker must, if reasonably so required by the relevant...
26.(1) Where any part of any highway has been broken...
27.If any damage to any highway or any property of...
28.The fact that any act or thing may have been...
29.Any difference arising between the undertaker and the relevant highway...
PART 4 FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
30.The following provisions apply for the protection of the Agency...
31.In this Part of this Schedule— “the Agency” means the...
Submission and approval of plans
32.(1) Before beginning to construct any specified work, the undertaker...
Construction of protective works
33.Without limiting paragraph 32, the requirements which the Agency may...
Timing of works and service of notices
34.(1) Subject to sub-paragraph (2), any specified work, and all...
Maintenance of drainage works
35.(1) Subject to sub-paragraph (5) the undertaker must from the...
Impairment of drainage works
36.Subject to paragraph 39, if by reason of the construction...
Agency access
37.If by reason of construction of the specified work the...
Free passage of fish
38.(1) The undertaker must take all such measures as may...
39.The undertaker must indemnify the Agency in respect of all...
Indemnity
40.(1) The undertaker is responsible for and indemnifies the Agency...
Disputes
41.Any dispute arising between the undertaker and the Agency under...
Roman Bank
42.(1) The undertaker must at its own cost engage the...
43.The undertaker must at its own cost engage the services...
44.The initial condition survey in accordance with paragraph 42 must...
45.The undertaker must provide to the Agency a copy of—...
46.The undertaker at its own costs will inspect, maintain and...
47.In respect of the Roman Bank only, this Part of...
PART 5 FOR THE PROTECTION OF DRAINAGE AUTHORITIES
48.The provisions of this Part have effect for the protection...
49.In this Part of this Schedule— “construction includes execution, placing,...
50.(1) Before commencing construction of a specified work, the undertaker...
51.Without limiting paragraph 50, the requirements which the drainage authority...
52.(1) Subject to sub-paragraph (2), any specified work, and all...
53.(1) Subject to sub-paragraph (5), the undertaker must from the...
54.Subject to paragraphs 55 and 56 and sub-paragraph 53(5)(b), if,...
55.The undertaker must make reasonable compensation for costs, charges and...
56.(1) Without limiting the other provisions of this Part, the...
57.The fact that any work or thing has been executed...
58.Any dispute arising between the undertaker and the drainage authority...
PART 6 FOR THE PROTECTION OF ANGLIAN WATER
59.For the protection of Anglian Water, the following provisions have...
60.In this Part of this Schedule— “alternative apparatus” means alternative...
61.The undertaker will not interfere with, build over or near...
62.The alteration, extension, removal or re-location of any apparatus must...
63.In the situation, where in exercise of the powers conferred...
64.Regardless of any provision in this Order or anything shown...
65.If in consequence of the exercise of the powers conferred...
66.If in consequence of the exercise of the powers conferred...
67.If for any reason or in consequence of the construction...
68.Any agreement or approval of Anglian Water required under this...
69.Any dispute arising between the undertaker and Anglian Water under...
SCHEDULE 9
DEEMED MARINE LICENCE
PART 1 INTRODUCTION
Interpretation
1.(1) In this licence— “the 2009 Act” means the Marine...
2.(1) Except where otherwise indicated, the main point of contact...
PART 2 LICENSED ACTIVITIES
3.Subject to the licence conditions in Part 3 of this...
4.(1) In this licence, “authorised development” means the construction, maintenance...
PART 3 CONDITIONS
General conditions
5.The undertaker must notify the MMO at the earliest opportunity...
6.(1) The undertaker must notify the HM Coastguard (mail to:...
7.(1) The undertaker must ensure that local mariners and fishermen’s...
Vessels
8.(1) The MMO must be notified in writing of any...
9.The undertaker must ensure that a copy of this licence...
Agents/contractors/sub-contractors
10.(1) The undertaker must provide the name, address and function...
11.(1) The undertaker must ensure that a copy of this...
Construction environmental management plan
12.(1) The undertaker must submit a CEMP in writing to...
Piling
13.(1) The undertaker must submit a piling method statement in...
Navigation management plan
14.(1) The undertaker must submit a navigation management plan in...
Marine archaeology
15.(1) The undertaker must submit an archaeological written scheme of...
Marine pollution contingency plan
16.(1) The undertaker must submit a marine pollution contingency plan...
Marine mammal mitigation protocol
17.(1) The undertaker must submit a marine mammal mitigation protocol...
Landscape and ecological mitigation strategy
18.(1) The undertaker must submit a landscape and ecological mitigation...
Concrete and cement
19.(1) Waste concrete, slurry or wash water from concrete or...
Coatings and treatment
20.The undertaker must ensure that any coatings and any treatments...
Spills, etc.
21.(1) The undertaker must— (a) store, handle, transport and use...
Removal of temporary structures etc.
22.The undertaker must remove all equipment, temporary structures, waste and...
Dropped objects
23.(1) All dropped objects must be reported to the harbour...
Bathymetric surveys
24.(1) Pre and post dredge bathymetrical surveys must be undertaken...
Sediment sampling
25.(1) The undertaker must submit a sample plan in writing...
Reporting of impact sound to the Marine Noise Registry
26.(1) Only when impact driven or part-driven pile foundations or...
Decommissioning
27.(1) Within 24 months of the permanent cessation of the...
Notice of completion of licensed activity
28.The undertaker must inform the MMO local office and MMO...
PART 4 PROCEDURE FOR THE DISCHARGE OF CONDITIONS
Meaning of “return”
29.In this Part, “return” means a submission by the undertaker...
Further information regarding return
30.(1) The MMO may request in writing such further information...
Determination of returns
31.(1) In determining the return the MMO may have regard...
Notice of determination
32.(1) Subject to sub-paragraph (2) or (3), the MMO must...
PART 5 CHANGES TO THE LICENCE
33.(1) In the event that the undertaker wishes to undertake...
SCHEDULE 10
DOCUMENTS AND PLANS TO BE CERTIFIED
PART 1 DOCUMENTS AND PLANS TO BE CERTIFIED
PART 2 ENVIRONMENTAL STATEMENT SUPPLEMENTS
SCHEDULE 11
ORNITHOLOGY COMPENSATION MEASURES
1.In this Schedule— “addendum to the outline ornithological compensation implementation...
2.The authorised development may not be commenced until a plan...
3.Following consultation with the OEG, the OCIMP must be submitted...
4.The OCIMP submitted for the approval of the Secretary of...
5.The OCIMP must include measures to compensate for the predicted...
6.The undertaker must implement the measures as set out in...
7.The undertaker must notify the Secretary of State of completion...
8.Results from the monitoring scheme must be submitted at least...
9.Unless otherwise agreed in writing by the Secretary of State...
10.The compensation measures delivered under this Schedule must not be...
11.The OCIMP approved under this Schedule includes any amendments that...
12.In the event of any conflict or inconsistency between the...
SCHEDULE 12
HARBOUR SEAL COMPENSATION MEASURES
1.In this Schedule— “harbour seal compensation measures document” means the...
2.No part of the authorised development may commence until a...
3.The strategy submitted for approval must be based on the...
4.The undertaker must implement the measures set out in the...
5.The harbour seal compensation strategy approved under this Schedule includes...
6.Results from the monitoring scheme specified in paragraph 3(d) must...
Explanatory Note