Article 27

SCHEDULE 5FOR PROTECTION OF RAILTRACK

1.—(1) The following provisions of this Schedule shall, unless otherwise agreed in writing between the Council and Railtrack PLC, have effect:—

(2) In this Schedule—

  • “construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;

  • “the engineer” means an engineer appointed by Railtrack PLC for the purpose in question;

  • “plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals and programmes;

  • “Railtrack” means Railtrack PLC and any associated company of Railtrack PLC which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 736 of the Companies Act 1985) the holding company of Railtrack PLC, a subsidiary of Railtrack PLC or another subsidiary of the holding company of Railtrack PLC;

  • “railway property” means any railway belonging to Railtrack PLC and any works, apparatus and equipment belonging to Railtrack connected with any such railway and includes any land held or used by Railtrack for the purposes of such railway or works, apparatus or equipment; and

  • “specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property.

2.—(1) The Council shall not under the powers conferred by this Order acquire or use or acquire new rights over any railway property unless such acquisition or use is with the consent of Railtrack PLC.

(2) Without prejudice to any requirement as to fencing made by Railtrack under paragraph 3(5) below on approval of plans, the Council shall provide and maintain, to the reasonable satisfaction of the engineer, a boundary fence incorporating gates where appropriate between railway property and any adjoining land of the Council acquired or appropriated for the purpose of Work No. 6.

(3) The Council shall not exercise the powers conferred by article 8 above or the powers conferred by section 11(3) of the 1965 Act in respect of any railway property unless the exercise of such powers is with the consent of Railtrack PLC.

(4) The Council shall not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Railtrack PLC.

(5) The Council shall not exercise the powers conferred by sections 271 or 272 of the 1990 Act, as applied by Schedule 4 to this Order, in relation to any right of access of Railtrack to railway property but such right of access may be diverted with the consent of Railtrack PLC.

(6) Where Railtrack PLC is asked to give its consent pursuant to sub-paragraph (3), (4), or (5) above, or to give its consent to the acquisition of new rights over or the use of railway property under sub-paragraph (1) above, such consent shall not be unreasonably withheld but may be given subject to reasonable conditions.

3.—(1) The Council shall before commencing construction of any specified work supply to Railtrack PLC proper and sufficient plans of that work for the reasonable approval of the engineer and shall not commence such construction of the specified work until plans of that work have been approved in writing by the engineer or settled by arbitration.

(2) The approval of the engineer under sub-paragraph (1) above shall not be unreasonably withheld, and if by the end of the period of 56 days beginning with the date on which such plans have been supplied to Railtrack PLC the engineer has not intimated his disapproval of those plans and the grounds of his disapproval he shall be deemed to have approved the plans as submitted.

(3) If by the end of the period of 56 days beginning with the date on which such plans have been supplied to Railtrack PLC, Railtrack PLC gives notice to the Council that Railtrack PLC desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Railtrack PLC then, if the Council desires such part of the specified work to be constructed, Railtrack PLC shall construct it (together with any adjoining part of the specified work which the Council reasonably requires to be constructed in one operation with that work) with all reasonable dispatch on behalf of and to the reasonable satisfaction of the Council in accordance with the plans approved or deemed to be approved or settled under this paragraph and under the supervision (where appropriate and if given) of the Council.

(4) In the event of Railtrack PLC not constructing or completing any part of a specified work pursuant to sub-paragraph (3) above with all reasonable dispatch and to the reasonable satisfaction of the Council in accordance with such programme as may be agreed with the Council or settled by arbitration, Railtrack PLC shall pay compensation to the Council for any loss which it may sustain as a result.

(5) When signifying his approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in his opinion should be carried out before the commencement of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Railtrack PLC or the services of operators using the same (including any relocation of works, apparatus and equipment necessitated by a specified work), and such protective works as may be reasonably necessary for those purposes shall be constructed by Railtrack PLC or by the Council, if Railtrack PLC so desires, with all reasonable dispatch and the Council shall not commence the construction of the specified works until the engineer has notified the Council that the protective works have been completed to his reasonable satisfaction.

4.—(1) Any specified work shall, when commenced, be constructed—

(a)with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled under paragraph 3 above;

(b)under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;

(c)in such manner as to cause as little damage as is possible to railway property; and

(d)so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Railtrack PLC or the traffic thereon and the use by passengers of railway property;

and, if any damage to railway property or any such interference or obstruction is caused or takes place in consequence of the construction of a specified work, the Council shall, notwithstanding any such approval, make good such damage and shall pay to Railtrack PLC all reasonable expenses to which Railtrack may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.

(2) Nothing in this paragraph shall impose any liability on the Council with respect to any damage, costs, expenses or loss attributable to the negligence of Railtrack or its servants, contractors or agents.

5.  The Council shall—

(a)at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and

(b)supply the engineer with all such information as he may reasonably require with regard to a specified work or the method of constructing it.

6.  Railtrack PLC shall at all times afford reasonable facilities to the Council and its agents for access to any works carried out by Railtrack PLC under this Schedule during their construction and shall supply the Council with such information as it may reasonably require with regard to such works or the method of constructing them.

7.—(1) If any alterations or additions, either permanent or temporary, to railway property are reasonably necessary during the construction of a specified work, or during a period of 12 months after the commencement of regular revenue-earning train operations using the new railways comprised in any specified work, in consequence of the construction of a specified work, and Railtrack PLC gives to the Council reasonable notice of its intention specifying the alterations or additions to be carried out, the Council shall pay to Railtrack PLC the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Railtrack in maintaining, working and, when necessary, renewing any such alterations or additions.

(2) The engineer shall, in respect of the capitalised sums referred to in this paragraph and paragraph 8(a) below, provide such details of the formula by which those sums have been calculated as the Council may reasonably require.

(3) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving shall be set off against any sum payable by the Council to Railtrack PLC under this paragraph.

8.  The Council shall repay to Railtrack PLC all reasonable fees, costs, charges and expenses reasonably incurred by Railtrack—

(a)in constructing any part of a specified work on behalf of the Council as provided by paragraph 3(3) above or in constructing any protective works under the provisions of paragraph 3(5) above including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works; and

(b)in respect of the approval by the engineer of plans submitted by the Council and the supervision by him of the construction of a specified work.

9.—(1) In this paragraph—

  • “EMI” means, subject to sub-paragraph (2) below, electromagnetic interference with Railtrack’s apparatus generated by the operation of the authorised works (including the operation of trains using the new railways comprised in the works) where such interference is of a level which adversely affects the safe operation of Railtrack’s apparatus; and

  • “Railtrack’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the works) which are owned or used by Railtrack for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.

(2) This paragraph shall apply to EMI only to the extent that such EMI is not attributable to any change to Railtrack’s apparatus carried out after approval of plans under paragraph 3(1) above for the relevant part of the authorised works giving rise to EMI (unless the Council has been given notice in writing before the approval of those plans of the intention to make such change).

(3) Subject to sub-paragraph (5) below, the Council shall in the design and construction of the authorised works take all measures necessary to prevent EMI and shall establish with Railtrack (both parties acting reasonably) appropriate arrangements to verify their effectiveness.

(4) In order to facilitate the Council’s compliance with sub-paragraph (3) above—

(a)the Council shall consult with Railtrack PLC as early as reasonably practicable to identify all Railtrack’s apparatus which may be at risk of EMI, and thereafter shall continue to consult with Railtrack PLC (both before and after formal submission of plans under paragraph 3(1) above) to identify all potential causes of EMI and the measures required to eliminate them;

(b)Railtrack PLC shall make available to the Council all information in Railtrack’s possession reasonably requested by the Council in respect of Railtrack’s apparatus identified pursuant to paragraph (a) above;

(c)Railtrack PLC shall allow the Council reasonable facilities for the inspection of Railtrack’s apparatus pursuant to paragraph (a) above.

(5) In any case where it is established that EMI can only reasonably be prevented by modifications to Railtrack’s apparatus, Railtrack shall not withhold its consent unreasonably to modifications of Railtrack’s apparatus, but the means of prevention and the method of their execution shall be selected in Railtrack PLC’s reasonable discretion and in relation to such modifications paragraph 3(1) above shall have effect subject to this sub-paragraph.

(6) If at any time prior to the commencement of regular revenue-earning train operations on the new railways comprised in the authorised works and notwithstanding any measures adopted pursuant to sub-paragraph (3) above, the testing or commissioning of the authorised works causes EMI then the Council shall immediately upon receipt of notification by Railtrack of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) the Council’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5) above) to Railtrack’s apparatus.

(7) In the event of EMI having occurred—

(a)the Council shall afford reasonable facilities to Railtrack PLC for access to the Council’s apparatus in the investigation of such EMI;

(b)Railtrack shall afford reasonable facilities to the Council for access to Railtrack’s apparatus in the investigation of such EMI; and

(c)Railtrack shall make available to the Council any additional material information in its possession reasonably requested by the Council in respect of Railtrack’s apparatus or such EMI.

(8) Where Railtrack PLC approves modifications to Railtrack’s apparatus pursuant to sub-paragraphs (5) or (6) above—

(a)Railtrack shall allow the Council reasonable facilities for the inspection of the relevant part of Railtrack’s apparatus;

(b)any modifications to Railtrack’s apparatus approved pursuant to those sub-paragraphs shall be carried out and completed by the Council in accordance with paragraph 4 above.

(9) To the extent that it would not otherwise do so, the indemnity in paragraph 13(1) below shall apply to the costs and expenses reasonably incurred or losses suffered by Railtrack through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Railtrack’s apparatus) or in consequence of any EMI to which sub-paragraph (6) above applies.

(10) For the purpose of paragraph 8(a) above any modifications to Railtrack’s apparatus under this paragraph shall be deemed to be protective works referred to in that paragraph.

(11) In relation to any dispute arising under this paragraph the reference in article 32 above to the Institution of Civil Engineers shall be read as a reference to the Institution of Electrical Engineers.

10.  If at any time after the completion of a specified work, not being a work vested in Railtrack, Railtrack PLC gives notice to the Council informing it that the state of maintenance of the specified work appears to be such as adversely affects the operation of railway property, the Council shall, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.

11.  The Council shall not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Railtrack PLC unless it shall have first consulted Railtrack PLC and it shall comply with Railtrack PLC’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.

12.  Any additional expenses which Railtrack may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work shall, provided that 56 days' previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the Council, be repaid by the Council to Railtrack PLC.

13.—(1) The Council shall pay to Railtrack PLC all reasonable costs, charges, damages and expenses not otherwise provided for in this Schedule which may be occasioned to or reasonably incurred by Railtrack—

(a)by reason of the construction or maintenance of a specified work or the failure thereof; or

(b)by reason of any act or omission of the Council or of any person in its employ or of its contractors or others whilst engaged upon a specified work;

and the Council shall indemnify Railtrack from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission; and the fact that any act or thing may have been done by Railtrack on behalf of the Council or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under his supervision shall not (if it was done without negligence on the part of Railtrack or of any person in its employ or of its contractors or agents) excuse the Council from any liability under the provisions of this sub-paragraph.

(2) Railtrack PLC shall give the Council reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand shall be made without the prior consent of the Council.

(3) The sums payable by the Council under sub-paragraph (1) above shall include a sum equivalent to the relevant costs.

(4) Subject to the terms of any agreement between Railtrack PLC and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Railtrack PLC shall promptly pay to each train operator the amount of any sums which Railtrack PLC receives under sub-paragraph (3) above which relates to the relevant costs of that train operator.

(5) The obligation under sub-paragraph (3) above to pay Railtrack PLC the relevant costs shall, in the event of default, be enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4) above.

(6) In this paragraph—

“the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any restriction of the use of Railtrack’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1) above; and

“train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.

14.  In the assessment of any sums payable to Railtrack under this Schedule there shall not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Railtrack if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the Council under this Schedule or increasing the sums so payable.

15.  The Council and Railtrack PLC may enter into, and carry into effect, agreements for the transfer to the Council of—

(a)any railway property shown on the deposited plans and described in the book of reference;

(b)any lands, works or other property held in connection with any such railway property; and

(c)any rights and obligations (whether or not statutory) of Railtrack PLC relating to any railway property.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources